FANNIN FM 274 (1880-01-008)

Items: 145

County: FANNIN
Length: N/A
Highway: FM 274
District: PARIS
Control Number: 1880-01-008
DBE Goal: N/A
Project: BR 2024(385)
Guaranty: N/A
Time: 366 WORKING DAYS
Engineer's Estimate: $19,636,353.63
Date: 11/01/2023 (2 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT & REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
AARON BLOOM
MELESE NORCHA
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (1)
E
Engineer's Estimate
$19,636,353.63
$19,819,267.36
Over/Under Est: 0.93% $182,913.73
Subcontractor Percentage Amount
RICHARD DRAKE CONSTRUCTION COMPANY, L.P. 19.63% $3,949,412.18
WITHERS CONSTRUCTION, LLC 2.13% $428,540.39
A. E. MOORE CONSTRUCTION, INC. 1.11% $223,323.87
STRIPING TECHNOLOGY, L.P. 1.07% $215,276.16
DIAMOND ELITE BARRICADES, LLC 0.16% $32,190.83
WEST TEXAS ROCK RESOURCES, LLC 0.08% $16,095.41
PENHALL COMPANY 0.04% $8,047.71
A. K. GILLIS & SONS, LLC 0.00% $0.00
Total: 24.22% $4,872,886.55

Bid Items & Bid Tabulations

145 Total 0 of 145
FANNIN  |  FM 274  |  PARIS  |  1880-01-008  |  11/01/2023  |  $19,636,353.63  |  BR 2024(385)  |  BRIDGE REPL & REHAB EXIST ROADWAY  |  366 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HIGHWAY 19 CONSTRUCTION LLC
PREPARING ROW
STA 545.000 $1,250.000 $1,000.000
REMOVING CONC (RIPRAP)
SY 17.000 $25.000 $50.000
EXCAVATION (ROADWAY)
CY 1,940.000 $100.000 $25.000
EXCAVATION (CHANNEL)
CY 540.000 $25.000 $30.000
SUBGRADE WIDENING (ORD COMP)
STA 537.000 $250.000 $350.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 15,180.000 $30.000 $18.000
BACKFILL (TY B)
STA 537.000 $255.000 $350.000
ROAD GRADER WORK (ORD COMP)
STA 537.000 $250.000 $350.000
BULLDOZER WORK
HR 30.000 $150.000 $250.000
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 30.000 $150.000 $150.000
BROADCAST SEED (TEMP) (WARM)
SY 119,396.000 $0.150 $0.130
BROADCAST SEED (TEMP) (COOL)
SY 119,396.000 $0.150 $0.140
STRAW/HAY MLCH SEED(PERM)(RURAL)(CLAY)
SY 238,791.000 $0.330 $0.320
VEGETATIVE WATERING
MG 1,431.000 $13.000 $10.000
SOIL RETENTION BLANKETS (CL 2) (TY E)
SY 3,626.000 $1.800 $3.000
PROOF ROLLING
HR 66.000 $100.000 $100.000
FL BS (CMP IN PLC)(TY A GR 4) (8")
SY 148,799.000 $23.000 $25.000
FL BS (CMP IN PLACE)(TY A GR 4)(9")
SY 3,615.000 $22.000 $28.000
REWORK BS MTL (TY B) (6") (ORD COMP)
SY 2,645.000 $15.000 $4.000
REWORK BS MTL (TY C) (6") (ORD COMP)
SY 139,917.000 $2.500 $3.500
CEMENT
TON 1,388.000 $260.000 $350.000
CEMENT TREAT (NEW BASE) (6")
SY 152,413.000 $2.850 $4.440
ASPH (RC-250)
GAL 43,447.000 $6.000 $5.280
AGGR(TY-B GR-4 SAC-A)
CY 1,300.000 $180.000 $207.000
ASPH (AC-20-5TR OR AC-20XP)
GAL 55,862.000 $5.250 $5.000
AGGR (TY-B GR-5)
CY 1,113.000 $140.000 $205.000
CEM STABIL BKFL
CY 140.000 $125.000 $350.000
CUT & RESTORING PAV
SY 229.000 $125.000 $250.000
FLOWABLE BACKFILL
CY 193.000 $275.000 $350.000
TRENCH EXCAVATION PROTECTION
LF 206.000 $17.000 $10.000
TEMPORARY SPL SHORING
SF 1,983.000 $30.000 $55.000
DRILL SHAFT (36 IN)
LF 1,226.000 $250.000 $308.000
CL C CONC (ABUT)
CY 89.600 $1,200.000 $1,536.000
CL C CONC (CAP)
CY 62.600 $1,400.000 $1,650.000
CL C CONC (COLUMN)
CY 126.400 $900.000 $1,100.000
REINF CONC SLAB
SF 10,800.000 $22.500 $28.000
APPROACH SLAB
CY 121.600 $700.000 $750.000
PRESTR CONC GIRDER (TX28)
LF 1,484.920 $200.000 $269.000
RIPRAP (STONE COMMON)(DRY)(8 IN)
