Show Job Controls
Bid Cobra

FREESTONE FM 27 (0456-01-047)

Items: 144

County: FREESTONE
Length: N/A
Highway: FM 27
District: BRYAN
Control Number: 0456-01-047
DBE Goal: N/A
Project: STP 1902(155)
Guaranty: N/A
Time: 330 WORKING DAYS
Engineer's Estimate: $17,432,231.07
Date: 10/03/2019 (6 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROAD
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$17,432,231.07
$14,892,846.02
Over/Under Est: -14.57% -$2,539,385.05
Over/Under Est: -8.33% -$1,452,752.49
Amt Left: 7.3% $1,086,632.56
Over/Under Est: -7.72% -$1,345,084.07
Amt Left: 8.02% $1,194,300.98
Delta: -0.67% -$107,668.42
$16,091,622.67
Over/Under Est: -7.69% -$1,340,608.40
Amt Left: 8.05% $1,198,776.65
Delta: -0.03% -$4,475.67

Bid Items & Bid Tabulations

144 Total 0 of 144
FREESTONE  |  FM 27  |  BRYAN  |  0456-01-047  |  10/03/2019  |  $17,432,231.07  |  STP 1902(155)  |  REHAB EXIST ROAD  |  330 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
JAMES CONSTRUCTION GROUP, L.L.C.
BIG CREEK CONSTRUCTION, LTD.
A. L. HELMCAMP, INC.
PREPARING ROW
STA 857.000 $250.000 $400.000 $1,600.000 $500.000 $400.000
REMOVING CONC (DRIVEWAYS)
SY 28.000 $12.000 $25.000 $81.070 $25.000 $55.000
REMOVING CONC (CURB)
LF 1,000.000 $1.900 $6.700 $2.770 $10.000 $18.000
REMOVING STAB BASE AND ASPH PAV (6")
SY 20,805.000 $3.800 $2.500 $3.000 $3.500 $3.500
EXCAVATION (ROADWAY)
CY 73,165.000 $15.000 $9.000 $4.130 $10.000 $12.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 18,890.000 $15.000 $8.000 $8.690 $10.000 $15.000
FURNISHING AND PLACING TOPSOIL (4")
SY 260,617.000 $0.580 $0.140 $0.260 $0.500 $0.650
BLOCK SODDING
SY 350.000 $4.430 $5.500 $5.000 $10.000 $7.000
CELL FBR MLCH SEED(PERM)(RURAL)(SANDY)
SY 260,617.000 $0.300 $0.320 $0.270 $0.290 $0.330
CELL FBR MLCH SEED(TEMP)(WARM)
SY 130,317.000 $0.270 $0.300 $0.260 $0.280 $0.310
CELL FBR MLCH SEED(TEMP)(COOL)
SY 130,317.000 $0.270 $0.300 $0.260 $0.280 $0.310
VEGETATIVE WATERING
MG 5,212.000 $12.040 $7.000 $16.610 $5.000 $10.000
FL BS (CMP IN PLACE) (TY D GR 1-2)(10")
SY 244,693.000 $17.510 $10.400 $9.180 $13.500 $12.000
FL BS (CMP IN PLC)(TY D GR1-2)(8")
SY 27,740.000 $10.660 $8.750 $8.680 $11.500 $10.000
REWORK BS MTL (TY C) (6") (ORD COMP)
SY 171,792.000 $1.740 $1.250 $3.000 $1.500 $1.400
LIME TRT (EXST MATL) (12")
SY 29,474.000 $3.000 $2.250 $4.000 $3.500 $6.000
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
TON 637.000 $160.000 $178.000 $145.160 $150.000 $160.000
CEMENT
TON 3,578.000 $144.800 $165.000 $139.690 $150.000 $155.000
CEMENT TREAT (EXIST MATL) (10")
SY 264,915.000 $2.500 $1.500 $0.810 $1.500 $2.000
ASPH (AC-20-5TR)
GAL 208,284.000 $3.900 $3.000 $2.900 $3.000 $3.100
ASPH (RC-250)
GAL 79,499.000 $3.790 $2.900 $3.250 $3.500 $3.500
AGGR (TY-B GR-5 OR TY-L GR-5)
CY 2,356.000 $89.520 $92.000 $94.650 $70.000 $130.000
