FORT BEND SH 6 (1685-06-042)

Items: 55

County: FORT BEND
Length: 4.5780 MILES
Highway: SH 6
District: HOUSTON
Control Number: 1685-06-042
DBE Goal: 0.0%
Project: C 1685-6-42
Guaranty: $100,000.00
Time: 78 WORKING DAYS
Engineer's Estimate: $7,142,956.41
Date: 03/05/2025 (1 year ago)
Contract Number: 3253209
Type: SURFACING/ROADWAY RESTORATION
Project ID: A00140284
Project Description: BASE REPAIR, 2 INCH PLANING, SEAL COAT, 1.5 INCH SUPERPAVE OVERLAY, SIGNING AND PAVEMENT MARKINGS
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
CARLOS ZEPEDA
DANIEL DVORAK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$7,142,956.41
$5,168,419.02
Over/Under Est: -27.64% -$1,974,537.39
Over/Under Est: -27.56% -$1,968,549.34
Amt Left: 0.12% $5,988.05
Over/Under Est: -24.64% -$1,760,359.52
Amt Left: 4.14% $214,177.87
Delta: -4.02% -$208,189.82
Subcontractor Percentage Amount
STRIPE LINES, INC. 8.66% $435,804.89
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. 3.42% $172,107.70
TRAFFIC SIGNS & LINES, LLC 1.82% $91,589.48
INTERSTATE BARRICADES & MARKINGS, INC. 0.26% $13,084.21
PROFESSIONAL TRAFFIC CONTROL LLC 0.13% $6,542.11
Total: 14.29% $719,128.39

Bid Items & Bid Tabulations

55 Total 0 of 55
FORT BEND  |  SH 6  |  HOUSTON  |  1685-06-042  |  03/05/2025  |  $7,142,956.41  |  C 1685-6-42  |  SURF/ROADWAY RESTOR  |  78 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DURWOOD GREENE CONSTRUCTION CO.
VULCAN MATERIALS ASPHALT AND CONSTRUCTION, LLC
TEXAS MATERIALS GROUP, INC.
BACKFILL (TY A OR B)
STA 242.000 $290.000 $150.000 $273.000 $200.000
ASPH (AC-20-5TR)
GAL 91,512.000 $3.170 $4.350 $3.110 $3.500
AGGR (TY-PB, GR-4)(SAC-B)
CY 2,200.000 $300.000 $140.000 $194.000 $206.000
SP MIXES SP-D SAC-A PG76-22
TON 21,449.000 $156.000 $145.000 $121.500 $132.250
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 5,720.000 $105.000 $24.000 $45.250 $54.500
PLANE ASPH CONC PAV(2")
SY 285,979.000 $2.500 $1.000 $1.190 $1.500
RIPRAP (MOW STRIP)(4 IN)
CY 44.000 $550.000 $1,200.000 $724.000 $1,015.000
MOBILIZATION
LS 1.000 $612,000.000 $170,000.000 $445,000.000 $182,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $10,000.000 $4,500.000 $13,175.000 $711.000
TMA (STATIONARY)
DAY 44.000 $190.000 $400.000 $336.000 $262.000
TMA (MOBILE OPERATION)
DAY 212.000 $675.000 $80.000 $336.000 $620.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 28,359.000 $0.150 $0.280 $0.120 $0.300
MTL W-BEAM GD FEN (TIM POST)
LF 600.000 $29.450 $28.000 $24.000 $25.500
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,500.000 $2,900.000 $3,339.520 $2,352.000
REMOVE METAL BEAM GUARD FENCE
LF 600.000 $4.000 $3.000 $2.500 $2.750
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 4.000 $295.000 $250.000 $250.000 $547.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,400.000 $3,650.000 $2,950.000 $3,228.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $370.000 $250.000 $250.000 $273.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 65.000 $755.000 $520.000 $530.870 $780.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 20.000 $655.000 $670.000 $699.700 $804.000
IN SM RD SN SUP&AM TYS80(2)SB(T-2EXT)
EA 4.000 $1,450.000 $1,850.000 $1,722.980 $1,072.000
REMOVE SM RD SN SUP&AM
EA 89.000 $102.000 $80.000 $103.580 $125.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)CTB
EA 16.000 $25.000 $25.000 $18.000 $28.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 12.000 $35.000 $35.000 $30.250 $38.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 8.000 $82.000 $120.000 $49.730 $91.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 22,471.000 $0.400 $0.320 $0.290 $0.270
WK ZN PAV MRK NON-REMOV (W)4"(DOT)
LF 271.000 $0.400 $0.320 $0.600 $0.270
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 49,253.000 $0.400 $0.320 $0.290 $0.270
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 22,471.000 $0.500 $0.350 $0.320 $0.340
WK ZN PAV MRK NON-REMOV (W)6"(DOT)
LF 271.000 $0.510 $0.350 $0.800 $0.340
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 49,253.000 $0.380 $0.350 $0.320 $0.340
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 37,816.000 $1.370 $0.800 $0.600 $0.560
WK ZN PAV MRK NON-REMOV (W)12"(SLD)
LF 150.000 $2.600 $2.000 $1.500 $2.070
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 14,668.000 $3.000 $4.250 $3.000 $4.250
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 234.000 $88.000 $95.000 $85.000 $93.020
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 216.000 $95.000 $95.000 $95.000 $93.020
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 2,800.000 $0.500 $0.320 $0.290 $0.270
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 2,800.000 $0.400 $0.350 $0.320 $0.340
WK ZN PAV MRK NON-REMOV (Y)24"(SLD)
LF 1,802.000 $6.000 $4.250 $2.300 $4.360
REFL PAV MRK TY I (W)6"(DOT)(100MIL)
LF 271.000 $1.000 $1.100 $1.630 $1.080
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 18,908.000 $1.270 $1.100 $0.950 $1.070
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 75.000 $3.150 $4.250 $3.000 $4.360
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 7,334.000 $7.180 $7.000 $6.000 $7.050
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 117.000 $151.000 $215.000 $150.000 $209.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 108.000 $179.000 $225.000 $200.000 $220.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 901.000 $6.380 $7.000 $6.000 $7.050
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
LF 22,471.000 $1.040 $0.950 $1.000 $0.960
RE PM TY II (Y) 12" (SLD)
LF 3,065.000 $1.080 $2.250 $2.840 $2.170
RE PM TY II (Y) 18" (SLD)
LF 175.000 $2.500 $2.600 $2.900 $2.570
RE PM TY II (Y) 24" (SLD)
LF 13,806.000 $4.000 $4.000 $5.500 $4.010
TY I HIGH PERF PM (W)6"(BRK)(100MIL)
LF 22,471.000 $0.860 $1.000 $0.770 $1.000
TY I HIGH PERF PM (W)6"(SLD)(100MIL)
LF 49,253.000 $0.860 $1.000 $0.770 $1.000
TY I HIGH PERF PM (Y)6"(SLD)(100MIL)
LF 2,800.000 $0.860 $1.050 $0.770 $1.040
REFL PAV MRKR TY II-A-A
EA 140.000 $6.250 $7.000 $6.000 $7.050
REFL PAV MRKR TY II-C-R
EA 1,226.000 $6.160 $7.000 $6.000 $7.050
Totals: $7,142,956.410 $5,168,419.020 $5,174,407.070 $5,382,596.890
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
ENVIRONMENTAL: CONTRACTOR FORCE ACCOUNT WORK (NONPART) $34,000.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $1,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $20,500.00
CONTRACTOR FORCE ACCOUNT WORK (NON-PART) $3,000.00
Total: $58,500.00