FISHER US 180 (0296-02-033)
Items: 69
County: FISHER
Length: N/A
Highway: US 180
District: ABILENE
Control Number: 0296-02-033
DBE Goal: N/A
Project: BR 2018(951)
Guaranty: N/A
Time: 200 WORKING DAYS
Engineer's Estimate: $2,051,214.25
Date: 06/06/2018 (8 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (8)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$2,051,214.25 | |||
| $1,763,518.63 |
-14.03%
-$287,695.62
|
|||
| $1,799,406.52 |
-12.28%
-$251,807.73
|
2.04%
$35,887.89
|
||
| $1,946,467.13 |
-5.11%
-$104,747.12
|
10.37%
$182,948.50
|
-8.17%
-$147,060.61
|
|
| $1,988,874.26 |
-3.04%
-$62,339.99
|
12.78%
$225,355.63
|
-2.18%
-$42,407.13
|
|
| $2,081,052.70 |
1.45%
$29,838.45
|
18.01%
$317,534.07
|
-4.63%
-$92,178.44
|
|
| $2,209,726.49 |
7.73%
$158,512.24
|
25.3%
$446,207.86
|
-6.18%
-$128,673.79
|
|
| $2,416,840.95 |
17.82%
$365,626.70
|
37.05%
$653,322.32
|
-9.37%
-$207,114.46
|
|
| $2,434,360.00 |
18.68%
$383,145.75
|
38.04%
$670,841.37
|
-0.72%
-$17,519.05
|
E
Engineer's Estimate
$2,051,214.25
1
Awarded
$1,763,518.63
Over/Under Est:
-14.03%
-$287,695.62
$1,799,406.52
Over/Under Est:
-12.28%
-$251,807.73
Amt Left:
2.04%
$35,887.89
$1,946,467.13
Over/Under Est:
-5.11%
-$104,747.12
Amt Left:
10.37%
$182,948.50
Delta:
-8.17%
-$147,060.61
$1,988,874.26
Over/Under Est:
-3.04%
-$62,339.99
Amt Left:
12.78%
$225,355.63
Delta:
-2.18%
-$42,407.13
$2,081,052.70
Over/Under Est:
1.45%
$29,838.45
Amt Left:
18.01%
$317,534.07
Delta:
-4.63%
-$92,178.44
$2,209,726.49
Over/Under Est:
7.73%
$158,512.24
Amt Left:
25.3%
$446,207.86
Delta:
-6.18%
-$128,673.79
$2,416,840.95
Over/Under Est:
17.82%
$365,626.70
Amt Left:
37.05%
$653,322.32
Delta:
-9.37%
-$207,114.46
$2,434,360.00
Over/Under Est:
18.68%
$383,145.75
Amt Left:
38.04%
$670,841.37
Delta:
-0.72%
-$17,519.05
Bid Items & Bid Tabulations
69
Total