AGGR (TY-PB GR-4 OR TY-PL GR-4 SAC-A)
CY 4,390.000 $100.000 $116.000 $122.650 $120.000 $130.000
D-GR HMA (SQ) TY-D PG64_22(LEVEL-UP)
TON 618.000 $71.790 $105.000 $160.000 $80.000 $100.000
SUPERPAVE MIXTURES SP-D SAC-A PG64-22
TON 1,531.000 $90.000 $100.000 $146.000 $85.000 $105.000
PLANE ASPH CONC PAV (2")
SY 13,917.000 $0.990 $1.650 $2.360 $1.500 $2.000
CEM STABIL BKFL
CY 1,204.000 $100.000 $130.000 $125.000 $130.000 $130.000
CUT & RESTORING PAV
SY 627.000 $80.000 $72.000 $100.000 $50.000 $100.000
TRENCH EXCAVATION PROTECTION
LF 783.000 $7.680 $6.250 $12.000 $5.000 $13.000
TEMPORARY SPL SHORING
SF 1,698.000 $12.950 $20.000 $30.000 $45.000 $35.000
RIPRAP (CONC)(5 IN)
CY 99.000 $470.690 $422.000 $408.810 $475.000 $525.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 638.000 $120.000 $170.000 $165.000 $125.000 $130.000
RIPRAP (MOW STRIP)(4 IN)
CY 592.000 $475.000 $465.000 $474.920 $475.000 $550.000
CONC BOX CULV (3 FT X 2 FT)
LF 281.000 $176.860 $235.000 $400.000 $270.000 $425.000
CONC BOX CULV (3 FT X 3 FT)
LF 78.000 $177.200 $240.000 $435.000 $275.000 $460.000
CONC BOX CULV (4 FT X 2 FT)
LF 312.000 $182.730 $264.000 $450.000 $285.000 $480.000
CONC BOX CULV (5 FT X 2 FT)
LF 92.000 $232.130 $320.000 $500.000 $350.000 $520.000
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 167.000 $450.000 $630.000 $485.000 $475.000 $510.000
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
LF 24.000 $450.000 $650.000 $485.000 $550.000 $510.000
CONC BOX CULV (4 FT X 3 FT)(EXTEND)
LF 13.000 $550.000 $680.000 $500.000 $650.000 $520.000
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
LF 75.000 $600.000 $600.000 $545.000 $750.000 $580.000
CONC BOX CULV (5 FT X 5 FT)(EXTEND)
LF 13.000 $600.000 $655.000 $600.000 $1,000.000 $640.000
CONC BOX CULV (8 FT X 6 FT)(EXTEND)
LF 16.000 $1,075.380 $850.000 $800.000 $1,400.000 $850.000
CONC BOX CULV (5 FT X 6.5 FT)(EXTEND)
LF 33.000 $800.000 $765.000 $750.000 $1,000.000 $790.000
RC PIPE (CL III)(18 IN)
LF 7,026.000 $47.700 $52.000 $48.000 $50.000 $50.000
RC PIPE (CL III)(24 IN)
LF 800.000 $62.000 $92.000 $90.000 $70.000 $94.000
RC PIPE (CL III)(30 IN)
LF 330.000 $76.380 $130.000 $125.000 $100.000 $130.000
RC PIPE (CL III)(36 IN)
LF 254.000 $109.000 $130.000 $145.000 $160.000 $150.000
RC PIPE (CL III)(48 IN)
LF 54.000 $150.000 $230.000 $160.000 $275.000 $175.000
RC PIPE (CL IV)(30 IN)
LF 45.000 $127.160 $155.000 $135.000 $160.000 $150.000
INLET (COMPL)(PCO)(3FT)(NONE)
EA 2.000 $3,874.500 $3,400.000 $3,500.000 $4,000.000 $3,600.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 1.000 $7,800.000 $7,500.000 $9,702.040 $8,100.000 $7,400.000
WINGWALL (PW - 1) (HW=10 FT)
EA 5.000 $30,000.000 $23,000.000 $20,665.300 $40,000.000 $32,000.000
WINGWALL (PW - 1) (HW=11 FT)
EA 1.000 $30,500.000 $29,000.000 $22,092.160 $52,000.000 $46,000.000
WINGWALL (PW - 1) (HW=12 FT)
