GARZA US 84 (0053-06-031)

Items: 77

County: GARZA
Length: N/A
Highway: US 84
District: LUBBOCK
Control Number: 0053-06-031
DBE Goal: N/A
Project: BR 2023(365)
Guaranty: N/A
Time: 175 WORKING DAYS
Engineer's Estimate: $2,242,931.40
Date: 01/06/2023 (3 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEVE SISNEROS
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$2,242,931.40
$1,791,545.60
Over/Under Est: -20.12% -$451,385.80
$2,790,830.00
Over/Under Est: 24.43% $547,898.60
Amt Left: 55.78% $999,284.40
$2,988,157.40
Over/Under Est: 33.23% $745,226.00
Amt Left: 66.79% $1,196,611.80
Delta: -7.07% -$197,327.40
$3,053,623.20
Over/Under Est: 36.14% $810,691.80
Amt Left: 70.45% $1,262,077.60
Delta: -2.19% -$65,465.80

Bid Items & Bid Tabulations

77 Total 0 of 77
GARZA  |  US 84  |  LUBBOCK  |  0053-06-031  |  01/06/2023  |  $2,242,931.40  |  BR 2023(365)  |  BRIDGE REPL  |  175 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
COPPELL CONSTRUCTION CO., INC.
DIGG COMMERCIAL, LLC
EARTH BUILDERS, L.P.
GILVIN-TERRILL, LTD.
PREP ROW (TREE)(LESS THAN 24" DIA)
EA 1.000 $1,100.000 $2,500.000 $3,000.000 $5,000.000 $5,000.000
REMOVING CONC (RIPRAP)
SY 321.000 $33.000 $70.000 $80.000 $50.000 $50.000
REMOVE CONC (RAIL)
LF 112.000 $22.000 $200.000 $100.000 $150.000 $30.000
EXCAVATION (CHANNEL)
CY 55.000 $55.000 $355.000 $200.000 $65.000 $100.000
BACKFILL (TY B)
STA 7.700 $1,100.000 $3,320.000 $3,000.000 $2,500.000 $4,500.000
BLADING
STA 7.700 $1,100.000 $300.000 $3,000.000 $400.000 $350.000
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 5,978.000 $0.550 $0.900 $2.000 $3.500 $2.000
PROOF ROLLING
HR 10.000 $275.000 $300.000 $300.000 $80.000 $150.000
EMULS ASPH (EROSN CONT)(CSS-1H)
GAL 837.000 $11.000 $10.000 $15.000 $20.000 $20.000
FOG SEAL (CSS-1H)
GAL 380.000 $11.000 $15.000 $17.000 $20.000 $20.000
ASPH (AC-20-5TR)
GAL 9,008.000 $7.700 $10.000 $10.000 $35.000 $7.500
AGGR(TY-PB GR-4 SAC-B)
CY 204.000 $220.000 $210.000 $400.000 $1,000.000 $230.000
PLANE ASPH CONC PAV (4")
SY 1,267.000 $11.000 $19.000 $12.000 $35.000 $25.000
CEM STABIL BKFL
CY 484.300 $330.000 $327.000 $400.000 $600.000 $500.000
TRENCH EXCAVATION PROTECTION
LF 184.000 $55.000 $60.000 $1.000 $1.000 $350.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 948.000 $33.000 $8.000 $1.000 $10.000 $50.000
CL C CONC (CULV)
CY 183.800 $2,200.000 $1,350.000 $2,500.000 $3,200.000 $2,000.000
CL C CONC (RAIL FOUNDATION)
CY 12.800 $1,100.000 $1,240.000 $3,000.000 $1,500.000 $2,000.000
RIPRAP (CONC)(4 IN)
CY 50.100 $880.000 $1,088.000 $1,000.000 $1,250.000 $1,700.000
RIPRAP (CONC)(5 IN)
CY 10.000 $1,100.000 $1,022.000 $1,200.000 $1,250.000 $1,700.000
RIPRAP (CONC)(CL B)
CY 22.500 $440.000 $927.000 $1,400.000 $1,250.000 $1,700.000
RAIL (TY T551)
LF 55.000 $275.000 $333.000 $250.000 $400.000 $300.000
INLET (COMPL) (DROP) (SPL)
EA 1.000 $16,500.000 $9,400.000 $20,000.000 $30,000.000 $40,000.000
WINGWALL (FW - 0) (HW=5 FT)
EA 2.000 $22,000.000 $16,000.000 $50,000.000 $50,000.000 $40,000.000
CLEAN EXIST CULVERTS
EA 2.000 $4,400.000 $2,400.000 $10,000.000 $15,000.000 $7,000.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $27,500.000 $150,000.000 $80,000.000 $70,000.000 $425,350.000
MOBILIZATION
LS 1.000 $204,000.000 $179,000.000 $756,000.000 $290,000.000 $300,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 14.000 $27,500.000 $1,800.000 $5,000.000 $4,000.000 $25,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 100.000 $55.000 $40.000 $50.000 $80.000 $45.000
ROCK FILTER DAMS (REMOVE)
LF 100.000 $27.500 $10.000 $10.000 $10.000 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 900.000 $55.000 $40.000 $50.000 $65.000 $25.000
CONSTRUCTION EXITS (REMOVE)
SY 900.000 $27.500 $10.000 $10.000 $10.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 572.000 $4.400 $5.000 $5.000 $6.000 $10.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 286.000 $2.200 $1.000 $1.000 $2.000 $5.000
