GALVESTON SH 6 (0192-04-111)

Items: 14

County: GALVESTON
Length: 0.0000 MILES
Highway: SH 6
District: HOUSTON
Control Number: 0192-04-111
DBE Goal: 0.0%
Project: STP 2B24(534)HES
Guaranty: $100,000.00
Time: 518 WORKING DAYS
Engineer's Estimate: $9,795,444.50
Date: 01/08/2025 (1 year ago)
Contract Number: 1253209
Type: HAZARD ELIMINATION & SAFETY
Project ID: A00186881
Contract Type: Federal
Project Description: SIGNAL INTERCONNECT - FIBER INSTALLATION
Mail/Deliver Bids To: N/A
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$9,795,444.50
1
Awarded
$9,176,024.54
Over/Under Est: -6.32% -$619,419.96
Over/Under Est: -5.78% -$565,752.70
Amt Left: 0.58% $53,667.26
Over/Under Est: -0.04% -$3,444.50
Amt Left: 6.71% $615,975.46
Delta: -6.09% -$562,308.20
Over/Under Est: 9.21% $902,349.76
Amt Left: 16.58% $1,521,769.72
Delta: -9.25% -$905,794.26
$13,549,172.61
Over/Under Est: 38.32% $3,753,728.11
Amt Left: 47.66% $4,373,148.07
Delta: -26.65% -$2,851,378.35
Subcontractor Percentage Amount
ROSAS COMPANY SERVICES INC 21.56% $1,978,350.89
ALTUS CONSTRUCTION LLC 0.44% $40,374.51
Total: 22.00% $2,018,725.40

Bid Items & Bid Tabulations

14 Total 0 of 14
GALVESTON  |  SH 6  |  HOUSTON  |  0192-04-111  |  01/08/2025  |  $9,795,444.50  |  STP 2B24(534)HES  |  HAZARD ELIM & SAFETY  |  518 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SICE, INC.
ALLSTATE SIGNAL & CONSTRUCTION, LLC
FLORIDA TRAFFIC CONTROL DEVICES, INC.
THIRD COAST SERVICES LLC
TRAF-TEX, INC.
MOBILIZATION
LS 1.000 $64,214.150 $875,933.684 $102,000.000 $500,015.500 $1,069,779.420 $1,285,658.460
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 35.000 $2,000.000 $4,253.664 $1,732.000 $3,775.000 $2,961.250 $812.250
CONDT (PVC) (SCH 80) (2") (BORE)
LF 77,800.000 $16.780 $11.835 $15.930 $15.700 $17.450 $25.550
CONDT (PVC) (SCH 80) (2") (CONC ENCSE)
LF 106,330.000 $9.350 $16.291 $24.180 $26.000 $21.740 $18.820
CONDT (PVC) (SCH 80) (4") (BORE)
LF 51,265.000 $42.840 $25.944 $19.050 $17.500 $30.260 $86.700
CONDT (PVC) (SCH 80) (4") (CONC ENCSE)
LF 72,170.000 $35.420 $18.391 $18.400 $24.750 $23.320 $13.260
CONDT (RM) (2")
LF 7,520.000 $41.600 $86.641 $48.810 $24.500 $47.470 $90.600
ELEC CONDR (NO.14) INSULATED
LF 191,620.000 $1.100 $0.839 $1.160 $1.050 $0.740 $0.850
ITS GND BOX(PCAST) TY 1 (243636)W/APRN
EA 360.000 $4,518.000 $3,651.247 $4,225.000 $4,330.000 $4,543.080 $4,410.000
FIBER OPTIC CBL (SINGLE-MODE)(12 FIBER)
LF 3,860.000 $4.350 $2.909 $2.850 $1.700 $1.480 $1.910
FIBER OPTIC CBL (SINGLE-MODE)(36 FIBER)
LF 200,575.000 $1.750 $2.864 $3.730 $2.100 $1.850 $1.540
FO SPLICE ENCLOSURE (TYPE 2)
EA 24.000 $1,552.000 $1,436.421 $766.380 $2,215.000 $1,205.480 $1,480.000
FIBER OPTIC FUSION SPLICE
EA 276.000 $93.100 $160.008 $137.800 $66.000 $225.480 $57.000
FIBER OPTIC PATCH PANEL (12 POSITION)
EA 24.000 $1,178.000 $2,077.487 $1,092.920 $1,962.000 $776.710 $1,884.000
Totals: $9,795,444.500 $9,176,024.544 $9,229,691.800 $9,792,000.000 $10,697,794.260 $13,549,172.610