CY 27.000 $290.000 $220.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 400.000 $150.000 $210.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 3,196.000 $185.000 $210.000
RIPRAP (MOW STRIP)(4 IN)
CY 118.000 $540.000 $550.000
RAIL (TY T222)
LF 696.000 $305.000 $180.000
ARMOR JOINT
LF 130.000 $150.000 $190.000
CONC BOX CULV (9 FT X 7 FT)
LF 108.000 $1,500.000 $1,400.000
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 13.000 $450.000 $1,000.000
CONC BOX CULV (4 FT X 3 FT)(EXTEND)
LF 15.000 $550.000 $1,000.000
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
LF 21.000 $600.000 $1,000.000
CONC BOX CULV (6 FT X 4 FT)(EXTEND)
LF 28.000 $700.000 $1,000.000
CONC BOX CULV (7 FT X 5 FT)(EXTEND)
LF 15.000 $800.000 $1,000.000
CONC BOX CULV (6 FT X 2 FT) (EXTEND)
LF 20.000 $550.000 $1,000.000
RC PIPE (CL III)(18 IN)
LF 2,004.000 $60.000 $55.000
RC PIPE (CL III)(24 IN)
LF 286.000 $75.000 $76.000
RC PIPE (CL III)(30 IN)
LF 158.000 $100.000 $127.000
RC PIPE (CL III)(36 IN)
LF 150.000 $125.000 $180.000
RC PIPE (CL III)(42 IN)
LF 32.000 $200.000 $245.000
JCTBOX(COMPL)(PJB)(3FTX3FT)
EA 1.000 $6,000.000 $5,700.000
HEADWALL (CH - PW - 0) (DIA= 18 IN)
EA 1.000 $5,000.000 $2,500.000
HEADWALL (CH - PW - 0) (DIA= 24 IN)
EA 2.000 $6,500.000 $4,500.000
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 2.000 $8,000.000 $6,000.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 3.000 $10,000.000 $7,200.000
WINGWALL (PW - 2) (HW=11 FT)
EA 1.000 $40,000.000 $55,000.000
WINGWALL (PW - 2) (HW=3 FT)
EA 1.000 $8,000.000 $12,000.000
WINGWALL (PW - 2) (HW=4 FT)
EA 1.000 $14,000.000 $16,000.000
WINGWALL (PW - 2) (HW=5 FT)
EA 2.000 $14,500.000 $20,000.000
WINGWALL (PW - 2) (HW=6 FT)
EA 4.000 $15,000.000 $24,000.000
WINGWALL (PW - 2) (HW=7 FT)
EA 1.000 $16,000.000 $28,000.000
WINGWALL (PW - 2) (HW=8 FT)
EA 1.000 $25,000.000 $37,000.000
WINGWALL (PW - 2) (HW=9 FT)
EA 2.000 $30,000.000 $34,000.000
SET (TY I)(S= 6 FT)(HW= 6 FT)(4:1) (C)
EA 2.000 $10,000.000 $18,000.000
SET (TY II) (18 IN) (CMP) (6: 1) (P)
EA 10.000 $825.000 $900.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 3.000 $800.000 $763.000
SET (TY II) (18 IN) (RCP) (6: 1) (C)
EA 2.000 $825.000 $900.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 207.000 $825.000 $900.000
SET (TY II) (24 IN) (CMP) (6: 1) (P)
EA 2.000 $1,000.000 $1,225.000
SET (TY II) (24 IN) (RCP) (3: 1) (C)
EA 7.000 $1,500.000 $1,000.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 4.000 $1,700.000 $1,160.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 19.000 $1,300.000 $1,350.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 4.000 $2,700.000 $2,430.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 12.000 $2,500.000 $2,600.000
SET (TY II) (36 IN) (RCP) (3: 1) (C)
EA 2.000 $3,400.000 $4,080.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 2.000 $4,000.000 $4,600.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 4.000 $2,500.000 $5,945.000
SET (TY II) (42 IN) (RCP) (6: 1) (P)
EA 2.000 $5,000.000 $10,200.000
REMOV & RE - LAY PIPE (18 IN)
LF 4.000 $50.000 $50.000
REMOV & RE - LAY PIPE (24 IN)
LF 8.000 $55.000 $75.000
REMOV & RE - LAY PIPE (30 IN)
LF 8.000 $65.000 $100.000
REMOV & RE - LAY PIPE (36 IN)
LF 24.000 $70.000 $100.000
CLEAN EXIST CULVERTS
EA 50.000 $200.000 $1,500.000
REMOV STR (SET)
EA 20.000 $200.000 $1,000.000
REMOV STR (WINGWALL)
EA 18.000 $1,500.000 $1,000.000
REMOV STR (PIPE)
LF 1,840.000 $825.000 $50.000
REMOV STR (BOX CULVERT)
LF 40.000 $75.000 $150.000
