GOLIAD CR (0916-26-021)
Items: 41
County: GOLIAD
Length: N/A
Highway: CR
District: CORPUS CHRISTI
Control Number: 0916-26-021
DBE Goal: N/A
Project: BR 2022(443)
Guaranty: N/A
Time: 77 WORKING DAYS
Engineer's Estimate: $677,236.23
Date: 04/07/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (6)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$677,236.23 | |||
| $643,104.49 |
-5.04%
-$34,131.74
|
|||
| $667,708.87 |
-1.41%
-$9,527.36
|
3.83%
$24,604.38
|
||
| $759,761.20 |
12.19%
$82,524.97
|
18.14%
$116,656.71
|
-13.79%
-$92,052.33
|
|
| $777,012.60 |
14.73%
$99,776.37
|
20.82%
$133,908.11
|
-2.27%
-$17,251.40
|
|
| $842,810.76 |
24.45%
$165,574.53
|
31.05%
$199,706.27
|
-8.47%
-$65,798.16
|
|
| $900,686.00 |
32.99%
$223,449.77
|
40.05%
$257,581.51
|
-6.87%
-$57,875.24
|
E
Engineer's Estimate
$677,236.23
1
Awarded
$643,104.49
Over/Under Est:
-5.04%
-$34,131.74
$667,708.87
Over/Under Est:
-1.41%
-$9,527.36
Amt Left:
3.83%
$24,604.38
$759,761.20
Over/Under Est:
12.19%
$82,524.97
Amt Left:
18.14%
$116,656.71
Delta:
-13.79%
-$92,052.33
$777,012.60
Over/Under Est:
14.73%
$99,776.37
Amt Left:
20.82%
$133,908.11
Delta:
-2.27%
-$17,251.40
$842,810.76
Over/Under Est:
24.45%
$165,574.53
Amt Left:
31.05%
$199,706.27
Delta:
-8.47%
-$65,798.16
$900,686.00
Over/Under Est:
32.99%
$223,449.77
Amt Left:
40.05%
$257,581.51
Delta:
-6.87%
-$57,875.24
Bid Items & Bid Tabulations
41
Total
0 of 41