GALVESTON FM 528 (1414-01-021)
Items: 12
County: GALVESTON
Length: N/A
Highway: FM 528
District: HOUSTON
Control Number: 1414-01-021
DBE Goal: N/A
Project: F 2024(141)
Guaranty: N/A
Time: 61 WORKING DAYS
Engineer's Estimate: $1,426,678.02
Date: 10/05/2023 (2 years ago)
Contract Number: N/A
Type: ADVANCED TRAFFIC MANAGEMENT SYSTEM
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (4)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,426,678.02 | |||
| $656,556.33 |
-53.98%
-$770,121.69
|
|||
| $817,549.90 |
-42.7%
-$609,128.12
|
24.52%
$160,993.57
|
||
| $909,348.65 |
-36.26%
-$517,329.37
|
38.5%
$252,792.32
|
-11.23%
-$91,798.75
|
|
| $1,062,235.04 |
-25.54%
-$364,442.98
|
61.79%
$405,678.71
|
-16.81%
-$152,886.39
|
E
Engineer's Estimate
$1,426,678.02
$656,556.33
Over/Under Est:
-53.98%
-$770,121.69
$817,549.90
Over/Under Est:
-42.7%
-$609,128.12
Amt Left:
24.52%
$160,993.57
$909,348.65
Over/Under Est:
-36.26%
-$517,329.37
Amt Left:
38.5%
$252,792.32
Delta:
-11.23%
-$91,798.75
$1,062,235.04
Over/Under Est:
-25.54%
-$364,442.98
Amt Left:
61.79%
$405,678.71
Delta:
-16.81%
-$152,886.39
| Subcontractor | Percentage | Amount |
|---|---|---|
| PATHCOM LLC | 4.27% | $30,185.39 |
| HART SERVICES LLC | 0.71% | $5,019.12 |
| Total: | 4.98% | $35,204.51 |
Bid Items & Bid Tabulations
12
Total
0 of 12