FAYETTE CR (0913-28-066)

Items: 34

County: FAYETTE
Length: N/A
Highway: CR
District: YOAKUM
Control Number: 0913-28-066
DBE Goal: N/A
Project: BR 2014(600)
Guaranty: N/A
Time: 0 X
Engineer's Estimate: $412,051.50
Date: 03/06/2019 (7 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$412,051.50
Over/Under Est: -6.49% -$26,741.10
$399,004.55
Over/Under Est: -3.17% -$13,046.95
Amt Left: 3.55% $13,694.15
Over/Under Est: 13.98% $57,617.35
Amt Left: 21.89% $84,358.45
Delta: -17.71% -$70,664.30
Over/Under Est: 19.63% $80,867.35
Amt Left: 27.93% $107,608.45
Delta: -4.95% -$23,250.00
Over/Under Est: 54.01% $222,552.80
Amt Left: 64.7% $249,293.90
Delta: -28.74% -$141,685.45
Over/Under Est: 77.45% $319,122.65
Amt Left: 89.76% $345,863.75
Delta: -15.22% -$96,569.85

Bid Items & Bid Tabulations

34 Total 0 of 34
FAYETTE  |  CR  |  YOAKUM  |  0913-28-066  |  03/06/2019  |  $412,051.50  |  BR 2014(600)  |  REPLACE BRIDGE AND APPROACHES  |  0 X
Item Code
Description
Unit
Quantity
Engineer's Estimate
JOHN REED AND COMPANY, LLC
TREVWAY, INC.
DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC.
HILL COUNTRY BRIDGE, INC.
ANGEL BROTHERS HOLDINGS CORP.
ISI CONTRACTING, INC.
PREPARING ROW
STA 3.250 $2,500.000 $500.000 $915.000 $1,500.000 $5,160.000 $6,600.000 $9,000.000
EXCAVATION (ROADWAY)
CY 148.100 $15.000 $30.000 $30.120 $30.000 $26.300 $28.000 $32.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 116.300 $20.000 $30.000 $25.570 $15.000 $29.450 $60.000 $55.000
BLADING
HR 20.000 $100.000 $20.000 $50.000 $100.000 $90.000 $120.000 $65.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 667.000 $2.000 $0.500 $3.000 $1.750 $2.000 $4.000 $4.500
CELL FBR MLCH SEED(TEMP)(WARM)
SY 167.000 $2.000 $0.500 $3.000 $6.900 $6.900 $8.000 $11.500
CELL FBR MLCH SEED(TEMP)(COOL)
SY 167.000 $2.000 $0.500 $3.000 $6.900 $6.900 $8.000 $11.500
VEGETATIVE WATERING
MG 5.610 $100.000 $20.000 $100.000 $100.000 $180.000 $150.000 $45.000
FL BS (CMP IN PLC)(TY A GR 5)(FNAL POS)
CY 261.000 $100.000 $70.000 $80.000 $100.000 $110.500 $120.000 $91.000
ASPH (RC-250)
GAL 211.000 $5.000 $15.000 $40.000 $10.000 $15.800 $20.000 $4.000
AGGR(TY-PE GR-3 SAC-B)
CY 12.000 $125.000 $600.000 $757.000 $300.000 $631.000 $600.000 $425.000
AGGR(TY-PE GR-5 SAC-B)
CY 8.000 $125.000 $600.000 $757.000 $300.000 $631.000 $900.000 $600.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 422.000 $6.000 $15.000 $18.000 $10.000 $15.800 $15.000 $3.000
CEM STABIL BKFL
CY 100.400 $120.000 $68.000 $92.000 $200.000 $120.500 $220.000 $50.000
TRENCH EXCAVATION PROTECTION
LF 32.000 $10.000 $5.000 $55.000 $1.000 $70.000 $170.000 $2.500
TEMPORARY SPL SHORING
SF 1,403.000 $15.000 $1.000 $9.000 $3.000 $6.000 $40.000 $100.000
CMP (GAL STL 24 IN)
LF 8.000 $70.000 $40.000 $78.880 $110.000 $80.000 $450.000 $300.000
CONC BOX CULV (8 FT X 7 FT)
LF 128.000 $560.000 $700.000 $748.000 $1,200.000 $837.000 $1,200.000 $900.000
WINGWALL (PW - 1) (HW=8 FT)
EA 2.000 $26,000.000 $10,000.000 $17,000.000 $25,000.000 $32,250.000 $35,000.000 $30,000.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 2.000 $1,200.000 $1,000.000 $1,500.000 $1,500.000 $1,500.000 $2,000.000 $5,300.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $20,000.000 $30,000.000 $20,000.000 $35,000.000 $21,600.000 $10,000.000 $70,000.000
MOBILIZATION
LS 1.000 $26,500.000 $40,000.000 $40,000.000 $40,000.000 $37,000.000 $70,000.000 $60,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 4.000 $2,500.000 $1,000.000 $1,200.000 $1,000.000 $2,565.000 $1,100.000 $3,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 75.000 $50.000 $30.000 $10.000 $40.000 $24.250 $50.000 $75.000
ROCK FILTER DAMS (REMOVE)
LF 75.000 $10.000 $5.000 $3.000 $15.000 $13.300 $20.000 $40.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 725.000 $3.000 $3.000 $3.000 $3.000 $2.800 $4.000 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 725.000 $1.000 $1.000 $1.000 $1.000 $0.500 $1.000 $2.500
DRIVEWAYS (BASE)
SY 73.300 $20.000 $25.000 $38.000 $25.000 $26.300 $50.000 $150.000
MTL W-BEAM GD FEN (TIM POST)
LF 75.000 $25.000 $20.000 $30.000 $20.000 $21.050 $40.000 $31.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 75.000 $65.000 $42.000 $25.000 $45.000 $44.200 $70.000 $110.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,200.000 $2,032.000 $2,566.000 $2,100.000 $2,138.000 $4,000.000 $3,500.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 8.000 $20.000 $10.000 $16.000 $20.000 $18.000 $30.000 $40.000
NO. OF WORKING DAYS
$/D 2,000.000 $60.000 $60.000 $43.000 $40.000 $60.000 $50.000 $60.000
TMA (STATIONARY)
DAY 3.000 $500.000 $150.000 $1,000.000 $350.000 $1,100.000 $300.000 $360.000
Totals: $412,051.500 $385,310.400 $399,004.553 $469,668.850 $492,918.855 $634,604.300 $731,174.150