EA 1.000 $45,233.800 $43,000.000 $21,570.300 $68,000.000 $54,000.000
WINGWALL (PW - 1) (HW=3 FT)
EA 1.000 $7,706.890 $7,600.000 $9,156.820 $6,800.000 $5,200.000
WINGWALL (PW - 1) (HW=4 FT)
EA 2.000 $6,500.000 $8,700.000 $9,638.510 $10,000.000 $7,800.000
WINGWALL (PW - 1) (HW=5 FT)
EA 7.000 $8,300.000 $9,700.000 $10,000.420 $11,500.000 $11,000.000
WINGWALL (PW - 1) (HW=7 FT)
EA 7.000 $18,750.000 $11,900.000 $14,321.440 $20,000.000 $18,000.000
WINGWALL (PW - 1) (HW=8 FT)
EA 12.000 $21,317.000 $14,700.000 $16,829.300 $26,000.000 $23,000.000
WINGWALL (PW - 1) (HW=9 FT)
EA 7.000 $26,485.190 $16,400.000 $19,791.120 $36,000.000 $32,000.000
SET (TY I)(S=3 FT)(HW=3FT)(3:1)(C)
EA 9.000 $4,894.810 $8,400.000 $4,019.960 $2,800.000 $4,000.000
SET (TY I)(S=3 FT)(HW=3FT)(4:1)(C)
EA 4.000 $5,587.240 $8,500.000 $4,294.960 $4,000.000 $4,700.000
SET (TY I)(S=3 FT)(HW= 4 FT)(3:1)(C)
EA 6.000 $5,313.330 $8,500.000 $4,019.960 $4,200.000 $6,300.000
SET (TY I)(S= 4 FT)(HW= 3 FT)(3:1) (C)
EA 8.000 $4,953.250 $8,800.000 $4,254.960 $3,400.000 $6,800.000
SET (TY I)(S= 4 FT)(HW= 4 FT)(3:1) (C)
EA 2.000 $5,700.000 $9,200.000 $4,254.970 $3,800.000 $6,800.000
SET (TY I)(S= 4 FT)(HW= 5 FT)(3:1) (C)
EA 4.000 $6,750.000 $10,200.000 $5,574.960 $6,200.000 $7,800.000
SET (TY I)(S= 5 FT)(HW= 4 FT)(3:1) (C)
EA 4.000 $7,500.000 $10,100.000 $4,754.960 $4,400.000 $8,500.000
SET (TY II) (18 IN) (RCP) (3: 1) (C)
EA 8.000 $770.000 $1,150.000 $750.000 $600.000 $780.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 2.000 $1,000.000 $1,150.000 $800.000 $900.000 $850.000
SET (TY II) (18 IN) (RCP) (4: 1) (P)
EA 7.000 $1,193.520 $850.000 $800.000 $700.000 $850.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 229.000 $825.000 $850.000 $800.000 $1,000.000 $850.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 4.000 $850.000 $1,400.000 $825.000 $750.000 $870.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 2.000 $875.000 $1,400.000 $825.000 $1,100.000 $870.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 28.000 $1,100.000 $1,000.000 $950.000 $1,200.000 $1,000.000
SET (TY II) (30 IN) (RCP) (3: 1) (C)
EA 8.000 $1,250.000 $2,000.000 $2,000.000 $1,300.000 $2,100.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 2.000 $1,500.000 $2,000.000 $2,250.000 $1,400.000 $2,400.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 6.000 $1,551.000 $2,600.000 $2,500.000 $1,500.000 $2,600.000
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 5.000 $1,950.000 $2,200.000 $2,500.000 $2,100.000 $2,600.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 6.000 $2,500.000 $2,400.000 $3,000.000 $2,200.000 $3,200.000
SET (TY II) (48 IN) (RCP) (4: 1) (C)
EA 2.000 $4,100.000 $6,800.000 $4,500.000 $4,200.000 $4,700.000
ADJUSTING MANHOLES
EA 1.000 $750.000 $1,000.000 $1,000.000 $1,500.000 $1,100.000
ADJUSTING MANHOLES (WATER VALVE BOX)
