REMOVING STAB BASE & ASPH PAV (1.5")
|
SY
|
4,111.780
|
$2.000
|
$4.000
|
$4.500
|
$2.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
323.580
|
$10.000
|
$12.000
|
$20.000
|
$50.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY C)
|
CY
|
167.000
|
$30.000
|
$24.000
|
$17.500
|
$80.000
|
|
|
EMBANKMENT (FINAL)(DENS CONT)(TY D)
|
CY
|
24,650.000
|
$45.000
|
$6.000
|
$17.000
|
$24.000
|
|
|
BACKFILL TY A
|
CY
|
1,682.000
|
$50.000
|
$28.000
|
$75.000
|
$110.000
|
|
|
BLADING
|
HR
|
433.780
|
$80.000
|
$110.000
|
$95.000
|
$90.000
|
|
|
BLOCK SODDING
|
SY
|
131,910.000
|
$3.000
|
$3.000
|
$3.250
|
$3.000
|
|
|
STRAW OR HAY MULCH
|
SY
|
131,910.000
|
$0.200
|
$0.140
|
$0.150
|
$0.160
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
131,910.000
|
$0.150
|
$0.150
|
$0.130
|
$0.190
|
|
|
FERTILIZER
|
AC
|
54.900
|
$650.000
|
$710.000
|
$775.000
|
$625.000
|
|
|
VEGETATIVE WATERING
|
MG
|
6,541.000
|
$20.000
|
$14.000
|
$8.000
|
$25.000
|
|
|
LIME TRT (EXST MATL) (6")
|
SY
|
8,737.000
|
$2.500
|
$3.000
|
$4.000
|
$15.000
|
|
|
LIME (HYD, COM, OR QK(SLURRY))
|
TON
|
118.000
|
$160.000
|
$170.000
|
$175.000
|
$200.000
|
|
|
CEM TRT(PLNT MX) (CL N)(TY E)(GR 4)(6")
|
SY
|
8,737.000
|
$18.000
|
$14.000
|
$18.000
|
$38.000
|
|
|
ASPHALT STAB BASE (GR 2)(PG 64)
|
TON
|
225,163.600
|
$40.000
|
$60.000
|
$67.000
|
$80.000
|
|
|
D-GR HMA TY-D SAC-A PG70-22
|
TON
|
17,297.530
|
$80.000
|
$77.000
|
$84.000
|
$92.000
|
|
|
D-GR HMA TY-D SAC-B PG70-22
|
TON
|
917.600
|
$75.000
|
$105.000
|
$100.000
|
$160.000
|
|
|
PLANE ASPH CONC PAV (0" TO 1 1/2")
|
SY
|
1,226.000
|
$8.000
|
$3.600
|
$6.000
|
$8.000
|
|
|
STRUCT EXCAV (BOX)
|
CY
|
128.470
|
$15.000
|
$25.500
|
$60.000
|
$100.000
|
|
|
STRUCT EXCAV (PIPE)
|
CY
|
4.990
|
$10.000
|
$225.000
|
$60.000
|
$100.000
|
|
|
CEM STABIL BKFL
|
CY
|
83.000
|
$50.000
|
$122.000
|
$95.000
|
$150.000
|
|
|
RIPRAP (CONC)(4 IN)
|
CY
|
8.870
|
$250.000
|
$560.000
|
$850.000
|
$1,500.000
|
|
|
RIPRAP (STONE PROTECTION)(30 IN)
|
CY
|
13,933.000
|
$154.000
|
$125.000
|
$150.000
|
$230.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
2.080
|
$500.000
|
$660.000
|
$1,150.000
|
$2,400.000
|
|
|
BEDDING MATERIAL (VARIABLE)
|
CY
|
5,313.000
|
$121.000
|
$93.000
|
$115.000
|
$130.000
|
|
|
CONC BOX CULV (10 FT X 3 FT)(EXTEND)
|
LF
|
37.500
|
$450.000
|
$1,220.000
|
$1,250.000
|
$3,000.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
87.000
|
$125.000
|
$122.000
|
$170.000
|
$170.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 24 IN)
|
EA
|
3.000
|
$3,000.000
|
$4,050.000
|
$6,000.000
|
$6,500.000
|
|
|
WINGWALL (PW - 1) (HW=6 FT)
|
EA
|
2.000
|
$16,000.000
|
$10,100.000
|
$10,500.000
|
$22,000.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,351,210.750
|
$1,145,000.000
|
$1,450,000.000
|
$1,000,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
14.000
|
$5,000.000
|
$3,200.000
|
$2,650.000
|
$5,500.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
684.000
|
$20.000
|
$33.000
|
$40.000
|
$60.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
684.000
|
$10.000
|
$7.100
|
$10.000
|
$32.000
|
|
|
CONSTRUCTION EXITS (INSTALL) (TY 1)
|
SY
|
900.000
|
$30.000
|
$35.000
|
$40.000
|
$38.000
|
|
|
CONSTRUCTION EXITS (REMOVE)
|
SY
|
900.000
|
$10.000
|
$8.100
|
$10.000
|
$18.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
8,250.000
|
$5.000
|
$2.700
|
$2.000
|
$2.500
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
8,250.000
|
$1.000
|
$1.000
|
$0.750
|
$0.850
|
|
|
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
|
LF
|
2,920.000
|
$35.000
|
$27.000
|
$50.000
|
$75.000
|
|
|
DRIVEWAYS (BASE)
|
SY
|
11,122.200
|
$40.000
|
$51.000
|
$44.000
|
$25.000
|
|
|
RUMBLE STRIPS (SHOULDER)
|
LF
|
75,804.000
|