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 1,248.000 $8.800 $4.000 $7.000 $11.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 624.000 $4.400 $1.000 $1.000 $2.000 $5.000
PTB (FRN&INSTL)(F SHAPE)(TY 1) OR (STL)
LF 600.000 $55.000 $90.000 $70.000 $65.000 $70.000
PTB (MOVE)(F SHAPE)(TY 1) OR (STL)
LF 600.000 $22.000 $5.000 $13.000 $30.000 $45.000
PTB (REMOVE)(F SHAPE)(TY 1) OR (STL)
LF 600.000 $16.500 $13.000 $15.000 $30.000 $45.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 600.000 $0.550 $12.000 $10.000 $15.000 $25.000
MTL W-BEAM GD FEN (STEEL POST)
LF 450.000 $55.000 $35.000 $50.000 $45.000 $35.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 2.000 $2,200.000 $1,780.000 $5,000.000 $2,000.000 $1,650.000
MTL BM GD FEN TRANS (NON - SYM)
EA 2.000 $1,650.000 $1,185.000 $2,400.000 $1,200.000 $900.000
MTL THRIE-BEAM GD FEN (STEEL POST)
EA 2.000 $2,200.000 $2,525.000 $1,000.000 $2,500.000 $2,365.000
REMOVE METAL BEAM GUARD FENCE
LF 675.000 $7.700 $2.000 $5.000 $3.000 $4.500
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $1,100.000 $237.000 $2,000.000 $400.000 $300.000
GUARDRAIL END TREATMENT (INSTALL)
EA 2.000 $4,400.000 $3,770.000 $5,000.000 $4,000.000 $4,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $1,320.000 $235.000 $1,000.000 $300.000 $300.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $3,300.000 $2,970.000 $2,000.000 $4,000.000 $1,500.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $1,650.000 $1,188.000 $1,500.000 $2,000.000 $900.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 2.000 $11,000.000 $12,329.000 $15,000.000 $14,000.000 $11,100.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 4.000 $110.000 $17.000 $100.000 $25.000 $2,000.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 22.000 $110.000 $45.000 $100.000 $50.000 $55.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 2.000 $110.000 $140.000 $160.000 $125.000 $140.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 5,080.000 $0.440 $0.750 $1.000 $0.800 $0.650
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 1,280.000 $0.440 $1.000 $1.000 $1.100 $0.860
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 5,080.000 $0.440 $0.750 $1.000 $0.800 $0.650
WK ZN PAV MRK REMOV (REFL) TY I-A
EA 1,016.000 $4.400 $4.000 $10.000 $8.000 $3.650
WK ZN PAV MRK REMOV (REFL) TY I-C
EA 1,016.000 $4.400 $4.000 $10.000 $8.000 $3.650
WK ZN PAV MRK REMOV (TRAF BTN) TY W
EA 3,048.000 $4.400 $3.000 $9.000 $4.000 $2.500
WK ZN PAV MRK REMOV (TRAF BTN) TY Y
EA 3,048.000 $4.400 $3.000 $9.000 $4.000 $2.500
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 382.000 $3.300 $3.000 $15.000 $0.700 $2.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 5,080.000 $1.100 $1.000 $1.000 $0.700 $1.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 1,280.000 $1.100 $1.000 $1.000 $0.800 $1.170
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 5,080.000 $1.100 $1.000 $1.000 $0.600 $1.000
REFL PAV MRKR TY II-C-R
EA 64.000 $5.500 $7.000 $24.000 $12.000 $6.000
ELIM EXT PAV MRK & MRKS (4")
LF 11,430.000 $2.200 $0.800 $1.000 $0.700 $0.750
FULL - WIDTH MOWING
CYC 2.000 $5,500.000 $3,000.000 $2,000.000 $3,500.000 $540.000
LITTER REMOVAL
CYC 2.000 $3,300.000 $2,300.000 $2,000.000 $4,500.000 $540.000
REINFORCED FAB FOR ASPH PVMNT OVERLAYS
SY 1,267.000 $11.000 $10.000 $26.000 $20.000 $10.000
ASPH FOR REINF FAB (PG76-28)
GAL 190.000 $11.000 $18.000 $22.000 $25.000 $20.000
TACK COAT
GAL 177.000 $11.000 $42.000 $20.000 $25.000 $10.000
D-GR HMA TY-C PG76-28 (EXEMPT)
TON 291.000 $275.000 $261.000 $400.000 $400.000 $400.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 720.000 $99.000 $35.000 $1.000 $130.000 $110.000
TMA (STATIONARY)
DAY 350.000 $220.000 $360.000 $1.000 $250.000 $380.000
TMA (MOBILE OPERATION)
DAY 24.000 $1,650.000 $475.000 $2,000.000 $700.000 $850.000
TEMP SPEED MONITOR SYS
EA 2.000 $22,000.000 $20,000.000 $30,000.000 $5,000.000 $11,000.000
Totals: $2,242,931.400 $1,791,545.600 $2,790,830.000 $2,988,157.400 $3,053,623.200