EA 1.000 $213.000 $750.000 $1,000.000 $750.000 $1,100.000
REMOV STR (BOX CULVERT)
EA 9.000 $4,300.000 $1,150.000 $4,000.000 $5,000.000 $4,200.000
REMOV STR (INLET)
EA 2.000 $875.000 $1,400.000 $2,000.000 $650.000 $600.000
REMOV STR (HEADWALL)
EA 62.000 $2,500.000 $875.000 $2,500.000 $1,200.000 $800.000
REMOV STR (PIPE)
EA 145.000 $895.450 $415.000 $1,750.000 $650.000 $450.000
MOBILIZATION
LS 1.000 $1,587,000.000 $1,480,000.000 $1,474,589.240 $1,606,000.000 $1,220,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 22.000 $6,000.000 $25,000.000 $21,255.930 $8,500.000 $7,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 8,220.000 $28.590 $27.000 $26.500 $25.000 $27.000
ROCK FILTER DAMS (REMOVE)
LF 8,220.000 $7.000 $9.000 $9.500 $3.000 $9.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 1,800.000 $15.000 $11.000 $21.000 $15.000 $18.000
CONSTRUCTION EXITS (REMOVE)
SY 1,800.000 $2.500 $4.000 $9.000 $3.000 $7.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 47,835.000 $2.390 $2.900 $1.900 $3.000 $2.400
TEMP SEDMT CONT FENCE (REMOVE)
LF 47,835.000 $0.520 $0.750 $0.600 $0.500 $0.800
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 40.000 $3.650 $8.000 $3.750 $10.000 $10.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 40.000 $0.850 $1.000 $0.900 $1.000 $1.500
CONC CURB & GUTTER (TY II)
LF 1,000.000 $36.390 $32.000 $60.560 $24.000 $42.000
INTERSECTIONS (ACP)
SY 1,761.000 $30.630 $47.000 $34.780 $30.000 $41.000
TURNOUTS (SURF TREAT)
SY 1,253.000 $60.000 $38.000 $52.450 $30.000 $21.000
DRIVEWAYS AND TURNOUTS (ACP)
SY 1,816.000 $30.000 $47.000 $39.690 $30.000 $40.000
DRIVEWAYS AND TURNOUTS (SURF TREAT)
SY 15,182.000 $20.000 $29.000 $42.980 $25.000 $26.000
MTL W-BEAM GD FEN (TIM POST)
LF 9,801.000 $22.000 $18.000 $16.000 $23.000 $19.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,000.000 $2,000.000 $1,300.000 $2,000.000 $1,500.000
MTL BEAM GD FEN TRANS (T101)
EA 16.000 $1,312.000 $850.000 $1,025.000 $1,600.000 $850.000
MTL THRIE-BEAM GD FEN ADJUSTMENT
LF 1,780.000 $10.000 $11.500 $17.000 $17.000 $12.000
REMOVE METAL BEAM GUARD FENCE
LF 6,280.000 $2.120 $2.350 $2.000 $4.000 $2.500
REMOVE TERMINAL ANCHOR SECTION
EA 36.000 $218.000 $105.000 $200.000 $200.000 $110.000
GUARDRAIL END TREATMENT (INSTALL)
EA 76.000 $2,615.350 $2,700.000 $2,500.000 $3,000.000 $2,700.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 20.000 $1,400.000 $1,250.000 $1,400.000 $500.000 $1,300.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 83.000 $265.000 $180.000 $110.000 $150.000 $175.000
MAILBOX INSTALL-D (WC-POST) TY 3
EA 11.000 $320.000 $235.000 $155.000 $200.000 $190.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 130.000 $383.030 $425.000 $345.000 $400.000 $480.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 11.000 $465.600 $500.000 $470.000 $500.000 $580.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 4.000 $550.220 $550.000 $535.000 $600.000 $670.000
