Show Job Controls
Bid Cobra

FREESTONE IH0045 (6479-82-001)

Items: 20

County: FREESTONE
Length: 0.0100 MILES
Highway: IH0045
District: BRYAN
Control Number: 6479-82-001
DBE Goal: N/A
Project: BPM - A00213949
Guaranty: $15,000.00
Time: 50 WORKING DAYS
Engineer's Estimate: $747,777.38
Date: 05/06/2025 (1 year ago)
Contract Number: 5251704
Type: BRIDGE REPAIR
Project ID: A00213949
Project Description: BRIDGE PREVENTATIVE MAINTENANCE FOR LOCATIONS IN FREESTONE COUNTY.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: MAINTENANCE CONTRACT OFFICE
2591 NORTH EARL RUDDER FRWY, BRYAN, TX 77803
DELMY REYES
MATT HENSARLING
MICHAEL ESTILLETTE
MATTHEW DAWSONMATHUR
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (12)
E
Engineer's Estimate
$747,777.38
$422,313.00
Over/Under Est: -43.52% -$325,464.38
Over/Under Est: -37.51% -$280,456.38
Amt Left: 10.66% $45,008.00
Over/Under Est: -35.62% -$266,379.38
Amt Left: 13.99% $59,085.00
Delta: -3.01% -$14,077.00
Over/Under Est: -25.12% -$187,871.38
Amt Left: 32.58% $137,593.00
Delta: -16.31% -$78,508.00
Over/Under Est: -24.14% -$180,521.88
Amt Left: 34.32% $144,942.50
Delta: -1.31% -$7,349.50
Over/Under Est: -22.95% -$171,633.08
Amt Left: 36.43% $153,831.30
Delta: -1.57% -$8,888.80
Over/Under Est: -20.94% -$156,618.98
Amt Left: 39.98% $168,845.40
Delta: -2.61% -$15,014.10
Over/Under Est: -17.35% -$129,768.38
Amt Left: 46.34% $195,696.00
Delta: -4.54% -$26,850.60
$625,559.70
Over/Under Est: -16.34% -$122,217.68
Amt Left: 48.13% $203,246.70
Delta: -1.22% -$7,550.70
Over/Under Est: -12.06% -$90,164.88
Amt Left: 55.72% $235,299.50
Delta: -5.12% -$32,052.80
$683,383.50
Over/Under Est: -8.61% -$64,393.88
Amt Left: 61.82% $261,070.50
Delta: -3.92% -$25,771.00
$769,052.00
Over/Under Est: 2.85% $21,274.62
Amt Left: 82.1% $346,739.00
Delta: -12.54% -$85,668.50
Subcontractor Percentage Amount
W-TEX SERVICES LLC 0.00% $0.00
Total: 0.00% $0.00

