FORT BEND FM 3155 (3223-01-010)
Items: 48
County: FORT BEND
Length: 1.0160 MILES
Highway: FM 3155
District: HOUSTON
Control Number: 3223-01-010
DBE Goal: 3.0%
Project: F 2025(633)
Guaranty: $13,000.00
Time: 17 WORKING DAYS
Engineer's Estimate: $628,501.57
Date: 02/07/2025 (1 year ago)
Contract Number: 2253234
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00140276
Contract Type: Federal
Project Description: BASE REPAIR, 2" PLANING, SEAL COAT, 1.5" ACP OVERLAY, SIGNING, AND PAVEMENT MARKINGS
Mail/Deliver Bids To: N/A
CARLOS ZEPEDA
DANIEL DVORAK
FORT BEND FM 3155 (3223-01-010)
Project Name: N/A
Project: F 2025(633)
Length: 1.0160 MILES
Project Type: CONSTRUCTION
Limits From: RICHMOND STATE SCHOOL
Limits To: UA 90
Project Description: BASE REPAIR, 2" PLANING, SEAL COAT, 1.5" ACP OVERLAY, SIGNING, AND PAVEMENT MARKINGS
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$628,501.57 | |||
| $585,949.45 |
-6.77%
-$42,552.12
|
|||
| $589,897.06 |
-6.14%
-$38,604.51
|
0.67%
$3,947.61
|
||
| $619,148.43 |
-1.49%
-$9,353.14
|
5.67%
$33,198.98
|
-4.96%
-$29,251.37
|
|
| $652,939.86 |
3.89%
$24,438.29
|
11.43%
$66,990.41
|
-5.46%
-$33,791.43
|
|
| $701,284.57 |
11.58%
$72,783.00
|
19.68%
$115,335.12
|
-7.40%
-$48,344.71
|
|
| $726,320.89 |
15.56%
$97,819.32
|
23.96%
$140,371.44
|
-3.57%
-$25,036.32
|
|
| $738,217.64 |
17.46%
$109,716.07
|
25.99%
$152,268.19
|
-1.64%
-$11,896.75
|
E
Engineer's Estimate
$628,501.57
1
Awarded
$585,949.45
Over/Under Est:
-6.77%
-$42,552.12
$589,897.06
Over/Under Est:
-6.14%
-$38,604.51
Amt Left:
0.67%
$3,947.61
$619,148.43
Over/Under Est:
-1.49%
-$9,353.14
Amt Left:
5.67%
$33,198.98
Delta:
-4.96%
-$29,251.37
$652,939.86
Over/Under Est:
3.89%
$24,438.29
Amt Left:
11.43%
$66,990.41
Delta:
-5.46%
-$33,791.43
$701,284.57
Over/Under Est:
11.58%
$72,783.00
Amt Left:
19.68%
$115,335.12
Delta:
-7.40%
-$48,344.71
$726,320.89
Over/Under Est:
15.56%
$97,819.32
Amt Left:
23.96%
$140,371.44
Delta:
-3.57%
-$25,036.32
$738,217.64
Over/Under Est:
17.46%
$109,716.07
Amt Left:
25.99%
$152,268.19
Delta:
-1.64%
-$11,896.75
| Subcontractor | Percentage | Amount |
|---|---|---|
| TRAFFIC SIGNS & LINES, LLC | 9.90% | $58,009.00 |
| R & A TRANSPORT, INC. | 7.68% | $45,000.92 |
| STRIPE LINES, INC. | 6.96% | $40,782.08 |
| CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. | 3.41% | $19,980.88 |
| INTERSTATE BARRICADES & MARKINGS, INC. | 0.87% | $5,097.76 |
| Total: | 28.82% | $168,870.64 |
Bid Items & Bid Tabulations
48
Total
0 of 48