FISHER FM 57 (0317-02-017)
Items: 31
County: FISHER
Length: 0.0000 MILES
Highway: FM 57
District: ABILENE
Control Number: 0317-02-017
DBE Goal: 0.0%
Project: C 317-2-17
Guaranty: $71,000.00
Time: 72 WORKING DAYS
Engineer's Estimate: $3,570,711.55
Date: 10/08/2025 (8 months ago)
Contract Number: 10253018
Type: RESURFACE ROADWAY
Project ID: A00195453
Project Description: OVERLAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
MICHAEL WITTIE
JOSE CABRERA
FISHER FM 57 (0317-02-017)
Project Name: N/A
Project: C 317-2-17
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: US 180
Limits To: JONES COUNTY
Project Description: OVERLAY
JONES FM 57 (0317-03-015)
Project Name: FM 57 OVERLAY JONES COUNTY 0317-03
Project: C 317-3-15
Length: 0.0000 MILES
Project Type: OVERLAY
Limits From: FISHER COUNTY
Limits To: US 83
Project Description: OVERLAY
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$3,570,711.55 | |||
| $2,898,664.55 |
-18.82%
-$672,047.00
|
|||
| $2,982,134.23 |
-16.48%
-$588,577.32
|
2.88%
$83,469.68
|
||
| $3,111,166.05 |
-12.87%
-$459,545.50
|
7.33%
$212,501.50
|
-4.33%
-$129,031.82
|
|
| $3,167,781.56 |
-11.28%
-$402,929.99
|
9.28%
$269,117.01
|
-1.82%
-$56,615.51
|
|
| $3,299,331.95 |
-7.6%
-$271,379.60
|
13.82%
$400,667.40
|
-4.15%
-$131,550.39
|
|
| $3,541,708.10 |
-0.81%
-$29,003.45
|
22.18%
$643,043.55
|
-7.35%
-$242,376.15
|
|
| $3,697,998.11 |
3.56%
$127,286.56
|
27.58%
$799,333.56
|
-4.41%
-$156,290.01
|
E
Engineer's Estimate
$3,570,711.55
1
Awarded
$2,898,664.55
Over/Under Est:
-18.82%
-$672,047.00
$2,982,134.23
Over/Under Est:
-16.48%
-$588,577.32
Amt Left:
2.88%
$83,469.68
$3,111,166.05
Over/Under Est:
-12.87%
-$459,545.50
Amt Left:
7.33%
$212,501.50
Delta:
-4.33%
-$129,031.82
$3,167,781.56
Over/Under Est:
-11.28%
-$402,929.99
Amt Left:
9.28%
$269,117.01
Delta:
-1.82%
-$56,615.51
$3,299,331.95
Over/Under Est:
-7.6%
-$271,379.60
Amt Left:
13.82%
$400,667.40
Delta:
-4.15%
-$131,550.39
$3,541,708.10
Over/Under Est:
-0.81%
-$29,003.45
Amt Left:
22.18%
$643,043.55
Delta:
-7.35%
-$242,376.15
$3,697,998.11
Over/Under Est:
3.56%
$127,286.56
Amt Left:
27.58%
$799,333.56
Delta:
-4.41%
-$156,290.01
| Subcontractor | Percentage | Amount |
|---|---|---|
| STRIPE-A-ZONE, LLC | 2.83% | $82,032.21 |
| HJC FARMS, INC. | 1.75% | $50,726.63 |
| Total: | 4.58% | $132,758.84 |
Bid Items & Bid Tabulations
31
Total
0 of 31
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $5,000.00 |
| SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (NON-PART) | $10,000.00 |
| Total: | $15,000.00 |