FREESTONE IH0045 (6493-38-001)

Items: 44

County: FREESTONE
Length: 0.0100 MILES
Highway: IH0045
District: BRYAN
Control Number: 6493-38-001
DBE Goal: 0.0%
Project: RMC - A00218314
Guaranty: $8,000.00
Time: 365 CALENDAR DAYS
Engineer's Estimate: $389,575.00
Date: 12/09/2025 (6 months ago)
Contract Number: 12251703
Type: METAL BEAM GUARD FENCE REPAIR
Project ID: A00218314
Project Description: METAL BEAM GUARD FENCE REPAIR FOR LOCATIONS IN FREESTONE AND LEON COUNTIES.
Mail/Deliver Bids To: N/A
MICHAEL ESTILLETTE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$389,575.00
$296,311.00
Over/Under Est: -23.94% -$93,264.00
$299,615.00
Over/Under Est: -23.09% -$89,960.00
Amt Left: 1.12% $3,304.00
Over/Under Est: -10.57% -$41,180.00
Amt Left: 17.58% $52,084.00
Delta: -16.28% -$48,780.00
Over/Under Est: -9.58% -$37,335.00
Amt Left: 18.88% $55,929.00
Delta: -1.10% -$3,845.00

Bid Items & Bid Tabulations

44 Total 0 of 44
FREESTONE  |  IH0045  |  BRYAN  |  6493-38-001  |  12/09/2025  |  $389,575.00  |  RMC - A00218314  |  METAL BEAM GUARD FENCE REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
T&L CLEANING SERVICES LLC
RHINO EQUITY, LLC
ABOVE ALL CONTRACTING LLC
BK FIELD OPERATIONS LLC
RIPRAP (MOW STRIP)(4 IN)
CY 10.000 $700.000 $300.000 $100.000 $600.000 $1.000
MOBILIZATION (CALLOUT)
EA 20.000 $1,000.000 $1.000 $100.000 $1.000 $1.000
TMA (STATIONARY)
DAY 50.000 $500.000 $1,000.000 $1,200.000 $200.000 $5,000.000
MTL W-BEAM GD FEN (TIM POST)
LF 500.000 $35.000 $36.000 $35.000 $35.000 $14.000
MTL W-BEAM GD FEN (STEEL POST)
LF 200.000 $40.000 $1.000 $20.000 $50.000 $15.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 5.000 $2,200.000 $1,000.000 $750.000 $3,000.000 $350.000
MTL W-BEAM GD FEN ADJUSTMENT
LF 25.000 $20.000 $1.000 $1.000 $20.000 $1.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 5.000 $1,700.000 $1,200.000 $1.000 $1,900.000 $1.000
REMOVE METAL BEAM GUARD FENCE
LF 500.000 $6.000 $0.010 $1.000 $5.000 $1.000
REMOVE TERMINAL ANCHOR SECTION
EA 5.000 $300.000 $1.000 $1.000 $200.000 $1.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 5.000 $260.000 $1.000 $1.000 $200.000 $1.000
GUARDRAIL END TREATMENT (INSTALL)
EA 5.000 $3,400.000 $3,000.000 $3,200.000 $3,100.000 $2,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 5.000 $470.000 $1.000 $1.000 $500.000 $1.000
REPLACE RAIL ELEMENT (W-BEAM)
LF 1,500.000 $25.000 $24.000 $30.000 $28.000 $8.000
REPLACE RAIL ELEMENT (THRIE-BEAM)
LF 50.000 $50.000 $20.000 $10.000 $55.000 $1.000
REPL RAIL ELMNT(THRIE-BM TRANS TO W-BM)
EA 20.000 $80.000 $1.000 $100.000 $400.000 $1.000
REPLACE TIMBER POST W/O CONC FND
EA 100.000 $60.000 $1.000 $50.000 $50.000 $1.000
REPLACE STEEL POST W/O CONC FND
EA 25.000 $80.000 $1.000 $75.000 $75.000 $1.000
REPLACE TIMBER POST W/ CONC FND
EA 50.000 $85.000 $1.000 $100.000 $50.000 $20.000
REPLACE STEEL POST W/ CONC FND
EA 10.000 $95.000 $1.000 $1.000 $75.000 $1.000
REALIGN POSTS
EA 100.000 $35.000 $1.000 $1.000 $50.000 $1.000
REM OBSOLETE GET & REPL W/ SGT
EA 25.000 $4,400.000 $4,000.000 $3,200.000 $3,200.000 $2,000.000
REPL SINGLE GDRAIL TERM IMPACT HEAD
EA 5.000 $1,000.000 $1,000.000 $750.000 $900.000 $150.000
REPLACE SINGLE GDRAIL TERMINAL RAIL
LF 500.000 $50.000 $50.000 $20.000 $35.000 $12.000
REPLACE SINGLE GDRAIL TERMINAL POST
EA 10.000 $150.000 $100.000 $50.000 $100.000 $20.000
REPLACE BLOCKOUT
EA 100.000 $40.000 $1.000 $50.000 $50.000 $1.000
REPAIR STEEL POST WITH BASE PLATE
EA 5.000 $150.000 $200.000 $100.000 $300.000 $1.000
RESET SGT IMPACT HEAD
EA 5.000 $240.000 $50.000 $1.000 $100.000 $1.000
REPLACE SGT OBJECT MARKER
EA 5.000 $20.000 $30.000 $1.000 $30.000 $1.000
REPLACE SGT CABLE ANCHOR
EA 5.000 $20.000 $1.000 $1.000 $100.000 $1.000
REPLACE SGT CABLE ASSEMBLY
EA 5.000 $40.000 $1.000 $1.000 $100.000 $1.000
REPLACE SGT STRUT
EA 5.000 $70.000 $1.000 $1.000 $100.000 $1.000
RAISE RAIL
LF 100.000 $10.000 $1.000 $1.000 $10.000 $1.000
REPLACE DOWNSTREAM ANCHOR TERMINAL
EA 5.000 $1,000.000 $1,200.000 $1,000.000 $1,900.000 $200.000
REPAIR RAIL ELEMENT (CURVED RAIL)
LF 20.000 $35.000 $50.000 $30.000 $80.000 $10.000
REPLACE POSTS (TL-4)(GIBRALTAR)
EA 50.000 $190.000 $150.000 $180.000 $180.000 $40.000
REPLACE POSTS (TL-4)(NU-CABLE)
EA 50.000 $190.000 $1.000 $1.000 $150.000 $1.000
REPLACE POSTS (TL-4)(TRINITY)
EA 50.000 $190.000 $180.000 $250.000 $200.000 $40.000
CABLE SPLICE / TURNBUCKLE (TL-4)
EA 5.000 $95.000 $100.000 $1.000 $250.000 $1.000
REPAIR CONCRETE FOUNDATION (TL-4)
EA 5.000 $130.000 $1.000 $1.000 $700.000 $1.000
REPR OR REPLC CABLE BARR TERM SEC(TL-4)
EA 10.000 $1,500.000 $500.000 $800.000 $2,800.000 $400.000
REPLACE CABLE (TL-4)
LF 100.000 $10.000 $0.010 $0.500 $10.000 $1.000
CHECK / RE-TENSION CABLE (TL-4)
EA 20.000 $230.000 $1.000 $10.000 $150.000 $1.000
REPLACE POST HARDWARE (TL-4)
EA 50.000 $70.000 $1.000 $1.000 $50.000 $1.000
Totals: $389,575.000 $296,311.000 $299,615.000 $348,395.000 $352,240.000