PREPARING ROW
|
STA
|
545.000
|
$1,250.000
|
$1,000.000
|
|
|
REMOVING CONC (RIPRAP)
|
SY
|
17.000
|
$25.000
|
$50.000
|
|
|
EXCAVATION (ROADWAY)
|
CY
|
1,940.000
|
$100.000
|
$25.000
|
|
|
EXCAVATION (CHANNEL)
|
CY
|
540.000
|
$25.000
|
$30.000
|
|
|
SUBGRADE WIDENING (ORD COMP)
|
STA
|
537.000
|
$250.000
|
$350.000
|
|
|
EMBANKMENT (FINAL)(ORD COMP)(TY B)
|
CY
|
15,180.000
|
$30.000
|
$18.000
|
|
|
BACKFILL (TY B)
|
STA
|
537.000
|
$255.000
|
$350.000
|
|
|
ROAD GRADER WORK (ORD COMP)
|
STA
|
537.000
|
$250.000
|
$350.000
|
|
|
BULLDOZER WORK
|
HR
|
30.000
|
$150.000
|
$250.000
|
|
|
SPEC EXCAV WORK (HYD EXCAVATOR)
|
HR
|
30.000
|
$150.000
|
$150.000
|
|
|
BROADCAST SEED (TEMP) (WARM)
|
SY
|
119,396.000
|
$0.150
|
$0.130
|
|
|
BROADCAST SEED (TEMP) (COOL)
|
SY
|
119,396.000
|
$0.150
|
$0.140
|
|
|
STRAW/HAY MLCH SEED(PERM)(RURAL)(CLAY)
|
SY
|
238,791.000
|
$0.330
|
$0.320
|
|
|
VEGETATIVE WATERING
|
MG
|
1,431.000
|
$13.000
|
$10.000
|
|
|
SOIL RETENTION BLANKETS (CL 2) (TY E)
|
SY
|
3,626.000
|
$1.800
|
$3.000
|
|
|
PROOF ROLLING
|
HR
|
66.000
|
$100.000
|
$100.000
|
|
|
FL BS (CMP IN PLC)(TY A GR 4) (8")
|
SY
|
148,799.000
|
$23.000
|
$25.000
|
|
|
FL BS (CMP IN PLACE)(TY A GR 4)(9")
|
SY
|
3,615.000
|
$22.000
|
$28.000
|
|
|
REWORK BS MTL (TY B) (6") (ORD COMP)
|
SY
|
2,645.000
|
$15.000
|
$4.000
|
|
|
REWORK BS MTL (TY C) (6") (ORD COMP)
|
SY
|
139,917.000
|
$2.500
|
$3.500
|
|
|
CEMENT
|
TON
|
1,388.000
|
$260.000
|
$350.000
|
|
|
CEMENT TREAT (NEW BASE) (6")
|
SY
|
152,413.000
|
$2.850
|
$4.440
|
|
|
ASPH (RC-250)
|
GAL
|
43,447.000
|
$6.000
|
$5.280
|
|
|
AGGR(TY-B GR-4 SAC-A)
|
CY
|
1,300.000
|
$180.000
|
$207.000
|
|
|
ASPH (AC-20-5TR OR AC-20XP)
|
GAL
|
55,862.000
|
$5.250
|
$5.000
|
|
|
AGGR (TY-B GR-5)
|
CY
|
1,113.000
|
$140.000
|
$205.000
|
|
|
CEM STABIL BKFL
|
CY
|
140.000
|
$125.000
|
$350.000
|
|
|
CUT & RESTORING PAV
|
SY
|
229.000
|
$125.000
|
$250.000
|
|
|
FLOWABLE BACKFILL
|
CY
|
193.000
|
$275.000
|
$350.000
|
|
|
TRENCH EXCAVATION PROTECTION
|
LF
|
206.000
|
$17.000
|
$10.000
|
|
|
TEMPORARY SPL SHORING
|
SF
|
1,983.000
|
$30.000
|
$55.000
|
|
|
DRILL SHAFT (36 IN)
|
LF
|
1,226.000
|
$250.000
|
$308.000
|
|
|
CL C CONC (ABUT)
|
CY
|
89.600
|
$1,200.000
|
$1,536.000
|
|
|
CL C CONC (CAP)
|
CY
|
62.600
|
$1,400.000
|
$1,650.000
|
|
|
CL C CONC (COLUMN)
|
CY
|
126.400
|
$900.000
|
$1,100.000
|
|
|
REINF CONC SLAB
|
SF
|
10,800.000
|
$22.500
|
$28.000
|
|
|
APPROACH SLAB
|
CY
|
121.600
|
$700.000
|
$750.000
|
|
|
PRESTR CONC GIRDER (TX28)
|
LF
|
1,484.920
|
$200.000
|
$269.000
|
|
|
RIPRAP (STONE COMMON)(DRY)(8 IN)
|
CY
|
27.000
|
$290.000
|
$220.000
|
|
|
RIPRAP (STONE PROTECTION)(12 IN)
|
CY
|
400.000
|
$150.000
|
$210.000
|
|
|