Bid Items & Bid Tabulations

20 Total 0 of 20
FREESTONE  |  IH0045  |  BRYAN  |  6479-82-001  |  05/06/2025  |  $747,777.38  |  BPM - A00213949  |  BRIDGE REPAIR  |  50 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BK FIELD OPERATIONS LLC
GARRET SHIELDS INFRASTRUCTURE
BECK-REIT & SONS, LTD.
ROY JORGENSEN ASSOCIATES, INC.
PREMIER CONTRACTORS LLC
CROSS PLUS CONSTRUCTION, LLC
STRUCTURAL INTEGRITY GROUP LLC
BLACKSMITH VENTURES LLC
RHINO EQUITY, LLC
PATHFIELD INVESTMENTS LLC
ICOS MANAGEMENT, LLC
IBCTX, LLC
FLOWABLE BACKFILL
CY 13.400 $672.560 $500.000 $500.000 $400.000 $500.000 $400.000 $450.000 $675.000 $1,000.000 $1,000.000 $800.000 $550.000 $900.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 63.800 $278.660 $150.000 $200.000 $220.000 $250.000 $400.000 $181.000 $500.000 $200.000 $160.000 $300.000 $220.000 $400.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 1,285.000 $315.270 $160.000 $200.000 $200.000 $200.000 $230.000 $225.000 $257.000 $220.000 $220.000 $280.000 $220.000 $250.000
STR STEEL (MISC NON-BRIDGE)
LB 245.900 $23.790 $60.000 $40.000 $30.000 $80.000 $45.000 $25.000 $81.000 $60.000 $13.000 $325.000 $25.000 $80.000
CLEAN EXIST CULVERTS
EA 2.000 $4,926.940 $3,500.000 $5,000.000 $5,000.000 $6,000.000 $3,000.000 $1,251.000 $11,600.000 $5,000.000 $6,000.000 $5,000.000 $22,000.000 $10,000.000
MOBILIZATION
LS 1.000 $46,077.120 $35,000.000 $50,000.000 $52,000.000 $56,000.000 $55,000.000 $40,000.000 $30,500.000 $65,000.000 $10,000.000 $60,000.000 $44,000.000 $76,900.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $11,735.440 $1.000 $5,000.000 $1,000.000 $10,000.000 $1.000 $4,123.000 $8,250.000 $5,000.000 $2,000.000 $7,500.000 $500.000 $8,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 6.000 $129.820 $200.000 $100.000 $500.000 $10.000 $1.000 $100.000 $1,500.000 $1,000.000 $300.000 $200.000 $500.000 $500.000
TMA (STATIONARY)
DAY 50.000 $284.140 $1.000 $300.000 $122.000 $10.000 $1.000 $411.000 $1.000 $400.000 $150.000 $1.000 $250.000 $75.000
MTL W-BEAM GD FEN (TIM POST)
LF 25.000 $29.890 $100.000 $40.000 $180.000 $50.000 $80.000 $55.000 $180.000 $100.000 $40.000 $1.000 $55.000 $90.000
REMOVE METAL BEAM GUARD FENCE
LF 25.000 $4.710 $25.000 $10.000 $40.000 $5.000 $10.000 $5.000 $12.500 $5.000 $7.000 $300.000 $11.000 $20.000
DRIFTWOOD REMOVAL
LS 4.000 $6,950.000 $5,000.000 $1,000.000 $8,000.000 $5,000.000 $1,000.000 $8,700.000 $2,400.000 $10,000.000 $600.000 $2,500.000 $11,000.000 $7,000.000
SPOT TREE TRIMMING / BRUSH REMOVAL
LF 565.000 $93.000 $20.000 $15.000 $45.000 $57.000 $120.000 $10.000 $50.000 $58.000 $12.000 $30.000 $44.000 $30.000
TREE REMOVAL (4" - 12" DIA)
EA 8.000 $334.850 $250.000 $100.000 $400.000 $328.000 $100.000 $500.000 $286.000 $300.000 $200.000 $200.000 $1,100.000 $4,000.000
TREE REMOVAL (12" - 18" DIA)
EA 4.000 $224.730 $400.000 $200.000 $500.000 $454.000 $200.000 $500.000 $400.000 $400.000 $200.000 $200.000 $2,200.000 $7,000.000
TREE REMOVAL (24" - 30" DIA)
EA 8.000 $663.340 $550.000 $500.000 $800.000 $926.000 $300.000 $900.000 $800.000 $1,500.000 $200.000 $600.000 $3,300.000 $9,000.000
TREE REMOVAL (30" - 36" DIA)
EA 2.000 $677.420 $1,200.000 $1,000.000 $800.000 $1,134.000 $500.000 $1,500.000 $1,000.000 $1,500.000 $200.000 $1,200.000 $4,400.000 $10,000.000
TREE REMOVAL (36" - 42" DIA)
EA 2.000 $520.860 $1,600.000 $1,000.000 $1,000.000 $1,550.000 $500.000 $1,900.000 $1,350.000 $2,000.000 $200.000 $2,500.000 $5,500.000 $12,000.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 30.000 $137.270 $75.000 $150.000 $40.000 $250.000 $75.000 $200.000 $115.000 $100.000 $80.000 $105.000 $220.000 $80.000
CARBON FIBER REINF POLYMER PROTECTION
SF 576.000 $165.880 $160.000 $100.000 $75.000 $128.000 $150.000 $200.000 $75.000 $125.000 $450.000 $60.000 $220.000 $50.000
Totals: $747,777.383 $422,313.000 $467,321.000 $481,398.000 $559,906.000 $567,255.500 $576,144.300 $591,158.400 $618,009.000 $625,559.700 $657,612.500 $683,383.500 $769,052.000