FAYETTE FM 154 (0334-08-033)

Items: 45

County: FAYETTE
Length: N/A
Highway: FM 154
District: YOAKUM
Control Number: 0334-08-033
DBE Goal: N/A
Project: BR 2017(488)
Guaranty: N/A
Time: 45 WORKING DAYS
Engineer's Estimate: $497,410.00
Date: 01/05/2017 (9 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$497,410.00
$519,583.10
Over/Under Est: 4.46% $22,173.10
Over/Under Est: 21.14% $105,154.60
Amt Left: 15.97% $82,981.50
$644,291.10
Over/Under Est: 29.53% $146,881.10
Amt Left: 24% $124,708.00
Delta: -6.92% -$41,726.50
Over/Under Est: 35.98% $178,975.80
Amt Left: 30.18% $156,802.70
Delta: -4.98% -$32,094.70
Over/Under Est: 36.27% $180,431.56
Amt Left: 30.46% $158,258.46
Delta: -0.22% -$1,455.76
Over/Under Est: 65.81% $327,343.30
Amt Left: 58.73% $305,170.20
Delta: -21.67% -$146,911.74

Bid Items & Bid Tabulations

45 Total 0 of 45
FAYETTE  |  FM 154  |  YOAKUM  |  0334-08-033  |  01/05/2017  |  $497,410.00  |  BR 2017(488)  |  REPLACE BRIDGE AND APPROACHES  |  45 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
3LW MANAGEMENT, LLC
ANGEL BROTHERS HOLDINGS CORP.
RELMCO, INC.
DEAN WORD COMPANY, LTD.
CURRAN CONTRACTING COMPANY
ACME BRIDGE COMPANY, INC.
PREPARING ROW(TREE)(5" TO 12" DIA)
EA 7.000 $900.000 $450.000 $3,000.000 $3,000.000 $1,560.000 $1,689.450 $1,000.000
SUBGRADE WIDENING (ORD COMP)
STA 6.600 $650.000 $460.000 $3,200.000 $2,000.000 $1,955.547 $550.000 $1,000.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 150.000 $25.000 $35.000 $60.000 $50.000 $39.248 $31.200 $110.000
BLADING
HR 10.000 $125.000 $150.000 $112.000 $160.000 $119.790 $134.650 $190.000
BROADCAST SEED (PERM) (RURAL) (SANDY)
SY 1,600.000 $1.000 $2.300 $0.550 $1.500 $0.478 $0.500 $0.650
VEGETATIVE WATERING
MG 8.900 $100.000 $85.000 $50.000 $200.000 $115.500 $181.740 $70.000
FL BS (CMP IN PLC)(TYE GR1-2)(FNAL POS)
CY 145.000 $120.000 $70.000 $170.000 $120.000 $167.324 $125.000 $140.000
PRIME COAT (MC-30)
GAL 154.000 $10.000 $6.000 $35.000 $20.000 $10.043 $27.900 $34.800
AGGR(TY-PE GR-4 SAC-B)
CY 23.000 $150.000 $175.000 $450.000 $235.000 $409.629 $670.150 $837.000
ASPH (AC-15P OR AC-10-2TR OR CRS-2P)
GAL 1,018.000 $4.000 $6.000 $8.000 $5.500 $6.083 $16.100 $20.100
HMCL ACP TY-D AC-0.6
TON 55.000 $150.000 $300.000 $350.000 $160.000 $199.111 $117.050 $274.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(8")
SY 125.000 $75.000 $75.000 $100.000 $100.000 $87.252 $73.450 $274.000
CEM STABIL BKFL
CY 250.000 $130.000 $145.000 $210.000 $125.000 $157.300 $165.350 $232.000
TEMPORARY SPL SHORING
SF 1,200.000 $25.000 $25.000 $30.000 $30.000 $73.700 $6.600 $25.000
RIPRAP (STONE COMMON)(DRY)(12 IN)
CY 30.000 $200.000 $170.000 $260.000 $250.000 $159.500 $142.600 $75.000
CONC BOX CULV (10 FT X 8 FT)
LF 168.000 $800.000 $675.000 $530.000 $1,150.000 $1,080.543 $1,200.000 $1,280.000
WINGWALL (PW - 1) (HW=10 FT)
EA 2.000 $15,000.000 $22,000.000 $44,000.000 $30,000.000 $38,460.000 $45,000.000 $33,400.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $15,000.000 $10,000.000 $11,000.000 $26,000.000 $20,900.000 $46,000.000 $35,500.000
