FORT BEND PR 72 (3422-01-012)

Items: 35

County: FORT BEND
Length: N/A
Highway: PR 72
District: HOUSTON
Control Number: 3422-01-012
DBE Goal: N/A
Project: C 3422-1-12
Guaranty: N/A
Time: 27 WORKING DAYS
Engineer's Estimate: $347,019.52
Date: 03/05/2021 (5 years ago)
Contract Number: N/A
Type: STATE PARK IMPROVEMENTS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (4)
E
Engineer's Estimate
$347,019.52
Over/Under Est: 11.5% $39,894.57
Over/Under Est: 31.2% $108,283.76
Amt Left: 17.68% $68,389.19
Over/Under Est: 36.07% $125,180.38
Amt Left: 22.04% $85,285.81
Delta: -3.71% -$16,896.62
Over/Under Est: 46.23% $160,415.48
Amt Left: 31.15% $120,520.91
Delta: -7.46% -$35,235.10

Bid Items & Bid Tabulations

35 Total 0 of 35
FORT BEND  |  PR 72  |  HOUSTON  |  3422-01-012  |  03/05/2021  |  $347,019.52  |  C 3422-1-12  |  STATE PARK IMPRVS  |  27 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
TRIPLE B SERVICES LLP
MAIN LANE INDUSTRIES LTD.
FORDE CONSTRUCTION COMPANY, INC.
PREPARING ROW(TREE)(5" TO 12" DIA)
EA 6.000 $800.000 $550.000 $1,000.000 $1,000.000 $4,200.000
REMOVING CONC (CTB)
LF 350.000 $8.000 $40.000 $25.000 $20.000 $25.000
EXCAVATION (ROADWAY)
CY 260.000 $8.830 $15.000 $3.000 $10.000 $19.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 4,669.000 $7.790 $16.500 $25.000 $26.000 $29.000
BLOCK SODDING
SY 6,583.000 $3.600 $2.850 $3.000 $4.000 $2.850
STRAW OR HAY MULCH
SY 80.000 $0.250 $8.680 $10.000 $1.500 $8.680
BROADCAST SEED (TEMP) (WARM)
SY 66.000 $0.220 $9.280 $10.500 $1.500 $9.280
DRILL SEED (TEMP)(WARM OR COOL)
SY 14.000 $0.210 $9.890 $11.000 $1.500 $9.890
FERTILIZER
AC 1.380 $766.000 $1,508.000 $1,700.000 $1,000.000 $1,507.490
VEGETATIVE WATERING
MG 165.600 $25.390 $20.000 $19.000 $40.000 $87.320
FL BS (CMP IN PLC)(TY D GR 4) (6")
SY 753.000 $25.000 $22.500 $22.000 $18.000 $26.000
LIME TRT (EXST MATL) (6")
SY 2,541.000 $3.080 $3.900 $6.000 $5.000 $5.000
LIME(HYD,COM OR QK)(SLRY)OR QK(DRY)
TON 34.310 $180.000 $180.000 $185.000 $200.000 $177.000
ASPHALT STAB BASE (GR 2)(PG 64)
TON 1,414.390 $80.000 $77.550 $92.000 $100.000 $84.000
SALV, HAUL & STKPL RCL APH PV (4")
SY 2,233.000 $5.000 $4.500 $6.000 $4.000 $4.000
D-GR HMA(SQ) TY-D SAC-A PG70-22
TON 191.710 $205.000 $122.000 $140.000 $140.000 $126.000
STRUCT EXCAV (PIPE)
CY 19.000 $3.230 $200.000 $12.000 $15.000 $39.000
CEM STABIL BKFL
CY 29.000 $41.580 $285.000 $50.000 $50.000 $64.000
RC PIPE (CL III)(24 IN)
LF 60.000 $74.000 $190.000 $110.000 $150.000 $80.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 2.000 $1,800.000 $3,100.000 $2,650.000 $2,000.000 $1,200.000
MOBILIZATION
LS 1.000 $31,548.000 $14,000.000 $40,000.000 $41,000.000 $50,500.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 2.000 $3,000.000 $1,000.000 $1,000.000 $5,000.000 $3,900.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 20.000 $30.340 $81.310 $100.000 $70.000 $70.000
ROCK FILTER DAMS (REMOVE)
LF 20.000 $9.460 $19.540 $22.000 $10.000 $22.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 907.000 $2.110 $3.500 $5.000 $3.000 $2.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 907.000 $0.510 $1.000 $1.000 $1.000 $1.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $400.000 $495.000 $600.000 $600.000 $495.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 2.000 $65.000 $50.000 $55.000 $60.000 $50.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 1,675.000 $0.260 $0.200 $0.250 $0.250 $0.200
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 1,675.000 $0.280 $0.200 $0.250 $0.250 $0.200
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,675.000 $0.320 $0.400 $0.500 $0.500 $0.400
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 1,675.000 $0.320 $0.440 $0.550 $0.500 $0.440
REFL PAV MRKR TY II-A-A
EA 21.000 $3.830 $4.500 $5.000 $5.000 $4.500
DECOMPOSED GRANITE (3" DEPTH)
SY 753.000 $20.000 $34.800 $21.000 $16.000 $25.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 67.000 $108.000 $85.000 $65.000 $50.000 $170.000
Totals: $347,019.524 $386,914.094 $455,303.280 $472,199.900 $507,435.008