RIPRAP (STONE PROTECTION)(18 IN)
|
CY
|
3,196.000
|
$185.000
|
$210.000
|
|
|
RIPRAP (MOW STRIP)(4 IN)
|
CY
|
118.000
|
$540.000
|
$550.000
|
|
|
RAIL (TY T222)
|
LF
|
696.000
|
$305.000
|
$180.000
|
|
|
ARMOR JOINT
|
LF
|
130.000
|
$150.000
|
$190.000
|
|
|
CONC BOX CULV (9 FT X 7 FT)
|
LF
|
108.000
|
$1,500.000
|
$1,400.000
|
|
|
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
|
LF
|
13.000
|
$450.000
|
$1,000.000
|
|
|
CONC BOX CULV (4 FT X 3 FT)(EXTEND)
|
LF
|
15.000
|
$550.000
|
$1,000.000
|
|
|
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
|
LF
|
21.000
|
$600.000
|
$1,000.000
|
|
|
CONC BOX CULV (6 FT X 4 FT)(EXTEND)
|
LF
|
28.000
|
$700.000
|
$1,000.000
|
|
|
CONC BOX CULV (7 FT X 5 FT)(EXTEND)
|
LF
|
15.000
|
$800.000
|
$1,000.000
|
|
|
CONC BOX CULV (6 FT X 2 FT) (EXTEND)
|
LF
|
20.000
|
$550.000
|
$1,000.000
|
|
|
RC PIPE (CL III)(18 IN)
|
LF
|
2,004.000
|
$60.000
|
$55.000
|
|
|
RC PIPE (CL III)(24 IN)
|
LF
|
286.000
|
$75.000
|
$76.000
|
|
|
RC PIPE (CL III)(30 IN)
|
LF
|
158.000
|
$100.000
|
$127.000
|
|
|
RC PIPE (CL III)(36 IN)
|
LF
|
150.000
|
$125.000
|
$180.000
|
|
|
RC PIPE (CL III)(42 IN)
|
LF
|
32.000
|
$200.000
|
$245.000
|
|
|
JCTBOX(COMPL)(PJB)(3FTX3FT)
|
EA
|
1.000
|
$6,000.000
|
$5,700.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 18 IN)
|
EA
|
1.000
|
$5,000.000
|
$2,500.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 24 IN)
|
EA
|
2.000
|
$6,500.000
|
$4,500.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 30 IN)
|
EA
|
2.000
|
$8,000.000
|
$6,000.000
|
|
|
HEADWALL (CH - PW - 0) (DIA= 36 IN)
|
EA
|
3.000
|
$10,000.000
|
$7,200.000
|
|
|
WINGWALL (PW - 2) (HW=11 FT)
|
EA
|
1.000
|
$40,000.000
|
$55,000.000
|
|
|
WINGWALL (PW - 2) (HW=3 FT)
|
EA
|
1.000
|
$8,000.000
|
$12,000.000
|
|
|
WINGWALL (PW - 2) (HW=4 FT)
|
EA
|
1.000
|
$14,000.000
|
$16,000.000
|
|
|
WINGWALL (PW - 2) (HW=5 FT)
|
EA
|
2.000
|
$14,500.000
|
$20,000.000
|
|
|
WINGWALL (PW - 2) (HW=6 FT)
|
EA
|
4.000
|
$15,000.000
|
$24,000.000
|
|
|
WINGWALL (PW - 2) (HW=7 FT)
|
EA
|
1.000
|
$16,000.000
|
$28,000.000
|
|
|
WINGWALL (PW - 2) (HW=8 FT)
|
EA
|
1.000
|
$25,000.000
|
$37,000.000
|
|
|
WINGWALL (PW - 2) (HW=9 FT)
|
EA
|
2.000
|
$30,000.000
|
$34,000.000
|
|
|
SET (TY I)(S= 6 FT)(HW= 6 FT)(4:1) (C)
|
EA
|
2.000
|
$10,000.000
|
$18,000.000
|
|
|
SET (TY II) (18 IN) (CMP) (6: 1) (P)
|
EA
|
10.000
|
$825.000
|
$900.000
|
|
|
SET (TY II) (18 IN) (RCP) (4: 1) (C)
|
EA
|
3.000
|
$800.000
|
$763.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (C)
|
EA
|
2.000
|
$825.000
|
$900.000
|
|
|
SET (TY II) (18 IN) (RCP) (6: 1) (P)
|
EA
|
207.000
|
$825.000
|
$900.000
|
|
|
SET (TY II) (24 IN) (CMP) (6: 1) (P)
|
EA
|
2.000
|
$1,000.000
|
$1,225.000
|
|
