Show Job Controls
Bid Cobra

FORT BEND SH 6 (1685-06-036)

Items: 19

County: FORT BEND
Length: N/A
Highway: SH 6
District: HOUSTON
Control Number: 1685-06-036
DBE Goal: N/A
Project: STP 2021(330)HES
Guaranty: N/A
Time: 273 WORKING DAYS
Engineer's Estimate: $2,219,345.27
Date: 02/05/2021 (5 years ago)
Contract Number: N/A
Type: SAFETY LIGHTING
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (10)
E
Engineer's Estimate
$2,219,345.27
Over/Under Est: -10.79% -$239,523.15
Over/Under Est: -10.51% -$233,154.67
Amt Left: 0.32% $6,368.48
Over/Under Est: -10.37% -$230,166.27
Amt Left: 0.47% $9,356.88
Delta: -0.15% -$2,988.40
$2,008,757.41
Over/Under Est: -9.49% -$210,587.86
Amt Left: 1.46% $28,935.29
Delta: -0.98% -$19,578.41
$2,064,028.00
Over/Under Est: -7% -$155,317.27
Amt Left: 4.25% $84,205.88
Delta: -2.75% -$55,270.59
Over/Under Est: -1.04% -$22,975.03
Amt Left: 10.94% $216,548.12
Delta: -6.41% -$132,342.24
Over/Under Est: -0.94% -$20,934.62
Amt Left: 11.04% $218,588.53
Delta: -0.09% -$2,040.41
Over/Under Est: 4.16% $92,236.05
Amt Left: 16.76% $331,759.20
Delta: -5.15% -$113,170.67
$2,491,239.85
Over/Under Est: 12.25% $271,894.58
Amt Left: 25.83% $511,417.73
Delta: -7.77% -$179,658.53
$2,732,939.79
Over/Under Est: 23.14% $513,594.52
Amt Left: 38.04% $753,117.67
Delta: -9.70% -$241,699.94
Subcontractor Percentage Amount
WILLOW CITY SIGN & RAIL, INC. 15.47% $580,163.37
LONESTAR TRAFFIC SAFETY, LLC 0.45% $16,876.12
Total: 15.92% $597,039.49

Bid Items & Bid Tabulations

19 Total 0 of 19
FORT BEND  |  SH 6  |  HOUSTON  |  1685-06-036  |  02/05/2021  |  $2,219,345.27  |  STP 2021(330)HES  |  SAFETY LIGHTING  |  273 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ALLSTATE SIGNAL & CONSTRUCTION, LLC
THIRD COAST SERVICES LLC
VACA UNDERGROUND UTILITIES INC
TRAF-TEX, INC.
CITYLYNX, INC.
FLORIDA TRAFFIC CONTROL DEVICES, INC.
SEFBO PIPELINE BRIDGE, INCORPORATED
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
ISI CONTRACTING, INC.
CREACOM, INC.
DRILL SHAFT (RDWY ILL POLE) (30 IN)
LF 1,100.000 $144.600 $188.910 $135.000 $140.000 $109.240 $160.000 $173.290 $81.000 $194.630 $150.000 $165.310
RIPRAP (CONC)(4 IN)
CY 1.400 $313.190 $1,389.510 $395.000 $400.000 $642.830 $550.000 $444.520 $383.250 $420.630 $450.000 $5,803.430
RIPRAP (CONC) (CL B) (4")
CY 36.800 $425.330 $604.300 $400.000 $400.000 $604.660 $550.000 $456.310 $519.750 $431.630 $475.000 $795.780
RIPRAP (MOW STRIP)(4 IN)
CY 763.000 $470.000 $200.000 $416.000 $400.000 $388.820 $300.000 $467.920 $433.800 $440.000 $550.000 $579.730
MOBILIZATION
LS 1.000 $4,618.490 $5,000.000 $195,000.000 $100,000.000 $76,264.350 $173,000.000 $85,732.730 $150,000.000 $158,609.300 $250,000.000 $246,344.870
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 19.000 $6,985.820 $1,055.000 $1,100.000 $1,000.000 $1,859.350 $1,300.000 $795.460 $3,500.000 $3,029.750 $1,200.000 $7,506.220
MTL W-BEAM GD FEN (TIM POST)
LF 5,026.000 $22.660 $19.420 $19.000 $19.500 $19.800 $19.000 $21.640 $19.520 $21.660 $20.000 $22.680
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 109.000 $1,188.280 $1,422.980 $1,000.000 $900.000 $1,221.000 $1,200.000 $1,163.940 $920.290 $1,099.750 $1,090.000 $1,305.930
GUARDRAIL END TREATMENT (INSTALL)
EA 109.000 $2,644.580 $2,423.230 $2,000.000 $2,300.000 $2,667.500 $2,500.000 $2,333.730 $2,033.290 $2,199.750 $2,230.000 $3,412.530
IN RD IL (TY SA) 50T-10 (400W EQ) LED
EA 109.000 $3,322.000 $3,597.250 $3,350.000 $3,265.000 $3,379.690 $3,200.000 $3,638.910 $3,465.000 $3,341.350 $3,800.000 $3,675.700
CONDT (PVC) (SCH 80) (2")
LF 25,272.000 $7.730 $9.350 $5.050 $6.750 $7.220 $7.500 $9.690 $9.980 $7.800 $10.500 $8.790
CONDT (PVC) (SCH 80) (2") (BORE)
LF 14,168.000 $12.840 $12.030 $10.000 $9.500 $8.100 $9.500 $14.070 $13.440 $17.450 $11.300 $14.940
CONDT (RM) (2")
LF 280.000 $25.260 $24.410 $23.000 $26.000 $19.330 $38.000 $18.860 $36.750 $25.710 $39.000 $35.130
ELEC CONDR (NO.8) BARE
LF 39,715.000 $0.990 $1.070 $1.000 $1.500 $1.180 $1.400 $0.740 $1.260 $0.980 $1.330 $0.670
ELEC CONDR (NO.8) INSULATED
LF 79,430.000 $1.040 $1.220 $1.100 $1.650 $1.370 $1.400 $0.970 $1.470 $1.100 $1.550 $0.750
GROUND BOX TY D (162922)W/APRON
EA 18.000 $912.640 $813.090 $785.000 $900.000 $644.400 $650.000 $677.020 $945.000 $829.750 $1,000.000 $748.570
ELC SRV TY A 240/480 060(SS)SS(E)GC(U)
EA 6.000 $6,038.500 $6,997.000 $4,970.000 $4,600.000 $9,255.200 $4,300.000 $4,892.040 $4,620.000 $5,634.500 $4,900.000 $7,279.360
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 654.000 $27.820 $16.800 $21.000 $20.000 $29.970 $30.000 $18.720 $17.920 $22.850 $17.000 $22.050
TMA (STATIONARY)
DAY 273.000 $283.320 $149.000 $150.000 $121.000 $74.660 $125.000 $124.870 $250.000 $201.000 $250.000 $190.620
Totals: $2,219,345.270 $1,979,822.124 $1,986,190.600 $1,989,179.000 $2,008,757.420 $2,064,028.000 $2,196,370.256 $2,198,410.650 $2,311,581.326 $2,491,239.850 $2,732,939.796