FORT BEND SS 10 (0187-05-061)

Items: 46

County: FORT BEND
Length: 8.6350 MILES
Highway: SS 10
District: HOUSTON
Control Number: 0187-05-061
DBE Goal: 0.0%
Project: CM 2B25(175)
Guaranty: $100,000.00
Time: 220 WORKING DAYS
Engineer's Estimate: $6,524,455.25
Date: 05/06/2026 (5 weeks ago)
Contract Number: 5263011
Type: ADVANCED TRAFFIC MANAGEMENT SYSTEM
Project ID: A00123433
Contract Type: Federal
Project Description: INSTALL NEW ITS EQUIPMENT AND INFRASTRUCTURE WHERE NO CURRENT SYSTEM EXISTS. THE NEW EQUIPMENT DOES NOT REPLACE OR UPGRADE EXISTING EQUIPMENT.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
EUGENE AMPOMAH
KIALEE GBOSI
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (7)
E
Engineer's Estimate
$6,524,455.25
$5,436,518.97
Over/Under Est: -16.67% -$1,087,936.28
$5,688,472.93
Over/Under Est: -12.81% -$835,982.32
Amt Left: 4.63% $251,953.96
Over/Under Est: -8.95% -$583,952.46
Amt Left: 9.27% $503,983.82
Delta: -4.43% -$252,029.86
$5,988,370.65
Over/Under Est: -8.22% -$536,084.60
Amt Left: 10.15% $551,851.68
Delta: -0.81% -$47,867.86
Over/Under Est: 45.83% $2,990,299.00
Amt Left: 75.02% $4,078,235.28
Delta: -58.89% -$3,526,383.60
$9,977,760.83
Over/Under Est: 52.93% $3,453,305.58
Amt Left: 83.53% $4,541,241.86
Delta: -4.87% -$463,006.58
$11,730,903.20
Over/Under Est: 79.8% $5,206,447.95
Amt Left: 115.78% $6,294,384.23
Delta: -17.57% -$1,753,142.37