|
SET (TY II) (24 IN) (RCP) (3: 1) (C)
|
EA
|
7.000
|
$1,500.000
|
$1,000.000
|
|
|
SET (TY II) (24 IN) (RCP) (4: 1) (C)
|
EA
|
4.000
|
$1,700.000
|
$1,160.000
|
|
|
SET (TY II) (24 IN) (RCP) (6: 1) (P)
|
EA
|
19.000
|
$1,300.000
|
$1,350.000
|
|
|
SET (TY II) (30 IN) (RCP) (4: 1) (C)
|
EA
|
4.000
|
$2,700.000
|
$2,430.000
|
|
|
SET (TY II) (30 IN) (RCP) (6: 1) (P)
|
EA
|
12.000
|
$2,500.000
|
$2,600.000
|
|
|
SET (TY II) (36 IN) (RCP) (3: 1) (C)
|
EA
|
2.000
|
$3,400.000
|
$4,080.000
|
|
|
SET (TY II) (36 IN) (RCP) (4: 1) (C)
|
EA
|
2.000
|
$4,000.000
|
$4,600.000
|
|
|
SET (TY II) (36 IN) (RCP) (6: 1) (P)
|
EA
|
4.000
|
$2,500.000
|
$5,945.000
|
|
|
SET (TY II) (42 IN) (RCP) (6: 1) (P)
|
EA
|
2.000
|
$5,000.000
|
$10,200.000
|
|
|
REMOV & RE - LAY PIPE (18 IN)
|
LF
|
4.000
|
$50.000
|
$50.000
|
|
|
REMOV & RE - LAY PIPE (24 IN)
|
LF
|
8.000
|
$55.000
|
$75.000
|
|
|
REMOV & RE - LAY PIPE (30 IN)
|
LF
|
8.000
|
$65.000
|
$100.000
|
|
|
REMOV & RE - LAY PIPE (36 IN)
|
LF
|
24.000
|
$70.000
|
$100.000
|
|
|
CLEAN EXIST CULVERTS
|
EA
|
50.000
|
$200.000
|
$1,500.000
|
|
|
REMOV STR (SET)
|
EA
|
20.000
|
$200.000
|
$1,000.000
|
|
|
REMOV STR (WINGWALL)
|
EA
|
18.000
|
$1,500.000
|
$1,000.000
|
|
|
REMOV STR (PIPE)
|
LF
|
1,840.000
|
$825.000
|
$50.000
|
|
|
REMOV STR (BOX CULVERT)
|
LF
|
40.000
|
$75.000
|
$150.000
|
|
|
MOBILIZATION
|
LS
|
1.000
|
$1,652,551.050
|
$2,000,000.000
|
|
|
BARRICADES, SIGNS AND TRAFFIC HANDLING
|
MO
|
23.000
|
$3,000.000
|
$5,000.000
|
|
|
ROCK FILTER DAMS (INSTALL) (TY 2)
|
LF
|
1,800.000
|
$40.000
|
$45.000
|
|
|
ROCK FILTER DAMS (REMOVE)
|
LF
|
1,800.000
|
$8.000
|
$10.000
|
|
|
TEMP SEDMT CONT FENCE (INSTALL)
|
LF
|
2,595.000
|
$4.000
|
$4.000
|
|
|
TEMP SEDMT CONT FENCE (REMOVE)
|
LF
|
2,595.000
|
$1.000
|
$1.000
|
|
|
DRIVEWAYS (ACP)
|
SY
|
410.000
|
$65.000
|
$44.000
|
|
|
TURNOUTS (ACP)
|
SY
|
1,959.000
|
$95.000
|
$85.000
|
|
|
DRIVEWAYS (BASE)
|
SY
|
3,442.000
|
$30.000
|
$45.000
|
|
|
RUMBLE STRIPS (SHOULDER) ASPHALT
|
LF
|
103,844.000
|
$0.300
|
$0.120
|
|
|
RUMBLE STRIPS (CENTERLINE) ASPHALT
|
LF
|
52,638.000
|
$0.300
|
$0.120
|
|
|
MTL W-BEAM GD FEN (STEEL POST)
|
LF
|
1,637.500
|
$35.000
|
$24.000
|
|
|
MTL BEAM GD FEN TRANS (THRIE-BEAM)
|
EA
|
7.000
|
$2,150.000
|
$2,500.000
|
|
|
REMOVE METAL BEAM GUARD FENCE
|
LF
|
1,300.000
|
$3.050
|
$2.000
|
|
|
REMOVE TERMINAL ANCHOR SECTION
|
EA
|
4.000
|
$300.000
|
$250.000
|
|
|
GUARDRAIL END TREATMENT (INSTALL)
|
EA
|
13.000
|
$3,025.000
|
$3,000.000
|
|
|
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
|
EA
|
1.000
|
$40,000.000
|
$31,000.000
|
|
|
WIRE FENCE (TY C)
|
LF
|
150.000
|
$15.000
|
$25.000
|
|
|
MAILBOX INSTALL-M (TWG-POST) TY 1
|
EA
|
5.000
|
$600.000
|
