FRANKLIN SH0037 (6498-80-001)

Items: 16

County: FRANKLIN
Length: 0.0100 MILES
Highway: SH0037
District: PARIS
Control Number: 6498-80-001
DBE Goal: 0.0%
Project: RMC - A00220064
Guaranty: $0.00
Time: 40 WORKING DAYS
Engineer's Estimate: $253,524.00
Date: 04/16/2026 (7 weeks ago)
Contract Number: 4260103
Type: CULVERT REPAIR
Project ID: A00220064
Project Description: CULVERT REPAIR ON SPUR 423 AND SH 37 IN FRANKLIN CO.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: MAINTENANCE CONTRACT OFFICE
3500 SW LOOP 286, PARIS, TX 75460
JESSE HERRERA
DUSTIN LYDAY
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$253,524.00
$121,450.00
Over/Under Est: -52.1% -$132,074.00
Over/Under Est: -47.6% -$120,674.00
Amt Left: 9.39% $11,400.00
Over/Under Est: -42.63% -$108,080.00
Amt Left: 19.76% $23,994.00
Delta: -9.48% -$12,594.00
Over/Under Est: -33.64% -$85,284.00
Amt Left: 38.53% $46,790.00
Delta: -15.67% -$22,796.00
$173,575.00
Over/Under Est: -31.54% -$79,949.00
Amt Left: 42.92% $52,125.00
Delta: -3.17% -$5,335.00
Over/Under Est: -28.01% -$71,024.00
Amt Left: 50.27% $61,050.00
Delta: -5.14% -$8,925.00
Over/Under Est: -24.24% -$61,454.00
Amt Left: 58.15% $70,620.00
Delta: -5.24% -$9,570.00
$211,124.00
Over/Under Est: -16.72% -$42,400.00
Amt Left: 73.84% $89,674.00
Delta: -9.92% -$19,054.00

Bid Items & Bid Tabulations

16 Total 0 of 16
FRANKLIN  |  SH0037  |  PARIS  |  6498-80-001  |  04/16/2026  |  $253,524.00  |  RMC - A00220064  |  CULVERT REPAIR  |  40 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
RB CONTRACTING, LLC
GARRET SHIELDS INFRASTRUCTURE
ICOS MANAGEMENT, LLC
JACKSON EXCAVATION, LLC
CATOCON, INC.
SHALOM SERVICES CORPORATION
GHB EQUIPMENT COMPANY, L.L.C.
ROAD DOCTORS LLC
REMOV CONC (RIPRAP)
CY 7.000 $1,800.000 $200.000 $200.000 $110.000 $110.000 $1,000.000 $150.000 $600.000 $550.000
EXCAV (CHANNEL)
CY 70.000 $500.000 $60.000 $50.000 $44.000 $40.000 $150.000 $30.000 $300.000 $500.000
EMBANK (FNL)(OC)(TY A)
CY 100.000 $150.000 $40.000 $50.000 $66.000 $60.000 $50.000 $70.000 $250.000 $200.000
CUT & RESTORE ASPH PAVING
SY 30.000 $350.000 $300.000 $150.000 $220.000 $90.000 $400.000 $350.000 $300.000 $1,000.000
FLOWABLE BACKFILL
CY 10.000 $1,500.000 $385.000 $300.000 $330.000 $600.000 $250.000 $1,000.000 $1,500.000 $300.000
RIPRAP (CONC)(4 IN)
CY 11.000 $2,000.000 $900.000 $600.000 $770.000 $1,000.000 $600.000 $1,250.000 $1,000.000 $750.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 40.000 $550.000 $275.000 $300.000 $220.000 $220.000 $200.000 $300.000 $450.000 $250.000
CLEANING AND SEALING EXISTING JOINTS
LF 285.000 $200.000 $60.000 $50.000 $66.000 $90.000 $75.000 $50.000 $62.000 $80.000
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
LF 4.000 $760.000 $2,000.000 $1,000.000 $1,540.000 $1,000.000 $5,000.000 $10,000.000 $800.000 $800.000
WINGWALL (PW - 2) (HW=5 FT)
EA 1.000 $21,000.000 $13,000.000 $20,000.000 $27,500.000 $50,000.000 $30,000.000 $17,000.000 $7,500.000 $30,000.000
REMOV STR (HEADWALL)
EA 1.000 $2,500.000 $1,000.000 $5,000.000 $4,400.000 $1,200.000 $10,000.000 $1,250.000 $2,500.000 $5,000.000
REMOVE STR (GABION)
LF 40.000 $100.000 $50.000 $100.000 $55.000 $10.000 $150.000 $50.000 $100.000 $100.000
MOBILIZATION
LS 1.000 $22,684.000 $15,000.000 $20,000.000 $44,000.000 $30,000.000 $15,000.000 $35,000.000 $16,000.000 $20,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $2,000.000 $5,000.000 $10,000.000 $1.000 $2,500.000 $5,000.000 $5,000.000 $10,000.000 $5,000.000
TMA (STATIONARY)
DAY 24.000 $200.000 $350.000 $300.000 $110.000 $520.000 $200.000 $175.000 $500.000 $1.000
CONC CURB & GUTTER (TY II)
LF 24.000 $100.000 $150.000 $100.000 $88.000 $60.000 $200.000 $100.000 $250.000 $250.000
Totals: $253,524.000 $121,450.000 $132,850.000 $145,444.000 $168,240.000 $173,575.000 $182,500.000 $192,070.000 $211,124.000