IN SM RD SN SUP&AM TY10BWG(2)SA(P)
EA 3.000 $1,095.680 $800.000 $765.000 $800.000 $1,100.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 4.000 $733.240 $675.000 $645.000 $700.000 $970.000
REMOVE SM RD SN SUP&AM
EA 138.000 $84.830 $75.000 $45.000 $75.000 $85.000
INSTL DEL ASSM (D-SW)SZ 1(FLX)GND(BI)
EA 11.000 $122.560 $55.000 $52.000 $60.000 $60.000
INSTL OM ASSM (OM-2Z)(FLX)GND
EA 120.000 $64.530 $56.000 $53.000 $60.000 $67.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 142.000 $45.000 $30.000 $28.000 $40.000 $45.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 333,706.000 $0.200 $0.100 $0.100 $0.110 $0.090
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 166,853.000 $0.200 $0.110 $0.100 $0.110 $0.110
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 333,706.000 $0.200 $0.100 $0.100 $0.110 $0.090
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 1,560.000 $0.870 $1.030 $4.050 $1.500 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 22,174.000 $1.150 $1.220 $1.030 $1.000 $0.600
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 215.000 $0.700 $1.030 $1.000 $1.500 $1.100
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 476.000 $15.000 $6.200 $8.050 $7.000 $6.300
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 6.000 $350.000 $175.000 $80.000 $200.000 $175.000
REFL PAV MRK TY I (W)(RR XING)(100MIL)
EA 6.000 $600.000 $575.000 $695.000 $600.000 $600.000
RE PM W/RET REQ TY I (W)4"(SLD)(090MIL)
LF 10,065.000 $0.360 $0.510 $0.360 $0.550 $0.520
RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL)
LF 635.000 $0.360 $1.030 $0.420 $1.500 $1.100
RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL)
LF 9,077.000 $0.360 $0.510 $0.360 $0.550 $0.520
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 396,004.000 $0.690 $0.550 $0.670 $0.600 $0.560
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 40,904.000 $0.760 $0.590 $0.730 $0.650 $0.600
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 181,616.000 $0.690 $0.550 $0.670 $0.600 $0.580
REFL PAV MRKR TY I-C
EA 11.000 $3.370 $6.200 $10.000 $10.000 $7.000
REFL PAV MRKR TY II-A-A
EA 1,950.000 $4.000 $3.600 $4.400 $4.000 $3.700
ELIM EXT PAV MRK & MRKS (4")
LF 76,196.000 $0.270 $0.370 $0.250 $0.400 $0.360
PAV SURF PREP FOR MRK (4")
LF 76,196.000 $0.080 $0.040 $0.010 $0.050 $0.040
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $4,982.580 $10,000.000 $2,612.500 $10,000.000 $10,000.000
PREFORMED CENTERLINE RUMBLE STRIP
LF 2,762.000 $5.000 $6.250 $6.550 $7.000 $6.500
TMA (STATIONARY)
EA 2.000 $7,000.000 $5,000.000 $16,000.000 $7,500.000 $34,000.000
TMA (MOBILE OPERATION)
DAY 48.000 $350.000 $250.000 $952.610 $250.000 $200.000
Totals: $17,432,231.070 $14,892,846.020 $15,979,478.580 $16,087,147.000 $16,091,622.670