MOBILIZATION
LS 1.000 $40,000.000 $40,000.000 $58,000.000 $65,000.000 $67,611.388 $60,000.000 $62,300.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 3.000 $4,000.000 $8,000.000 $800.000 $2,500.000 $2,786.195 $6,800.000 $837.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 50.000 $35.000 $50.000 $50.000 $46.250 $43.732 $31.100 $59.200
ROCK FILTER DAMS (REMOVE)
LF 50.000 $10.000 $10.000 $12.000 $11.150 $10.546 $5.260 $14.300
TEMP SEDMT CONT FENCE (INSTALL)
LF 820.000 $4.500 $4.000 $2.700 $2.480 $2.350 $2.550 $3.200
TEMP SEDMT CONT FENCE (REMOVE)
LF 820.000 $2.000 $1.000 $0.600 $0.550 $0.520 $0.550 $0.700
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 720.000 $50.000 $41.500 $30.000 $11.000 $11.275 $24.650 $80.300
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 720.000 $10.000 $15.150 $16.000 $8.800 $11.275 $9.570 $23.700
MTL W-BEAM GD FEN (TIM POST)
LF 400.000 $22.000 $18.000 $25.000 $21.000 $22.048 $21.500 $26.900
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 100.000 $50.000 $50.000 $82.000 $52.620 $70.876 $53.900 $67.300
REMOVE METAL BEAM GUARD FENCE
LF 400.000 $2.000 $3.000 $1.200 $1.100 $1.040 $3.350 $1.400
RM MTL BM GD FEN TRANS (T101)
EA 4.000 $200.000 $150.000 $30.000 $120.140 $26.000 $167.100 $154.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,500.000 $2,100.000 $2,800.000 $2,519.070 $2,406.560 $2,579.250 $3,220.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $250.000 $250.000 $120.000 $185.590 $104.000 $250.650 $237.000
CRASH CUSH ATTEN (INSTL)
EA 4.000 $8,000.000 $9,500.000 $8,300.000 $7,500.000 $7,176.000 $9,500.000 $11,300.000
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $800.000 $850.000 $240.000 $650.000 $208.000 $1,135.830 $703.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 14.000 $35.000 $25.000 $20.000 $18.430 $17.430 $5.400 $23.600
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 12.000 $35.000 $25.000 $20.000 $18.430 $17.430 $7.110 $23.600
REMOVE DELIN & OBJECT MARKER ASSMS
EA 4.000 $10.000 $25.000 $30.000 $27.500 $26.000 $11.200 $35.200
INSTL OM ASSM (OM-2Y)(WC)GND(BI)
EA 4.000 $60.000 $60.000 $67.000 $61.030 $57.710 $107.160 $78.100
WK ZN PAV MRK REMOV (Y)4"(SLD)
LF 120.000 $0.700 $42.000 $20.000 $68.200 $20.800 $24.700 $50.300
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 18.000 $1.000 $2.000 $1.200 $20.000 $3.025 $5.800 $7.800
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,400.000 $1.000 $4.600 $2.500 $2.750 $2.600 $2.800 $5.600
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 176.000 $1.000 $4.600 $5.000 $5.500 $5.200 $5.650 $5.600
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 50.000 $1.000 $18.500 $5.000 $5.500 $5.200 $5.650 $22.500
REFL PAV MRKR TY II-A-A
EA 9.000 $5.000 $50.000 $50.000 $55.000 $52.000 $56.300 $60.500
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $12,500.000 $6,000.000 $12,500.000 $3,300.000 $2,148.000 $12,000.000
Totals: $497,410.000 $519,583.100 $602,564.600 $644,291.100 $676,385.835 $677,841.566 $824,753.300