Show Job Controls
Bid Cobra

FORT BEND FM 521 (0111-03-063)

Items: 63

County: FORT BEND
Length: N/A
Highway: FM 521
District: HOUSTON
Control Number: 0111-03-063
DBE Goal: N/A
Project: C 111-3-63
Guaranty: N/A
Time: 47 WORKING DAYS
Engineer's Estimate: $1,694,331.67
Date: 03/04/2022 (4 years ago)
Contract Number: N/A
Type: SURFACING/ROADWAY RESTORATION
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (3)
E
Engineer's Estimate
$1,694,331.67
$2,089,681.98
Over/Under Est: 23.33% $395,350.31
Over/Under Est: 32.71% $554,190.10
Amt Left: 7.6% $158,839.79
Over/Under Est: 34.26% $580,464.01
Amt Left: 8.86% $185,113.70
Delta: -1.17% -$26,273.91

Bid Items & Bid Tabulations

63 Total 0 of 63
FORT BEND  |  FM 521  |  HOUSTON  |  0111-03-063  |  03/04/2022  |  $1,694,331.67  |  C 111-3-63  |  SURF/ROADWAY RESTOR  |  47 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
DURWOOD GREENE CONSTRUCTION CO.
JAMES CONSTRUCTION GROUP, LLC
TEXAS MATERIALS GROUP, INC.
REMOVING CONCRETE(MOW STRIP)
LF 510.000 $8.870 $15.000 $21.000 $9.250
BACKFILL (TY A OR B)
STA 251.610 $191.450 $160.000 $77.000 $162.000
FL BS (CMP IN PLC)(TY D GR 4)(FNAL POS)
CY 9.000 $150.000 $100.000 $250.000 $670.500
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 5,000.000 $21.330 $17.000 $46.000 $20.000
PLANE ASPH CONC PAV (1.5")
SY 107,730.000 $1.440 $2.500 $1.900 $1.900
RIPRAP (MOW STRIP)(4 IN)
CY 98.000 $432.670 $800.000 $455.000 $907.000
RAIL (TY T631)
LF 350.000 $75.060 $95.000 $71.140 $75.750
REMOVE STR (RAIL)
LF 387.500 $27.150 $45.000 $8.690 $107.000
MOBILIZATION
LS 1.000 $154,000.000 $125,000.000 $145,000.000 $220,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $5,281.660 $6,000.000 $19,000.000 $798.750
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 25,213.000 $0.200 $0.260 $0.370 $0.130
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 20,015.000 $0.200 $0.300 $0.330 $0.150
MTL W-BEAM GD FEN (TIM POST)
LF 1,250.000 $19.410 $27.000 $22.350 $24.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 1.000 $1,290.650 $1,500.000 $1,335.000 $1,422.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 2.000 $1,500.000 $1,400.000 $1,126.000 $1,200.000
REMOVE METAL BEAM GUARD FENCE
LF 900.000 $1.610 $2.000 $1.940 $2.100
REMOVE TERMINAL ANCHOR SECTION
EA 1.000 $114.670 $300.000 $267.000 $285.000
GUARDRAIL END TREATMENT (INSTALL)
EA 11.000 $2,418.890 $3,450.000 $3,054.000 $3,252.000
GUARDRAIL END TREATMENT (REMOVE)
EA 10.000 $186.890 $300.000 $267.000 $285.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 36.000 $168.420 $250.000 $209.000 $223.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 3.000 $220.170 $300.000 $244.000 $260.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 2.000 $546.380 $700.000 $586.000 $624.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 38.000 $522.310 $500.000 $438.000 $467.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 16.000 $510.300 $600.000 $552.000 $588.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 11.000 $813.250 $900.000 $799.000 $851.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $773.750 $1,200.000 $1,076.000 $1,146.000
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 1.000 $885.850 $1,100.000 $997.000 $1,062.000
REMOVE SM RD SN SUP&AM
EA 58.000 $85.820 $60.000 $49.000 $52.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 20.000 $94.000 $75.000 $60.000 $64.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2
EA 31.000 $18.540 $35.000 $30.000 $32.000
WK ZN PAV MRK NON-REMOV (W)4"(BRK)
LF 960.000 $0.250 $0.150 $0.260 $0.430
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 41,719.000 $0.210 $0.150 $0.260 $0.300
WK ZN PAV MRK NON-REMOV (W)6"(BRK)
LF 960.000 $0.180 $0.220 $0.280 $0.480
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 41,719.000 $0.240 $0.220 $0.280 $0.320
WK ZN PAV MRK NON-REMOV (W)8"(SLD)
LF 11,024.000 $0.420 $0.400 $0.550 $0.640
WK ZN PAV MRK NON-REMOV (W)24"(SLD)
LF 710.000 $1.840 $2.500 $3.000 $3.200
WK ZN PAV MRK NON-REMOV (W)(ARROW)
EA 72.000 $62.000 $45.000 $55.000 $59.000
WK ZN PAV MRK NON-REMOV (W)(RR XING)
EA 4.000 $112.000 $300.000 $221.000 $236.000
WK ZN PAV MRK NON-REMOV(W)(WORD)
EA 68.000 $52.980 $55.000 $55.000 $64.000
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 2,450.000 $0.250 $0.150 $0.260 $0.430
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 31,326.000 $0.240 $0.150 $0.260 $0.280
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 2,450.000 $0.240 $0.220 $0.280 $0.480
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 31,326.000 $0.240 $0.220 $0.280 $0.320
WK ZN PAV MRK NON-REMOV (Y)24"(SLD)
LF 188.000 $1.580 $2.500 $3.000 $3.460
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 7,746.000 $0.860 $0.700 $0.800 $1.040
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 567.000 $6.150 $5.000 $6.000 $6.400
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 50.000 $124.300 $110.000 $95.000 $106.500
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 44.000 $130.730 $125.000 $100.000 $111.830
REFL PAV MRK TY I (W)(RR XING)(100MIL)
EA 2.000 $365.000 $500.000 $336.000 $560.000
REFL PAV MRK TY I (Y)24"(SLD)(100MIL)
LF 94.000 $5.200 $5.000 $6.000 $6.400
RE PV MRK TY I(BLACK)6"(SHADOW)(100MIL)
LF 1,350.000 $0.610 $0.600 $0.550 $1.300
PAVEMENT SEALER 6"
LF 1,350.000 $0.140 $0.100 $0.120 $0.200
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 1,350.000 $0.510 $0.350 $0.490 $0.590
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 80.000 $0.440 $0.600 $0.490 $1.600
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 2,450.000 $0.400 $0.350 $0.490 $0.530
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 46,535.000 $0.430 $0.350 $0.490 $0.530
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 50,298.000 $0.710 $0.500 $0.790 $0.750
REFL PAV MRKR TY I-C
EA 445.000 $3.520 $4.000 $4.000 $4.250
REFL PAV MRKR TY II-A-A
EA 2,352.000 $3.420 $4.000 $4.000 $4.250
D-GR HMA TY-D SAC-A PG70-22
TON 9,016.430 $84.320 $120.000 $120.000 $131.500
TACK COAT
GAL 12,206.000 $3.350 $3.000 $2.100 $3.000
TMA (STATIONARY)
DAY 30.000 $262.860 $400.000 $298.000 $320.000
TMA (MOBILE OPERATION)
DAY 121.000 $424.060 $50.000 $648.000 $9.000
Totals: $1,694,331.667 $2,089,681.980 $2,248,521.775 $2,274,795.685