GARZA US 84 (0053-05-052)

Items: 18

County: GARZA
Length: N/A
Highway: US 84
District: LUBBOCK
Control Number: 0053-05-052
DBE Goal: N/A
Project: NH 2020(168)
Guaranty: N/A
Time: 40 WORKING DAYS
Engineer's Estimate: $3,250,059.60
Date: 11/06/2019 (6 years ago)
Contract Number: N/A
Type: SEALCOAT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$3,250,059.60
$2,699,603.95
Over/Under Est: -16.94% -$550,455.65
Over/Under Est: -5.04% -$163,798.73
Amt Left: 14.32% $386,656.92
Over/Under Est: 25.61% $832,243.52
Amt Left: 51.22% $1,382,699.17
Delta: -32.27% -$996,042.25

Bid Items & Bid Tabulations

18 Total 0 of 18
GARZA  |  US 84  |  LUBBOCK  |  0053-05-052  |  11/06/2019  |  $3,250,059.60  |  NH 2020(168)  |  SEALCOAT  |  40 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
COX PAVING OF TEXAS, INC.
BRANNAN PAVING CO., LTD.
RONALD R. WAGNER & CO., LP
ASPH (A-R TYPE II OR III)
GAL 525,284.000 $3.650 $2.750 $2.980 $4.580
AGGR(TY-PB GR-4 SAC-A)
CY 8,753.000 $110.000 $97.000 $109.050 $100.000
MOBILIZATION
LS 1.000 $155,000.000 $250,000.000 $396,500.000 $515,141.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,000.000 $5,000.000 $5,000.000 $6,400.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 14,460.000 $1.000 $0.500 $0.500 $2.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 6,505.000 $1.000 $0.500 $0.500 $2.000
REFL PAV MRK TY II (W) 4" (SLD)
LF 223,335.000 $0.150 $0.110 $0.110 $0.110
REFL PAV MRK TY II (W) 6" (BRK)
LF 56,480.000 $0.150 $0.160 $0.150 $0.150
REFL PAV MRK TY II (W) 8" (SLD)
LF 9,245.000 $0.300 $0.280 $0.220 $0.220
REFL PAV MRK TY II (Y) 4" (BRK)
LF 12,080.000 $0.150 $0.150 $0.110 $0.110
REFL PAV MRK TY II (Y) 4" (SLD)
LF 219,985.000 $0.150 $0.120 $0.110 $0.110
PREFAB PAV MRK TY C (W) (12") (SLD)
LF 1,090.000 $7.250 $7.000 $7.500 $7.500
PREFAB PAV MRK TY C (W) (24") (SLD)
LF 475.000 $15.000 $13.000 $14.000 $14.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 16.000 $300.000 $220.000 $225.000 $225.000
REFL PAV MRKR TY I-C
EA 1,040.000 $3.000 $2.800 $4.500 $4.500
REFL PAV MRKR TY II-A-A
EA 3,385.000 $3.000 $2.800 $4.500 $4.500
REFL PAV MRKR TY II-C-R
EA 2,440.000 $3.000 $2.800 $4.500 $4.500
TMA (MOBILE OPERATION)
DAY 98.000 $500.000 $200.000 $250.000 $1,043.000
Totals: $3,250,059.600 $2,699,603.950 $3,086,260.870 $4,082,303.120