$800.000
|
|
|
MAILBOX INSTALL-S (WC-POST) TY 3
|
EA
|
55.000
|
$200.000
|
$450.000
|
|
|
MAILBOX INSTALL-D (WC-POST) TY 3
|
EA
|
9.000
|
$225.000
|
$600.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
|
EA
|
137.000
|
$300.000
|
$750.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
|
EA
|
9.000
|
$400.000
|
$820.000
|
|
|
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
|
EA
|
2.000
|
$400.000
|
$850.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(T)
|
EA
|
1.000
|
$450.000
|
$1,000.000
|
|
|
IN SM RD SN SUP&AM TYS80(1)SA(U)
|
EA
|
4.000
|
$450.000
|
$1,000.000
|
|
|
RELOCATE SM RD SN SUP&AM(HIST MRKR)
|
EA
|
1.000
|
$300.000
|
$500.000
|
|
|
REMOVE SM RD SN SUP&AM
|
EA
|
144.000
|
$200.000
|
$150.000
|
|
|
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
|
EA
|
12.000
|
$15.000
|
$30.000
|
|
|
INSTL OM ASSM (OM-2Y)(WC)GND
|
EA
|
65.000
|
$88.000
|
$35.000
|
|
|
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
|
EA
|
32.000
|
$50.000
|
$35.000
|
|
|
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
|
LF
|
214,584.000
|
$0.500
|
$0.400
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
|
LF
|
17,870.000
|
$0.550
|
$0.420
|
|
|
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
|
LF
|
104,162.000
|
$0.550
|
$0.400
|
|
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
|
EA
|
16,095.000
|
$1.750
|
$1.000
|
|
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
|
LF
|
130.000
|
$10.000
|
$15.000
|
|
|
PAVEMENT SEALER 8"
|
LF
|
2,000.000
|
$0.250
|
$0.500
|
|
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
|
LF
|
107,264.000
|
$0.750
|
$0.720
|
|
RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL)
|
LF
|
8,990.000
|
$0.750
|
$0.740
|
|
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
|
LF
|
52,081.000
|
$0.750
|
$0.720
|
|
REFL PAV MRKR TY II-A-A
|
EA
|
1,094.000
|
$5.000
|
$6.000
|
|
|
PAV SURF PREP FOR MRK (6")
|
LF
|
2,000.000
|
$0.200
|
$1.250
|
|
|
D-GR HMA TY-B PG64-22 (EXEMPT)
|
TON
|
1,207.000
|
$150.000
|
$134.000
|
|
|
SP MIXES SP-C PG64-22
|
TON
|
25,601.000
|
$145.000
|
$139.000
|
|
|
BONDING COURSE
|
GAL
|
9,318.000
|
$6.750
|
$6.200
|
|
|
THERMOPLASTIC PIPE (24 IN)(PP)(TYPE I)
|
LF
|
254.000
|
$24.000
|
$62.000
|
|
|
THERMOPLASTIC PIPE (18 IN)(PP)(TYPE I)
|
LF
|
44.000
|
$23.000
|
$60.000
|
|
|
THERMOPLASTIC PIPE (36IN)(PP)(TYPE I)
|
LF
|
54.000
|
$77.000
|
$150.000
|
|
|
GEOGRID BASE REINFORCEMENT (TY II)
|
SY
|
168,886.000
|
$1.700
|
$1.670
|
|
|
PORTABLE CHANGEABLE MESSAGE SIGN
|
EA
|
4.000
|
$12,000.000
|
$20,000.000
|
|
|
TMA (STATIONARY)
|
DAY
|
148.000
|
$150.000
|
$500.000
|
|
|
TMA (MOBILE OPERATION)
|
DAY
|
102.000
|
$150.000
|
$500.000
|
|
Totals: |
$19,636,353.630
|
$19,819,267.360
|