FAYETTE CR (0913-28-073)
Items: 44
County: FAYETTE
Length: N/A
Highway: CR
District: YOAKUM
Control Number: 0913-28-073
DBE Goal: N/A
Project: BR 2B20(275)
Guaranty: N/A
Time: 251 WORKING DAYS
Engineer's Estimate: $1,425,163.50
Date: 01/07/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Bidders (3)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,425,163.50 | |||
| $1,498,742.87 |
5.16%
$73,579.37
|
|||
| $1,685,718.60 |
18.28%
$260,555.10
|
12.48%
$186,975.73
|
||
| $1,716,989.79 |
20.48%
$291,826.29
|
14.56%
$218,246.92
|
-1.86%
-$31,271.19
|
E
Engineer's Estimate
$1,425,163.50
1
Awarded
$1,498,742.87
Over/Under Est:
5.16%
$73,579.37
$1,685,718.60
Over/Under Est:
18.28%
$260,555.10
Amt Left:
12.48%
$186,975.73
$1,716,989.79
Over/Under Est:
20.48%
$291,826.29
Amt Left:
14.56%
$218,246.92
Delta:
-1.86%
-$31,271.19
| Subcontractor | Percentage | Amount |
|---|---|---|
| GREGORY PILE DRIVING, INC. | 10.62% | $159,519.30 |
| ROADWAY SPECIALTIES, INC. | 4.76% | $71,498.29 |
| D. I. J. CONSTRUCTION, INC. | 4.56% | $68,494.16 |
| BATTEN DRILLING, INC. | 4.04% | $60,683.43 |
| HEMPHILL WBE PILE DRIVING CO. | 3.21% | $48,216.29 |
| CEN TEX HYDROSEED, INC. | 1.36% | $20,428.08 |
| SOUTH TEXAS TRAFFIC ALLIANCE INC. | 0.73% | $10,965.07 |
| GK CONSTRUCTION, LLC | 0.62% | $9,312.80 |
| RAY'S CRANE SERVICE | 0.56% | $8,411.56 |
| Total: | 30.46% | $457,528.98 |
Bid Items & Bid Tabulations
44
Total
0 of 44