GALVESTON VA (0912-73-232)

Items: 63

County: GALVESTON
Length: N/A
Highway: VA
District: HOUSTON
Control Number: 0912-73-232
DBE Goal: 0.0%
Project: C 912-73-232
Guaranty: N/A
Time: 70 WORKING DAYS
Engineer's Estimate: $1,286,162.18
Date: 01/05/2024 (2 years ago)
Contract Number: N/A
Type: REHABILITATE BRIDGE
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$1,286,162.18
$1,093,187.76
Over/Under Est: -15% -$192,974.42
Over/Under Est: -8.34% -$107,213.80
Amt Left: 7.85% $85,760.62
Over/Under Est: -0.84% -$10,856.54
Amt Left: 16.66% $182,117.88
Delta: -8.17% -$96,357.26
$1,299,670.01
Over/Under Est: 1.05% $13,507.83
Amt Left: 18.89% $206,482.25
Delta: -1.91% -$24,364.37
Over/Under Est: 8.73% $112,344.44
Amt Left: 27.93% $305,318.86
Delta: -7.60% -$98,836.61
Over/Under Est: 17.03% $219,074.57
Amt Left: 37.69% $412,048.99
Delta: -7.63% -$106,730.13
$1,750,017.22
Over/Under Est: 36.07% $463,855.04
Amt Left: 60.08% $656,829.46
Delta: -16.26% -$244,780.47
Subcontractor Percentage Amount
HOLES INCORPORATED 1.57% $16,974.80
Total: 1.57% $16,974.80

Bid Items & Bid Tabulations

63 Total 0 of 63
GALVESTON  |  VA  |  HOUSTON  |  0912-73-232  |  01/05/2024  |  $1,286,162.18  |  C 912-73-232  |  REHAB BRIDGE  |  70 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ISI CONTRACTING, INC.
GARRET SHIELDS INFRASTRUCTURE
MB WESTERN INDUSTRIAL CONTRACTING COMPANY
TREVWAY, INC.
RAGLE CONSTRUCTION, INC.
HARPER BROTHERS CONSTRUCTION LLC
MC2 CIVIL, LLC
PREP ROW (TREE)(LESS THAN 24" DIA)
EA 5.000 $1,399.520 $850.000 $1,000.000 $1,500.000 $8,000.000 $3,000.000 $2,750.000 $3,000.000
REMOVING CONC (APPR SLAB)
SY 249.000 $20.000 $115.000 $50.000 $35.000 $250.000 $150.000 $60.000 $150.000
EXCAVATION (SPECIAL)
CY 197.000 $52.500 $48.000 $200.000 $100.000 $176.000 $36.300 $50.000 $100.000
CEM STABIL BKFL
CY 219.000 $80.000 $130.000 $150.000 $107.000 $200.000 $119.300 $155.000 $150.000
FLOWABLE BACKFILL
CY 61.000 $170.000 $652.000 $500.000 $350.000 $300.000 $403.500 $450.000 $750.000
TRENCH EXCAVATION PROTECTION
LF 5.000 $116.760 $170.000 $50.000 $250.000 $200.000 $108.300 $10.000 $50.000
APPROACH SLAB
CY 69.000 $750.000 $1,000.000 $1,000.000 $810.000 $1,087.000 $850.000 $1,000.000 $2,000.000
CONCRETE PAINT FINISH
SF 398.000 $3.000 $14.000 $100.000 $10.000 $12.790 $39.000 $39.000 $14.000
BLAST FINISH
SF 398.000 $2.250 $12.000 $4.000 $56.000 $53.880 $7.000 $7.000 $78.000
CONC STR REPR(RAPID DECK REP(FULL DPT))
SF 152.000 $370.000 $200.000 $250.000 $350.000 $300.000 $200.000 $420.000 $100.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 80.000 $525.000 $1,050.000 $300.000 $900.000 $600.000 $673.150 $1,500.000 $1,600.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 64.000 $275.500 $1,100.000 $200.000 $300.000 $600.000 $458.300 $1,000.000 $660.000
CLEANING AND SEALING EXISTING JOINTS
