FREESTONE US 84 (0057-05-033)
Items: 78
County: FREESTONE
Length: 0.0000 MILES
Highway: US 84
District: BRYAN
Control Number: 0057-05-033
DBE Goal: 0.0%
Project: STP 2026(114)HES
Guaranty: $27,000.00
Time: 81 WORKING DAYS
Engineer's Estimate: $1,370,335.77
Date: 02/05/2026 (4 months ago)
Contract Number: 2263228
Type: INTERSECTION IMPROVEMENTS ADDING RIGHT TURN LANES
Project ID: A00192964
Contract Type: Federal
Project Description: ADD RIGHT TURN LANES
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
DELMY REYES
MATT HENSARLING
FREESTONE US 84 (0057-05-033)
Project Name: N/A
Project: STP 2026(114)HES
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: 0.3 MI E OF FM 489
Limits To: 0.3 MI W OF FM 489
Project Description: ADD RIGHT TURN LANES
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,370,335.77 | |||
| $1,716,129.85 |
25.23%
$345,794.08
|
|||
| $1,798,041.60 |
31.21%
$427,705.83
|
4.77%
$81,911.75
|
||
| $1,807,581.88 |
31.91%
$437,246.11
|
5.33%
$91,452.03
|
-0.53%
-$9,540.28
|
|
| $1,842,051.77 |
34.42%
$471,716.00
|
7.34%
$125,921.92
|
-1.91%
-$34,469.89
|
|
| $2,396,485.87 |
74.88%
$1,026,150.10
|
39.64%
$680,356.02
|
-30.10%
-$554,434.10
|
E
Engineer's Estimate
$1,370,335.77
1
Awarded
$1,716,129.85
Over/Under Est:
25.23%
$345,794.08
$1,798,041.60
Over/Under Est:
31.21%
$427,705.83
Amt Left:
4.77%
$81,911.75
$1,807,581.88
Over/Under Est:
31.91%
$437,246.11
Amt Left:
5.33%
$91,452.03
Delta:
-0.53%
-$9,540.28
$1,842,051.77
Over/Under Est:
34.42%
$471,716.00
Amt Left:
7.34%
$125,921.92
Delta:
-1.91%
-$34,469.89
$2,396,485.87
Over/Under Est:
74.88%
$1,026,150.10
Amt Left:
39.64%
$680,356.02
Delta:
-30.10%
-$554,434.10
| Subcontractor | Percentage | Amount |
|---|---|---|
| STRIPING TECHNOLOGY, L.P. | 2.47% | $42,388.41 |
| THIRD COAST SERVICES LLC | 2.06% | $35,352.27 |
| SOUTHWEST ENVIRONMENT SERVICES LLC | 1.26% | $21,623.24 |
| 4E TREE WORX LLC | 0.96% | $16,474.85 |
| WEST TEXAS RUMBLE STRIP LLC | 0.43% | $7,379.36 |
| DIAMOND ELITE BARRICADES, LLC | 0.25% | $4,290.32 |
| Total: | 7.43% | $127,508.45 |
Bid Items & Bid Tabulations
78
Total
0 of 78
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) | $3,000.00 |
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) | $23,000.00 |
| Total: | $31,000.00 |