FAYETTE CR (0913-28-067)

Items: 41

County: FAYETTE
Length: N/A
Highway: CR
District: YOAKUM
Control Number: 0913-28-067
DBE Goal: N/A
Project: BR 1502(636)
Guaranty: N/A
Time: 120 WORKING DAYS
Engineer's Estimate: $852,144.00
Date: 06/04/2019 (7 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$852,144.00
1
$872,849.77
Over/Under Est: 2.43% $20,705.77
Over/Under Est: 9.06% $77,238.45
Amt Left: 6.48% $56,532.68
$955,084.50
Over/Under Est: 12.08% $102,940.50
Amt Left: 9.42% $82,234.73
Delta: -2.77% -$25,702.05
Over/Under Est: 23% $196,024.60
Amt Left: 20.09% $175,318.83
Delta: -9.75% -$93,084.10
Over/Under Est: 23.87% $203,379.80
Amt Left: 20.93% $182,674.03
Delta: -0.70% -$7,355.20
$1,105,033.00
Over/Under Est: 29.68% $252,889.00
Amt Left: 26.6% $232,183.23
Delta: -4.69% -$49,509.20

Bid Items & Bid Tabulations

41 Total 0 of 41
FAYETTE  |  CR  |  YOAKUM  |  0913-28-067  |  06/04/2019  |  $852,144.00  |  BR 1502(636)  |  REPLACE BRIDGE AND APPROACHES  |  120 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
TREVWAY, INC.
FUQUA CONSTRUCTION CO., INC.
SB CONTRACTORS LLC
ACME BRIDGE COMPANY, INC.
PROJECT ALLIED RESOURCES, LLC
J.D. ABRAMS, L.P.
PREPARING ROW
STA 8.800 $1,500.000 $1,000.000 $1,372.273 $2,500.000 $3,100.000 $4,160.000 $11,000.000
EXCAVATION (ROADWAY)
CY 158.000 $25.000 $11.000 $20.000 $12.000 $21.000 $18.800 $34.000
EXCAVATION (CHANNEL)
CY 351.000 $30.000 $6.000 $20.000 $12.000 $25.000 $29.600 $51.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 966.000 $25.000 $11.000 $20.000 $28.000 $21.000 $28.100 $41.000
BLADING
HR 46.000 $100.000 $15.000 $29.000 $65.000 $121.000 $133.000 $140.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 1,330.000 $2.000 $0.500 $3.776 $0.500 $1.100 $3.090 $1.100
BROADCAST SEED (TEMP) (WARM)
SY 665.000 $2.000 $0.500 $5.034 $0.500 $1.000 $1.050 $0.950
BROADCAST SEED (TEMP) (COOL)
SY 665.000 $2.000 $0.500 $5.030 $0.500 $1.000 $1.050 $0.950
VEGETATIVE WATERING
MG 19.000 $100.000 $25.000 $56.000 $45.000 $53.300 $12.300 $16.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 447.000 $95.000 $100.000 $46.000 $100.000 $102.000 $120.000 $110.000
ASPH (RC-250)
GAL 235.000 $20.000 $23.370 $10.000 $10.000 $15.800 $16.200 $9.500
AGGR(TY-E GR-5 SAC-B)
CY 13.000 $400.000 $750.000 $300.000 $440.000 $754.000 $773.000 $435.000
AGGR(TY-PE GR-4 SAC-B)
CY 13.000 $400.000 $710.000 $300.000 $440.000 $754.000 $773.000 $435.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 399.000 $20.000 $17.000 $10.000 $10.000 $15.800 $16.200 $9.500
CEM STABIL BKFL
CY 60.000 $100.000 $100.000 $150.000 $125.000 $188.000 $178.000 $170.000
DRILL SHAFT (24 IN)
LF 327.000 $175.000 $400.000 $281.667 $195.000 $265.000 $232.000 $245.000
DRILL SHAFT (30 IN)
LF 204.000 $200.000 $419.000 $377.676 $265.000 $407.000 $290.000 $380.000
CL C CONC (ABUT)
CY 47.600 $1,000.000 $450.000 $1,400.000 $1,100.000 $1,200.000 $1,150.000 $1,350.000
CL C CONC (CAP)
CY 13.200 $1,100.000 $700.000 $1,400.000 $2,000.000 $1,800.000 $1,330.000 $3,000.000
CL C CONC (COLUMN)
CY 6.000 $1,200.000 $900.000 $1,400.000 $2,000.000 $1,530.000 $1,160.000 $3,450.000
REINF CONC SLAB (BOX BEAM)
SF 1,701.000 $20.000 $17.500 $16.000 $25.000 $17.900 $20.800 $27.500
REINF CONC SLAB (SLAB BEAM)
SF 2,600.000 $20.000 $17.500 $16.000 $20.000 $18.200 $21.000 $22.000
SHEAR KEY
CY 8.600 $500.000 $100.000 $1,400.000 $750.000 $565.000 $549.000 $205.000
PRESTR CONC BOX BEAM (4B20)
LF 258.000 $175.000 $200.000 $234.056 $234.000 $238.000 $203.000 $166.000
PRESTR CONC BOX BEAM (5B20)
LF 129.000 $180.000 $229.000 $234.056 $234.000 $250.000 $203.000 $169.000
PRESTR CONC SLAB BEAM (5SB15)
LF 492.500 $170.000 $192.000 $223.648 $215.000 $264.000 $202.000 $152.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 514.000 $130.000 $122.000 $120.000 $140.000 $173.000 $152.000 $160.000
RAIL (TY T631)
LF 386.000 $75.000 $79.120 $100.680 $82.000 $89.600 $103.000 $80.000
ARMOR JOINT (SEALED)
LF 88.000 $75.000 $55.000 $79.500 $75.000 $121.000 $139.000 $145.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $20,000.000 $20,000.000 $12,000.000 $10,000.000 $12,200.000 $24,700.000 $15,000.000
MOBILIZATION
LS 1.000 $85,000.000 $85,000.000 $82,236.940 $95,000.000 $80,000.000 $117,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 9.000 $3,000.000 $800.000 $840.000 $2,500.000 $3,000.000 $2,230.000 $1,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 120.000 $50.000 $5.000 $56.003 $65.000 $24.700 $53.000 $26.400
ROCK FILTER DAMS (REMOVE)
LF 120.000 $10.000 $1.000 $37.692 $20.000 $7.900 $16.700 $8.400
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,930.000 $3.000 $1.000 $2.957 $6.000 $3.300 $4.550 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,930.000 $1.000 $0.500 $1.573 $0.500 $1.400 $1.320 $1.500
MTL W-BEAM GD FEN (TIM POST)
LF 200.000 $25.000 $17.000 $25.170 $41.000 $29.100 $24.700 $26.000
GUARDRAIL END TREATMENT (INSTALL)
EA 8.000 $2,400.000 $2,500.000 $3,083.325 $3,000.000 $2,790.000 $3,010.000 $2,500.000
WIRE FENCE (TY A)
LF 427.000 $15.000 $4.000 $20.000 $13.000 $18.800 $20.800 $25.000
WIRE FENCE (WATER GAP)
LF 200.000 $35.000 $9.000 $30.000 $50.000 $58.000 $51.000 $70.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 14.000 $21.000 $11.000 $12.585 $40.000 $20.900 $32.400 $20.000
Totals: $852,144.000 $872,849.770 $929,382.477 $955,084.500 $1,048,168.600 $1,055,523.800 $1,105,033.000