FRIO CR (0915-18-033)

Items: 47

County: FRIO
Length: N/A
Highway: CR
District: SAN ANTONIO
Control Number: 0915-18-033
DBE Goal: N/A
Project: BR 2021(141)
Guaranty: N/A
Time: 102 WORKING DAYS
Engineer's Estimate: $512,793.21
Date: 02/03/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (6)
E
Engineer's Estimate
$512,793.21
$525,525.25
Over/Under Est: 2.48% $12,732.04
$573,667.02
Over/Under Est: 11.87% $60,873.81
Amt Left: 9.16% $48,141.77
Over/Under Est: 15.48% $79,391.14
Amt Left: 12.68% $66,659.10
Delta: -3.23% -$18,517.33
Over/Under Est: 15.82% $81,146.48
Amt Left: 13.02% $68,414.44
Delta: -0.30% -$1,755.34
Over/Under Est: 21.4% $109,733.29
Amt Left: 18.46% $97,001.25
Delta: -4.81% -$28,586.81
Over/Under Est: 30.32% $155,497.43
Amt Left: 27.17% $142,765.39
Delta: -7.35% -$45,764.14

Bid Items & Bid Tabulations

47 Total 0 of 47
FRIO  |  CR  |  SAN ANTONIO  |  0915-18-033  |  02/03/2022  |  $512,793.21  |  BR 2021(141)  |  BRIDGE REPL  |  102 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DELGADO'S CONTRACTORS, LLC
SB CONTRACTORS LLC
HILL COUNTRY BRIDGE, INC.
ACME BRIDGE COMPANY, INC.
LUCANIA CONSTRUCTION LLC
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
PREPARING ROW
STA 3.800 $3,105.000 $3,000.000 $2,500.000 $4,595.000 $4,910.000 $1,500.000 $1,753.490
PREP ROW (TREE)(LESS THAN 24" DIA)
EA 9.000 $115.000 $500.000 $525.130 $1,625.000 $994.000 $800.000 $1,253.700
REMOVING STAB BASE AND ASPH PAV (6")
SY 739.000 $6.900 $10.000 $5.600 $5.400 $3.050 $13.000 $12.010
EXCAVATION (ROADWAY)
CY 50.000 $28.750 $10.000 $56.590 $59.500 $58.400 $35.000 $75.640
EXCAVATION (CHANNEL)
CY 405.000 $17.250 $10.000 $16.650 $21.650 $22.200 $30.000 $43.760
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 124.000 $46.000 $30.000 $25.020 $32.450 $25.200 $30.000 $44.040
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 824.000 $3.450 $1.000 $0.850 $1.350 $1.600 $2.000 $2.210
CELL FBR MLCH SEED(TEMP)(WARM)
SY 413.000 $4.600 $1.000 $3.340 $2.500 $1.600 $2.750 $0.620
CELL FBR MLCH SEED(TEMP)(COOL)
SY 413.000 $4.600 $1.000 $3.340 $2.500 $1.600 $2.750 $0.620
VEGETATIVE WATERING
MG 12.900 $57.500 $60.000 $45.370 $145.000 $98.600 $50.000 $73.340
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 824.000 $4.030 $4.000 $2.550 $1.350 $2.550 $4.000 $1.770
PROOF ROLLING
HR 2.000 $115.000 $150.050 $118.540 $250.000 $68.000 $80.000 $73.180
PRIME COAT (EC-30)
GAL 140.000 $5.750 $8.000 $10.210 $9.500 $10.600 $11.000 $15.160
CEM STABIL BKFL
CY 72.000 $172.500 $150.000 $139.140 $173.350 $214.000 $180.000 $123.370
DRILL SHAFT (24 IN)
LF 315.000 $172.500 $225.000 $222.080 $192.800 $181.000 $195.000 $223.180
CL C CONC (ABUT)
CY 18.400 $1,150.000 $1,080.550 $1,166.100 $1,184.000 $1,200.000 $1,800.000 $1,736.800
CL C CONC (CAP)
CY 6.600 $1,121.250 $1,200.000 $2,273.240 $1,370.000 $1,750.000 $2,600.000 $1,896.270
CL C CONC (COLUMN)
CY 1.100 $1,380.000 $1,200.000 $2,923.850 $2,025.000 $3,270.000 $2,600.000 $4,673.270
REINF CONC SLAB (SLAB BEAM)
