FORT BEND FM 1093 (1258-02-037)

Items: 34

County: FORT BEND
Length: N/A
Highway: FM 1093
District: HOUSTON
Control Number: 1258-02-037
DBE Goal: N/A
Project: STP 2018(564)
Guaranty: N/A
Time: 50 WORKING DAYS
Engineer's Estimate: $950,789.75
Date: 02/02/2018 (8 years ago)
Contract Number: N/A
Type: BASE REPAIR AND OVERLAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$950,789.75
Over/Under Est: -17.78% -$169,062.48
Over/Under Est: -15.92% -$151,336.62
Amt Left: 2.27% $17,725.86
Over/Under Est: -13.42% -$127,631.63
Amt Left: 5.3% $41,430.85
Delta: -2.97% -$23,704.99
Over/Under Est: 1.78% $16,880.51
Amt Left: 23.79% $185,942.99
Delta: -17.56% -$144,512.14

Bid Items & Bid Tabulations

34 Total 0 of 34
FORT BEND  |  FM 1093  |  HOUSTON  |  1258-02-037  |  02/02/2018  |  $950,789.75  |  STP 2018(564)  |  BASE REPAIR AND OVERLAY  |  50 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
JAMES CONSTRUCTION GROUP, L.L.C.
DURWOOD GREENE CONSTRUCTION CO.
ANGEL BROTHERS HOLDINGS CORP.
LONE STAR PAVING COMPANY
BACKFILL (TY A OR B)
STA 230.000 $235.000 $60.000 $50.000 $110.000 $150.000
SALV, HAUL & STKPL RCL APH PV (1 1/2")
SY 11,070.000 $1.250 $1.200 $0.200 $1.000 $1.500
SALV,HAUL&STKPL RCL APH PV(0 TO 1 1/2")
SY 8,200.000 $5.250 $1.000 $0.200 $1.000 $1.500
D-GR HMA TY-D SAC-B PG70-22
TON 8,815.000 $72.000 $68.000 $73.000 $69.000 $81.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(5")
SY 2,300.000 $19.250 $18.000 $20.000 $23.000 $25.000
MOBILIZATION
LS 1.000 $40,000.000 $15,000.000 $5,000.000 $15,000.000 $30,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $5,590.000 $1,400.000 $900.000 $2,000.000 $2,500.000
RUMBLE STRIPS (SHOULDER)
LF 44,014.000 $0.190 $0.120 $0.200 $0.170 $0.150
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 1.000 $220.000 $150.000 $200.000 $210.000 $150.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 14.000 $480.000 $359.750 $390.000 $370.000 $500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 14.000 $569.000 $470.500 $490.000 $475.000 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 6.000 $659.000 $591.100 $610.000 $610.000 $700.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 9.000 $702.000 $688.750 $710.000 $615.000 $800.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $773.000 $689.500 $750.000 $690.000 $950.000
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 2.000 $936.000 $710.810 $820.000 $1,100.000 $1,000.000
REMOVE SM RD SN SUP&AM
EA 46.000 $96.000 $56.000 $58.000 $80.000 $60.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 52,475.000 $0.180 $0.130 $0.140 $0.150 $0.140
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 524.000 $0.370 $0.320 $0.250 $0.350 $0.300
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 14.000 $60.000 $65.000 $35.000 $70.000 $65.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 2.000 $66.000 $65.000 $35.000 $70.000 $65.000
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 7,487.000 $0.190 $0.130 $0.150 $0.150 $0.140
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 46,386.000 $0.170 $0.130 $0.150 $0.150 $0.140
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 512.000 $1.000 $0.710 $0.750 $0.750 $0.750
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 14.000 $106.000 $120.000 $99.000 $127.000 $125.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 2.000 $132.000 $130.000 $99.000 $137.000 $135.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 44,620.000 $0.370 $0.360 $0.310 $0.400 $0.350
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 6,352.000 $0.460 $0.360 $0.310 $0.400 $0.350
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 40,202.000 $0.400 $0.360 $0.310 $0.400 $0.350
REFL PAV MRKR TY I-C
EA 26.000 $3.750 $3.400 $4.000 $3.600 $3.500
REFL PAV MRKR TY II-A-A
EA 1,066.000 $3.500 $3.400 $2.880 $3.600 $3.500
PAV SURF PREP FOR MRK (6")
LF 91,174.000 $0.020 $0.010 $0.010 $0.010 $0.010
PAV SURF PREP FOR MRK (8")
LF 512.000 $0.080 $0.050 $0.010 $0.050 $0.050
PAV SURF PREP FOR MRK (ARROW)
EA 14.000 $8.500 $7.900 $2.000 $8.500 $8.000
PAV SURF PREP FOR MRK (WORD)
EA 2.000 $11.000 $7.900 $2.000 $8.500 $8.000
Totals: $950,789.750 $781,727.270 $799,453.130 $823,158.120 $967,670.260