FANNIN SH0056 (6475-23-001)
Items: 4
County: FANNIN
Length: 0.0100 MILES
Highway: SH0056
District: PARIS
Control Number: 6475-23-001
DBE Goal: N/A
Project: RMC - A00212516
Guaranty: $9,000.00
Time: 365 CALENDAR DAYS
Engineer's Estimate: $430,636.00
Date: 02/20/2025 (1 year ago)
Contract Number: 2250104
Type: MOWING HIGHWAY RIGHT OF WAY
Project ID: A00212516
Contract Type: Waived
Project Description: MOWING HIGHWAY RIGHT OF WAY IN FANNIN COUNTY.
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: MAINTENANCE CONTRACT OFFICE
1365 N MAIN ST, PARIS, TX 75460
AARON BLOOM
MELESE NORCHA
FANNIN SH0056 (6475-23-001)
Project Name: N/A
Project: RMC - A00212516
Length: 0.0100 MILES
Project Type: MAINTENANCE
Limits From: VARIOUS LOCATIONS IN
Limits To: FANNIN COUNTY
Project Description: MOWING HIGHWAY RIGHT OF WAY IN FANNIN COUNTY.
Bidders (7)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$430,636.00 | |||
| $351,128.20 |
-18.46%
-$79,507.80
|
|||
| $358,300.00 |
-16.8%
-$72,336.00
|
2.04%
$7,171.80
|
||
| $400,466.00 |
-7.01%
-$30,170.00
|
14.05%
$49,337.80
|
-11.77%
-$42,166.00
|
|
| $402,320.10 |
-6.58%
-$28,315.90
|
14.58%
$51,191.90
|
-0.46%
-$1,854.10
|
|
| $407,308.80 |
-5.42%
-$23,327.20
|
16%
$56,180.60
|
-1.24%
-$4,988.70
|
|
| $445,384.00 |
3.42%
$14,748.00
|
26.84%
$94,255.80
|
-9.35%
-$38,075.20
|
|
| $477,466.00 |
10.87%
$46,830.00
|
35.98%
$126,337.80
|
-7.20%
-$32,082.00
|
E
Engineer's Estimate
$430,636.00
1
Awarded
$351,128.20
Over/Under Est:
-18.46%
-$79,507.80
$358,300.00
Over/Under Est:
-16.8%
-$72,336.00
Amt Left:
2.04%
$7,171.80
$400,466.00
Over/Under Est:
-7.01%
-$30,170.00
Amt Left:
14.05%
$49,337.80
Delta:
-11.77%
-$42,166.00
$402,320.10
Over/Under Est:
-6.58%
-$28,315.90
Amt Left:
14.58%
$51,191.90
Delta:
-0.46%
-$1,854.10
$407,308.80
Over/Under Est:
-5.42%
-$23,327.20
Amt Left:
16%
$56,180.60
Delta:
-1.24%
-$4,988.70
$445,384.00
Over/Under Est:
3.42%
$14,748.00
Amt Left:
26.84%
$94,255.80
Delta:
-9.35%
-$38,075.20
$477,466.00
Over/Under Est:
10.87%
$46,830.00
Amt Left:
35.98%
$126,337.80
Delta:
-7.20%
-$32,082.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| SERVIN MOWING | 0.00% | $0.00 |
| Total: | 0.00% | $0.00 |
Bid Items & Bid Tabulations
4
Total
0 of 4