SF 2,080.000 $23.000 $22.500 $24.190 $20.400 $21.500 $30.000 $25.220
APPROACH SLAB
CY 39.000 $460.000 $700.000 $572.590 $677.000 $697.000 $800.000 $722.520
PRESTR CONC SLAB BEAM (5SB15)
LF 395.000 $195.500 $235.000 $232.710 $215.800 $290.000 $240.000 $221.890
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 132.000 $287.500 $220.000 $226.190 $145.000 $171.000 $200.000 $214.040
RIPRAP (MOW STRIP)(4 IN)
CY 30.000 $460.000 $465.000 $401.790 $480.000 $718.000 $500.000 $613.430
RAIL (TY T223)
LF 184.000 $103.500 $115.000 $123.040 $119.450 $137.000 $180.000 $204.270
ARMOR JOINT (SEALED)
LF 44.000 $126.500 $110.000 $154.430 $118.200 $156.000 $200.000 $140.450
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $18,400.000 $20,000.000 $18,183.610 $29,000.000 $11,200.000 $24,000.000 $19,028.080
MOBILIZATION
LS 1.000 $47,917.340 $35,850.000 $57,800.000 $59,000.000 $46,000.000 $42,000.000 $115,194.630
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $2,875.000 $1,499.990 $1,500.000 $2,500.000 $1,770.000 $1,450.000 $967.490
TEMP SEDMT CONT FENCE (INSTALL)
LF 620.000 $4.600 $3.750 $5.110 $7.500 $3.750 $5.500 $3.180
TEMP SEDMT CONT FENCE (REMOVE)
LF 620.000 $1.150 $0.500 $1.130 $1.550 $2.150 $2.250 $1.260
BIODEG EROSN CONT LOGS (INSTL) (18")
LF 106.000 $5.750 $7.000 $11.280 $11.200 $9.600 $11.500 $10.830
BIODEG EROSN CONT LOGS (REMOVE)
LF 106.000 $1.150 $0.500 $1.700 $4.500 $3.200 $5.750 $3.130
MTL W-BEAM GD FEN (STEEL POST)
LF 100.000 $46.580 $40.000 $45.370 $50.000 $54.500 $70.000 $50.490
MTL BEAM GD FEN TRANS (TL2)
EA 4.000 $1,495.000 $1,750.000 $2,268.670 $1,570.000 $1,720.000 $1,400.000 $1,784.690
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,990.000 $3,500.000 $3,176.130 $4,150.000 $4,540.000 $3,500.000 $3,544.690
WIRE FENCE (TY B)
LF 128.000 $17.250 $20.000 $22.690 $57.350 $23.700 $25.000 $17.270
WIRE FENCE (TY C)
LF 80.000 $34.500 $20.000 $17.010 $43.300 $30.000 $40.000 $23.230
REMOVE SM RD SN SUP&AM
EA 3.000 $115.000 $100.000 $113.430 $190.000 $77.000 $120.000 $114.370
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 6.000 $34.500 $25.000 $28.360 $27.000 $29.600 $22.000 $70.370
REMOVE DELIN & OBJECT MARKER ASSMS
EA 2.000 $28.750 $20.000 $11.350 $100.000 $29.600 $28.000 $37.370
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $34.500 $30.000 $17.010 $54.000 $59.300 $30.000 $70.370
REFL PAV MRK TY II (W) 4" (SLD)
LF 760.000 $2.300 $4.000 $3.400 $3.250 $3.200 $3.500 $3.320
REFL PAV MRK TY II (Y) 4" (SLD)
LF 760.000 $2.300 $4.000 $3.400 $3.250 $3.200 $3.500 $3.320
REFL PAV MRKR TY II-A-A
EA 10.000 $11.500 $100.000 $22.690 $21.650 $21.300 $23.500 $11.110
TACK COAT
GAL 70.000 $3.000 $6.330 $3.170 $3.000 $3.300 $3.250 $21.310
D-GR HMA TY-C SAC-B PG70-22 (EXEMPT)
TON 230.000 $126.500 $140.000 $215.520 $225.000 $225.000 $220.000 $148.910
INSTALL BRIDGE IDENTIFICATION NUMBERS
EA 2.000 $275.000 $300.000 $510.450 $565.000 $180.000 $260.000 $874.370
Totals: $512,793.210 $525,525.250 $573,667.032 $592,184.350 $593,939.690 $622,526.500 $668,290.657