Bid Items & Bid Tabulations

46 Total 0 of 46
FORT BEND  |  SS 10  |  HOUSTON  |  0187-05-061  |  05/06/2026  |  $6,524,455.25  |  CM 2B25(175)  |  ADVANCED TRAF MGT SYSTEM  |  220 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THIRD COAST SERVICES LLC
SICE, INC.
ALLSTATE SIGNAL & CONSTRUCTION, LLC
TRAF-TEX, INC.
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, LLC
THE LEVY COMPANY, LLC
MICA CORPORATION
DRILL SHAFT (42 IN)
LF 170.000 $375.000 $284.340 $512.148 $388.990 $573.800 $545.230 $680.000 $761.000
DRILL SHAFT (SIGN MTS) (54 IN)
LF 37.000 $750.000 $695.700 $745.802 $691.180 $641.000 $696.910 $870.000 $945.000
RIPRAP (MOW STRIP)(4 IN)
CY 37.000 $700.000 $622.860 $812.511 $575.000 $764.000 $903.230 $1,000.000 $620.000
MOBILIZATION
LS 1.000 $882,473.000 $543,651.890 $509,460.588 $105,500.000 $179,072.000 $770,221.720 $997,776.080 $879,100.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $3,500.000 $1,850.910 $2,367.175 $2,433.340 $1,245.000 $10,702.620 $10,400.000 $63,435.000
TMA (STATIONARY)
DAY 225.000 $270.000 $355.490 $325.475 $500.000 $245.000 $227.950 $55.000 $2,530.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,500.000 $3.000 $2.840 $4.290 $4.000 $5.300 $3.540 $5.000 $2.820
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,500.000 $1.000 $1.010 $0.992 $2.000 $0.900 $1.180 $1.250 $1.000
MTL W-BEAM GD FEN (TIM POST)
LF 700.000 $27.000 $34.750 $33.457 $24.440 $30.850 $37.810 $32.000 $34.550
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 4.000 $1,600.000 $1,113.970 $1,911.791 $1,716.000 $1,827.000 $2,293.920 $2,100.000 $1,110.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,500.000 $3,618.390 $4,182.042 $3,328.000 $3,938.000 $4,378.980 $4,300.000 $3,595.000
CONDT (PVC) (SCH 80) (2")
LF 3,230.000 $11.000 $11.470 $14.036 $8.440 $13.600 $37.640 $14.000 $17.500
CONDT (PVC) (SCH 80) (2") (BORE)
LF 265.000 $23.000 $30.830 $13.769 $38.630 $31.500 $70.680 $86.000 $75.450
CONDUIT (PREPARE)
LF 1,554.000 $5.000 $4.450 $1.006 $10.000 $1.350 $1.260 $1.500 $11.050
ITS MULTI-DUCT CND (PVC-40)(CONC ENCSE)
LF 120,005.000 $24.000 $18.530 $21.664 $23.940 $23.000 $35.990 $36.000 $28.930
ITS MULTI-DUCT CND (PVC-80)(BORE)
LF 12,550.000 $45.000 $46.460 $23.775 $48.980 $62.900 $108.490 $160.000 $178.800
ITS MULTI-DUCT CND (RMC)
LF 3,820.000 $120.000 $103.020 $119.487 $115.000 $104.000 $122.530 $120.000 $200.250
ELEC CONDR (NO.14) INSULATED
LF 66,920.000 $0.800 $0.590 $0.702 $0.940 $1.000 $0.850 $1.000 $2.200
ELEC CONDR (NO.8) BARE
LF 1,160.000 $1.750 $2.130 $1.174 $1.920 $1.750 $1.620 $1.600 $2.950
ELEC CONDR (NO.8) INSULATED
LF 2,320.000 $2.000 $1.560 $1.844 $1.970 $2.000 $1.990 $1.600 $2.950
ELEC CONDR (NO.6) BARE
LF 1,945.000 $2.500 $1.720 $1.614 $2.080 $2.200 $2.190 $2.050 $3.500
ELEC CONDR (NO.6) INSULATED
LF 2,660.000 $2.500 $2.140 $1.961 $2.350 $2.600 $2.660 $2.050 $3.500
ELEC CONDR (NO.4) BARE
LF 625.000 $2.750 $2.810 $2.378 $3.290 $3.200 $2.800 $2.900 $4.250
ELEC CONDR (NO.4) INSULATED
LF 1,250.000 $3.000 $2.980 $2.698 $3.400 $3.350 $3.170 $2.900 $4.250
ITS GND BOX(PCAST) TY 1 (243636)W/APRN
EA 105.000 $3,800.000 $4,114.700 $4,354.958 $4,583.000 $4,170.000 $4,981.720 $5,000.000 $5,151.000
GROUND BOX TY A (122311)
EA 17.000 $800.000 $817.630 $900.859 $870.000 $1,110.000 $1,345.460 $900.000 $1,435.000
ELC SRV TY D 120/240 100(NS)SS(N)SP(O)
EA 13.000 $6,500.000 $8,218.390 $6,576.868 $6,555.000 $7,408.000 $9,319.260 $6,500.000 $10,061.000
INS OH SN SUP(35 FT BAL TEE)
EA 1.000 $55,000.000 $51,291.100 $53,560.199 $53,021.000 $52,905.000 $57,003.230 $58,000.000 $100,600.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 16.000 $35.000 $38.750 $41.821 $33.800 $39.000 $47.200 $35.000 $87.000
INSTALL DMS (FOUNDATION MTD CABINET)
EA 1.000 $8,750.000 $8,040.480 $13,432.211 $12,750.000 $19,100.000 $7,853.310 $12,500.000 $43,481.000
SYSTEM INTEGRATION
LS 1.000 $10,000.000 $4,020.250 $7,291.092 $10,000.000 $23,400.000 $39,173.630 $35,000.000 $44,707.000
ITS RVSD SYSTEM (DATA COLLECTION ONLY)
EA 5.000 $10,000.000 $7,960.690 $9,102.844 $10,260.000 $15,196.000 $14,547.670 $11,700.000 $17,583.000
ITS POLE (55 FT)(110 MPH)
EA 8.000 $21,000.000 $22,218.920 $23,129.193 $22,737.000 $20,185.000 $29,003.490 $24,500.000 $26,010.000
ITS POLE MNTD CAB (TY 2)(CONF 1)
EA 9.000 $6,500.000 $5,016.500 $4,489.594 $6,105.000 $6,680.000 $11,073.750 $5,500.000 $8,455.000
CCTV FIELD EQUIPMENT (DIGITAL)
EA 9.000 $6,750.000 $6,303.820 $7,171.669 $8,275.000 $8,238.000 $8,580.750 $8,800.000 $12,266.000
CCTV MOUNT (MAST)
EA 1.000 $600.000 $737.710 $648.108 $100.000 $2,038.000 $377.220 $240.000 $1,664.000
FIBER OPTIC CBL (SINGLE-MODE)(12 FIBER)
LF 28,815.000 $1.250 $1.050 $1.331 $0.810 $1.370 $3.410 $2.200 $4.940
FIBER OPTIC FUSION SPLICE
EA 156.000 $100.000 $67.260 $102.162 $292.050 $45.500 $71.890 $65.000 $103.850
FIBER OPTIC PATCH PANEL (12 POSITION)
EA 14.000 $1,200.000 $1,301.100 $1,661.150 $883.900 $201.300 $1,734.220 $1,200.000 $1,535.000
FIBER OPTIC CBL(SINGLE-MODE)(144 FIBER)
LF 72,115.000 $2.750 $2.670 $2.656 $2.620 $3.050 $4.580 $3.200 $6.020
FIBER OPTIC PATCH PANEL (144 POSITIONS)
EA 4.000 $2,500.000 $2,801.990 $2,827.740 $1,761.780 $3,023.000 $13,351.320 $3,700.000 $5,950.000
FIBER OPTIC CBL (SINGLE-MODE)(6 FIBER)
LF 20,185.000 $1.000 $1.130 $1.620 $0.700 $1.450 $1.590 $2.200 $4.910
FIBER OPTIC PATCH PANEL (6 POSITION)
EA 4.000 $2,500.000 $1,010.630 $1,363.908 $922.340 $300.000 $1,344.820 $1,200.000 $1,404.000
ITS GRND MNT CAB (TY 6)(CONF 2)
EA 3.000 $17,000.000 $12,552.520 $14,972.944 $15,850.000 $15,300.000 $21,305.440 $17,500.000 $29,884.000
COMMUNICATIONS HUB BUILDING
EA 1.000 $35,000.000 $34,935.410 $40,905.732 $37,700.000 $38,100.000 $54,154.500 $47,000.000 $72,275.000
SUBSURFACE UTIL LOCATE (OUTSIDE RDBED)
EA 20.000 $1,500.000 $1,174.710 $1,000.289 $2,695.000 $748.000 $882.700 $1,000.000 $3,015.000
Totals: $6,524,455.250 $5,436,518.970 $5,688,472.927 $5,940,502.790 $5,988,370.650 $9,514,754.250 $9,977,760.830 $11,730,903.200
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) $46,134.00
PUBLIC UTILITY FORCE ACCT WORK (PART) $20,000.00
MATERIAL FURNISHED BY THE STATE (PART) $223,500.00
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $8,000.00
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $5,600.00
Total: $303,234.00