MOBILIZATION
LS 1.000 $1,652,551.050 $2,000,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 23.000 $3,000.000 $5,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 1,800.000 $40.000 $45.000
ROCK FILTER DAMS (REMOVE)
LF 1,800.000 $8.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,595.000 $4.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,595.000 $1.000 $1.000
DRIVEWAYS (ACP)
SY 410.000 $65.000 $44.000
TURNOUTS (ACP)
SY 1,959.000 $95.000 $85.000
DRIVEWAYS (BASE)
SY 3,442.000 $30.000 $45.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 103,844.000 $0.300 $0.120
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 52,638.000 $0.300 $0.120
MTL W-BEAM GD FEN (STEEL POST)
LF 1,637.500 $35.000 $24.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 7.000 $2,150.000 $2,500.000
REMOVE METAL BEAM GUARD FENCE
LF 1,300.000 $3.050 $2.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $300.000 $250.000
GUARDRAIL END TREATMENT (INSTALL)
EA 13.000 $3,025.000 $3,000.000
CRASH CUSH ATTEN (INSTL)(L)(N)(TL3)
EA 1.000 $40,000.000 $31,000.000
WIRE FENCE (TY C)
LF 150.000 $15.000 $25.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 5.000 $600.000 $800.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 55.000 $200.000 $450.000
MAILBOX INSTALL-D (WC-POST) TY 3
EA 9.000 $225.000 $600.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 137.000 $300.000 $750.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 9.000 $400.000 $820.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 2.000 $400.000 $850.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $450.000 $1,000.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 4.000 $450.000 $1,000.000
RELOCATE SM RD SN SUP&AM(HIST MRKR)
EA 1.000 $300.000 $500.000
REMOVE SM RD SN SUP&AM
EA 144.000 $200.000 $150.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 12.000 $15.000 $30.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 65.000 $88.000 $35.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 32.000 $50.000 $35.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 214,584.000 $0.500 $0.400
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 17,870.000 $0.550 $0.420
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 104,162.000 $0.550 $0.400
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 16,095.000 $1.750 $1.000
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 130.000 $10.000 $15.000
PAVEMENT SEALER 8"
LF 2,000.000 $0.250 $0.500
RE PM W/RET REQ TY I (W)6"(SLD)(090MIL)
LF 107,264.000 $0.750 $0.720
RE PM W/RET REQ TY I (Y)6"(BRK)(090MIL)
LF 8,990.000 $0.750 $0.740
RE PM W/RET REQ TY I (Y)6"(SLD)(090MIL)
LF 52,081.000 $0.750 $0.720
REFL PAV MRKR TY II-A-A
EA 1,094.000 $5.000 $6.000
PAV SURF PREP FOR MRK (6")
LF 2,000.000 $0.200 $1.250
D-GR HMA TY-B PG64-22 (EXEMPT)
TON 1,207.000 $150.000 $134.000
SP MIXES SP-C PG64-22
TON 25,601.000 $145.000 $139.000
BONDING COURSE
GAL 9,318.000 $6.750 $6.200
THERMOPLASTIC PIPE (24 IN)(PP)(TYPE I)
LF 254.000 $24.000 $62.000
THERMOPLASTIC PIPE (18 IN)(PP)(TYPE I)
LF 44.000 $23.000 $60.000
THERMOPLASTIC PIPE (36IN)(PP)(TYPE I)
LF 54.000 $77.000 $150.000
GEOGRID BASE REINFORCEMENT (TY II)
SY 168,886.000 $1.700 $1.670
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $12,000.000 $20,000.000
TMA (STATIONARY)
DAY 148.000 $150.000 $500.000
TMA (MOBILE OPERATION)
DAY 102.000 $150.000 $500.000
Totals: $19,636,353.630 $19,819,267.360