LF 592.000 $80.000 $56.000 $50.000 $45.000 $69.170 $29.000 $42.000 $50.000
CLEAN EXIST CULVERTS
EA 3.000 $2,000.000 $1,225.000 $5,000.000 $20,000.000 $5,987.980 $10,000.000 $2,750.000 $550.000
MOBILIZATION
LS 1.000 $127,871.000 $90,000.000 $100,000.000 $160,000.000 $130,000.000 $140,000.000 $125,900.000 $175,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $9,550.750 $6,000.000 $5,000.000 $1,556.000 $2,183.000 $46,000.000 $52,475.000 $35,000.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 540.000 $7.000 $8.000 $4.000 $7.500 $4.000 $4.500 $12.500 $12.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 540.000 $2.100 $4.000 $1.000 $5.000 $2.000 $1.000 $10.000 $1.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 1)
LF 6,611.000 $15.000 $0.500 $15.000 $20.000 $14.000 $15.000 $20.000 $40.000
PORT CTB (DES SOURCE)(LOW PROF)(TY 2)
LF 80.000 $21.400 $1.000 $20.000 $20.000 $88.000 $100.000 $20.000 $40.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 3,967.000 $20.000 $1.000 $8.000 $10.000 $10.000 $15.000 $6.000 $29.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 80.000 $13.000 $1.000 $8.000 $10.000 $60.000 $100.000 $6.000 $29.000
PORT CTB (STKPL)(LOW PROF)(TY 1)
LF 6,611.000 $12.500 $0.500 $15.000 $20.000 $14.000 $15.000 $15.000 $30.000
PORT CTB (STKPL)(LOW PROF)(TY 2)
LF 80.000 $15.500 $1.000 $15.000 $20.000 $28.000 $100.000 $15.000 $30.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
EA 34.000 $34.370 $15.500 $40.000 $41.000 $75.380 $45.000 $25.000 $40.000
INSTL DEL ASSM (D-SY)SZ (BRF)GF1
EA 4.000 $40.000 $7.500 $40.000 $41.000 $224.600 $35.000 $200.000 $40.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 38.000 $32.000 $10.000 $1.000 $14.000 $20.900 $10.000 $5.000 $10.000
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 12,246.000 $0.400 $0.470 $0.400 $0.700 $0.640 $0.350 $0.450 $0.350
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 10,632.000 $0.750 $0.480 $0.400 $0.640 $0.580 $0.400 $0.460 $0.400
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 11,767.000 $0.420 $0.470 $0.400 $0.640 $0.580 $0.350 $0.450 $0.350
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 302.000 $2.300 $1.310 $2.000 $1.980 $1.800 $2.000 $1.250 $2.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 476.000 $7.930 $6.770 $8.000 $9.620 $8.700 $8.000 $6.480 $8.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 2,563.000 $6.200 $6.770 $8.000 $8.490 $7.710 $8.000 $6.480 $8.000
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
LF 8,057.000 $2.900 $0.740 $1.600 $2.120 $1.930 $1.500 $0.710 $1.500
PAVEMENT SEALER 4"
LF 12,411.000 $0.170 $0.260 $0.280 $0.300 $0.260 $0.250 $0.250 $0.250
PAVEMENT SEALER 6"
LF 20,513.000 $0.040 $0.400 $0.400 $0.420 $0.390 $0.350 $0.380 $0.350
PAVEMENT SEALER 24"
LF 3,039.000 $1.200 $1.010 $1.000 $2.120 $1.930 $0.600 $0.970 $0.600
PAVEMENT SEALER (BIKE ARROW)
