GRAYSON US 82 (0045-18-046)
Items: 69
County: GRAYSON
Length: N/A
Highway: US 82
District: PARIS
Control Number: 0045-18-046
DBE Goal: N/A
Project: STP 2023(138)HES
Guaranty: N/A
Time: 319 WORKING DAYS
Engineer's Estimate: $6,383,894.76
Date: 11/02/2022 (3 years ago)
Contract Number: N/A
Type: HAZARD ELIMINATION & SAFETY
Mail/Deliver Bids To: N/A
AARON BLOOM
COLBY SHELTON
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$6,383,894.76 | |||
| $5,981,039.00 |
-6.31%
-$402,855.76
|
|||
| $6,021,544.76 |
-5.68%
-$362,350.00
|
0.68%
$40,505.76
|
||
| $6,374,309.20 |
-0.15%
-$9,585.56
|
6.58%
$393,270.20
|
-5.86%
-$352,764.44
|
|
| $6,767,447.45 |
6.01%
$383,552.69
|
13.15%
$786,408.45
|
-6.17%
-$393,138.25
|
|
| $6,994,991.02 |
9.57%
$611,096.26
|
16.95%
$1,013,952.02
|
-3.36%
-$227,543.57
|
|
| $7,929,899.25 |
24.22%
$1,546,004.49
|
32.58%
$1,948,860.25
|
-13.37%
-$934,908.23
|
|
| $9,377,954.50 |
46.9%
$2,994,059.74
|
56.79%
$3,396,915.50
|
-18.26%
-$1,448,055.25
|
E
Engineer's Estimate
$6,383,894.76
1
Awarded
$5,981,039.00
Over/Under Est:
-6.31%
-$402,855.76
$6,021,544.76
Over/Under Est:
-5.68%
-$362,350.00
Amt Left:
0.68%
$40,505.76
$6,374,309.20
Over/Under Est:
-0.15%
-$9,585.56
Amt Left:
6.58%
$393,270.20
Delta:
-5.86%
-$352,764.44
$6,767,447.45
Over/Under Est:
6.01%
$383,552.69
Amt Left:
13.15%
$786,408.45
Delta:
-6.17%
-$393,138.25
$6,994,991.02
Over/Under Est:
9.57%
$611,096.26
Amt Left:
16.95%
$1,013,952.02
Delta:
-3.36%
-$227,543.57
$7,929,899.25
Over/Under Est:
24.22%
$1,546,004.49
Amt Left:
32.58%
$1,948,860.25
Delta:
-13.37%
-$934,908.23
$9,377,954.50
Over/Under Est:
46.9%
$2,994,059.74
Amt Left:
56.79%
$3,396,915.50
Delta:
-18.26%
-$1,448,055.25
| Subcontractor | Percentage | Amount |
|---|---|---|
| BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | 85.34% | $6,349,067.45 |
| MORRIS COUNTY CONTRACTORS, L.L.C. | 8.11% | $603,362.28 |
| SAFETEX,INC. | 2.26% | $168,137.95 |
| CHEROKEE SERVICES | 1.88% | $139,866.97 |
| KING GEORGE TRAFFIC SOLUTIONS LLC | 0.65% | $48,358.26 |
| FC TRAFFIC CONTROL, INC. | 0.53% | $39,430.58 |
| CAP RIVER LLC | 0.11% | $8,183.71 |
| MOBILE ENTERPRISES, INC. | 0.00% | $0.00 |
| ROADWAY SPECIALTIES, INC. | 0.00% | $0.00 |
| LANCO TURF & SEEDING, INC. | 0.00% | $0.00 |
| JB PINNACLE GROUP, LLC | 0.00% | $0.00 |
| KING GEORGE TRAFFIC SOLUTIONS LLC | 0.00% | $0.00 |
| FC TRAFFIC CONTROL, INC. | 0.00% | $0.00 |
| Total: | 98.88% | $7,356,407.20 |