$0.350
|
$0.480
|
$0.200
|
$0.300
|
|
|
MTL W-BEAM GD FEN (TIM POST)
|
LF
|
1,619.000
|
$19.000
|
$21.000
|
$27.000
|
$35.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
2,120.000
|
$3.500
|
$2.500
|
$2.500
|
$25.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
4.000
|
$2,300.000
|
$2,140.000
|
$3,000.000
|
$2,500.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
68.000
|
$427.000
|
$330.000
|
$500.000
|
$470.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(P)
|
EA
|
2.000
|
$450.000
|
$560.000
|
$700.000
|
$750.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
1.000
|
$675.000
|
$640.000
|
$900.000
|
$875.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
1.000
|
$775.000
|
$620.000
|
$900.000
|
$875.000
|
|
|
RELOCATE SM RD SN SUP&AM TY 10BWG
|
EA
|
36.000
|
$460.000
|
$300.000
|
$500.000
|
$475.000
|
|
|
RELOCATE SM RD SN SUP&AM TY S80
|
EA
|
1.000
|
$535.000
|
$400.000
|
$600.000
|
$750.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
34.000
|
$92.000
|
$76.000
|
$90.000
|
$100.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
6.000
|
$60.000
|
$45.000
|
$60.000
|
$70.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
65.000
|
$27.000
|
$27.000
|
$40.000
|
$30.000
|
|
|
WK ZN PAV MRK REMOV (W)4"(SLD)
|
LF
|
338,108.000
|
$0.650
|
$0.440
|
$0.500
|
$0.350
|
|
|
WK ZN PAV MRK REMOV (Y)4"(SLD)
|
LF
|
329,842.000
|
$0.650
|
$0.440
|
$0.500
|
$0.350
|
|
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
|
LF
|
1,005.000
|
$1.500
|
$1.000
|
$1.100
|
$0.850
|
|
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
|
LF
|
630.000
|
$6.000
|
$6.100
|
$6.750
|
$5.000
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
|
LF
|
81,250.000
|
$0.430
|
$0.430
|
$0.450
|
$0.600
|
|
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
|
LF
|
13,270.000
|
$0.500
|
$0.420
|
$0.450
|
$0.650
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
|
LF
|
34,440.000
|
$0.430
|
$0.420
|
$0.450
|
$0.600
|
|
PREFAB PAV MRK TY C (W) (ARROW)
|
EA
|
142.000
|
$226.000
|
$86.000
|
$95.000
|
$265.000
|
|
PREFAB PAV MRK TY C (W) (WORD)
|
EA
|
8.000
|
$286.000
|
$91.000
|
$100.000
|
$300.000
|
|
REFL PAV MRKR TY I-C
|
EA
|
37.000
|
$5.520
|
$3.050
|
$3.500
|
$5.000
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,233.000
|
$5.720
|
$3.550
|
$4.000
|
$5.000
|
|
|
ELIM EXT PAV MRK & MRKS (4")
|
LF
|
37,363.000
|
$0.500
|
$0.160
|
$0.180
|
$0.150
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
128,960.000
|
$0.060
|
$0.020
|
$0.020
|
$0.030
|
|
|
PAV SURF PREP FOR MRK (8")
|
LF
|
1,005.000
|
$0.080
|
$0.040
|
$0.040
|
$0.050
|
|
|
PAV SURF PREP FOR MRK (24")
|
LF
|
630.000
|
$0.240
|
$10.200
|
$11.000
|
$0.150
|
|
|
PAV SURF PREP FOR MRK (ARROW)
|
EA
|
142.000
|
$5.280
|
$10.200
|
$11.000
|
$10.000
|
|
|
PAV SURF PREP FOR MRK (WORD)
|
EA
|
8.000
|
$9.880
|
$12.200
|
$13.500
|
$10.000
|
|
|
FULL - WIDTH MOWING
|
CYC
|
3.000
|
$3,000.000
|
$2,200.000
|
$3,000.000
|
$10,000.000
|
|
|
LITTER REMOVAL
|
CYC
|
3.000
|
$250.000
|
$2,150.000
|
$2,000.000
|
$6,800.000
|
|
|
DEBRIS REMOVAL (CNTR MEDIANS/MAINLANES)
|
CYC
|
3.000
|
$250.000
|
$2,900.000
|
$3,000.000
|
$6,500.000
|
|
|
CLEANING / SWEEPING (CENTER MEDIAN)
|
CYC
|
3.000
|
$500.000
|
$2,100.000
|
$3,000.000
|
$5,500.000
|
|
|
GEOGRID BASE REINFORCEMENT (TY II)
|
SY
|
687.200
|
$36.000
|
$9.000
|
$4.500
|
$25.000
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
2.000
|
$9,000.000
|
$10,200.000
|
$25,000.000
|
$16,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
240.000
|
$200.000
|
$80.000
|
$500.000
|
$800.000
|
|
|
TMA (MOBILE OPERATION)
|
HR
|
100.000
|
$40.000
|
$100.000
|
$50.000
|
$100.000
|
|
Totals: |
$18,260,225.160
|
$20,817,021.425
|
$23,861,303.570
|
$28,498,228.470
|