EA 5.000 $119.500 $26.130 $50.000 $12.740 $11.560 $25.000 $25.000 $25.000
PAVEMENT SEALER (BIKE SYMBOL)
EA 5.000 $126.500 $26.130 $50.000 $12.740 $11.560 $30.000 $25.000 $30.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 12,411.000 $0.900 $0.680 $1.000 $0.850 $0.770 $0.600 $0.650 $0.600
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 8,057.000 $1.500 $0.840 $1.000 $1.200 $1.090 $0.950 $0.800 $0.950
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 79.000 $0.950 $0.840 $1.000 $4.250 $3.850 $0.890 $0.800 $0.890
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 6,173.000 $1.050 $0.840 $1.000 $1.200 $1.090 $0.890 $0.800 $0.890
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 6,204.000 $1.150 $0.890 $1.000 $2.120 $1.930 $1.000 $0.850 $1.000
PREFAB PAV MRK TY C (W)(BIKE ARROW)
EA 5.000 $281.300 $261.280 $200.000 $389.000 $353.160 $195.000 $250.000 $195.000
PREFAB PAV MRK TY C (W)(BIKE SYMBOL)
EA 5.000 $280.000 $258.150 $350.000 $446.000 $404.530 $300.000 $247.000 $300.000
REFL PAV MRKR TY I-C
EA 116.000 $7.000 $6.500 $7.000 $7.080 $6.420 $6.000 $6.220 $6.000
REFL PAV MRKR TY II-A-A
EA 666.000 $8.500 $6.500 $7.000 $7.080 $6.420 $6.000 $6.220 $6.000
ELIM EXT PAV MRK & MRKS (4")
LF 12,411.000 $0.900 $0.240 $0.400 $0.420 $0.390 $0.350 $0.230 $0.350
ELIM EXT PAV MRK & MRKS (6")
LF 20,513.000 $1.050 $0.330 $0.500 $0.500 $0.450 $0.450 $0.320 $0.450
ELIM EXT PAV MRK & MRKS (8")
LF 302.000 $1.600 $0.570 $0.700 $0.850 $0.770 $0.600 $0.550 $0.600
ELIM EXT PAV MRK & MRKS (24")
LF 3,039.000 $3.650 $1.280 $2.000 $3.110 $2.830 $2.000 $1.220 $2.000
ELIM EXT PAV MRK & MARKS (BIKE ARROW)
EA 5.000 $51.500 $26.130 $40.000 $70.750 $64.210 $35.000 $25.000 $35.000
ELIM EXT PAV MRK & MARKS (BIKE SYMBOL)
EA 5.000 $50.500 $26.130 $50.000 $70.750 $64.210 $45.000 $25.000 $45.000
PAV SURF PREP FOR MRK (4")
LF 12,411.000 $0.200 $0.030 $0.050 $0.110 $0.390 $0.010 $0.030 $0.010
PAV SURF PREP FOR MRK (6")
LF 20,513.000 $0.080 $0.050 $0.050 $0.110 $1.030 $0.010 $0.050 $0.010
PAV SURF PREP FOR MRK (24")
LF 3,039.000 $1.500 $1.010 $0.600 $0.340 $0.310 $0.500 $0.970 $0.500
PAV SURF PREP FOR MRK (BIKE ARROW)
EA 5.000 $60.500 $26.130 $16.000 $7.080 $6.420 $15.000 $25.000 $15.000
PAV SURF PREP FOR MRK (BIKE SYMBOL)
EA 5.000 $65.500 $26.130 $80.000 $7.080 $6.420 $25.000 $25.000 $25.000
BRIDGE JOINT REPLACEMENT (SEJ)
LF 444.000 $600.000 $725.000 $500.000 $510.000 $273.000 $450.000 $450.000 $200.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 140.000 $197.500 $125.000 $100.000 $10.000 $200.000 $86.600 $140.000 $150.000
TMA (STATIONARY)
DAY 290.000 $315.000 $265.000 $300.000 $1.000 $269.000 $151.550 $150.000 $100.000
TMA (MOBILE OPERATION)
DAY 30.000 $300.000 $525.000 $300.000 $1.000 $600.000 $630.930 $250.000 $200.000
Totals: $1,286,162.180 $1,093,187.760 $1,178,948.380 $1,275,305.640 $1,299,670.010 $1,398,506.620 $1,505,236.750 $1,750,017.220