FANNIN FM 1552 (1487-01-008)

Items: 73

County: FANNIN
Length: N/A
Highway: FM 1552
District: PARIS
Control Number: 1487-01-008
DBE Goal: N/A
Project: C 1487-1-8
Guaranty: N/A
Time: 96 WORKING DAYS
Engineer's Estimate: $1,641,195.20
Date: 05/06/2021 (5 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (4)
E
Engineer's Estimate
$1,641,195.20
$1,844,734.62
Over/Under Est: 12.4% $203,539.42
Over/Under Est: 12.47% $204,718.78
Amt Left: 0.06% $1,179.36
Over/Under Est: 12.51% $205,288.15
Amt Left: 0.09% $1,748.73
Delta: -0.03% -$569.37
Over/Under Est: 22.06% $362,026.40
Amt Left: 8.59% $158,486.98
Delta: -8.49% -$156,738.25

Bid Items & Bid Tabulations

73 Total 0 of 73
FANNIN  |  FM 1552  |  PARIS  |  1487-01-008  |  05/06/2021  |  $1,641,195.20  |  C 1487-1-8  |  REHAB EXIST ROADWAY  |  96 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
HIGHWAY 19 CONSTRUCTION LLC
HARRISON, WALKER AND HARPER, LLC
A. K. GILLIS & SONS, LLC
D. L. LENNON INCORPORATED - CONTRACTOR
PREPARING ROW
STA 128.640 $500.000 $389.000 $459.500 $388.900 $332.000
REMOVING CONC (DRIVEWAYS)
SY 19.000 $20.000 $25.000 $23.600 $22.000 $22.000
EXCAVATION (ROADWAY)
CY 525.000 $6.000 $15.000 $8.200 $20.000 $26.000
EXCAVATION (CHANNEL)
CY 156.000 $30.000 $25.000 $15.450 $100.000 $45.000
SUBGRADE WIDENING (ORD COMP)
STA 128.640 $170.000 $150.000 $303.450 $158.380 $230.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 85.000 $17.000 $50.000 $16.800 $90.690 $42.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 113.000 $25.000 $50.000 $16.300 $55.820 $42.000
BACKFILL (TY B)
STA 128.640 $160.000 $150.000 $234.900 $158.380 $274.000
ROAD GRADER WORK (ORD COMP)
STA 128.640 $155.000 $150.000 $120.600 $158.380 $308.000
BROADCAST SEED (TEMP) (WARM)
SY 28,587.000 $0.060 $0.010 $0.050 $0.010 $0.050
BROADCAST SEED (TEMP) (COOL)
SY 28,587.000 $0.060 $0.010 $0.050 $0.010 $0.050
STRAW/HAY MLCH SEED(PERM)(RURAL)(CLAY)
SY 57,174.000 $0.200 $0.250 $0.250 $0.250 $0.190
VEGETATIVE WATERING
MG 343.000 $10.000 $10.000 $9.200 $5.990 $45.000
FL BS (RDWY DEL) (TY A GR 4)
TON 45.000 $45.000 $40.000 $35.350 $100.000 $54.000
FL BS (CMP IN PLC)(TY A GR 4) (8")
SY 34,572.000 $12.000 $14.250 $12.750 $13.870 $15.000
REWORK BS MTL (TY C) (6") (ORD COMP)
SY 31,713.000 $2.500 $2.910 $2.350 $2.090 $2.750
ASPH (RC-250)
GAL 9,680.000 $4.650 $4.770 $3.850 $4.640 $6.500
AGGR (TY-B GR-5 OR TY-L GR-5)
CY 247.000 $110.000 $157.000 $91.300 $123.740 $98.000
AGGR (TY-PB GR-4 OR TY-PL GR-4 SAC-A)
CY 288.000 $125.000 $186.000 $115.150 $184.280 $147.000
ASPH (AC-20-5TR OR AC-20XP)
GAL 28,348.000 $3.250 $3.550 $3.350 $4.170 $5.150
AGGR (TY-B GR-3 OR TY-L GR-3)(SAC-B)
CY 330.000 $116.500 $159.000 $97.250 $128.040 $109.000
CUT & RESTORE ASPH PAVING
SY 225.000 $100.000 $250.000 $147.700 $110.000 $110.000
TRENCH EXCAVATION PROTECTION
LF 120.000 $20.000 $5.000 $23.600 $20.000 $20.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 11.000 $115.000 $250.000 $160.600 $289.400 $150.000
RIPRAP (MOW STRIP)(4 IN)
CY 43.000 $420.000 $450.000 $561.250 $500.000 $500.000
RETROFIT RAIL (TY T631)
LF 120.000 $100.000 $92.000 $81.500 $69.000 $94.000
CONC BOX CULV (7 FT X 3 FT)
LF 240.000 $440.000 $507.000 $977.150 $700.000 $700.000
RC PIPE (CL III)(18 IN)
LF 366.000 $50.000 $41.000 $53.900 $45.000 $45.000
RC PIPE (CL III)(24 IN)
LF 60.000 $70.000 $55.000 $80.900 $65.000 $65.000
RC PIPE (CL III)(30 IN)
LF 290.000 $100.000 $88.000 $94.350 $90.000 $90.000
WINGWALL (FW - 0) (HW=4 FT)
EA 6.000 $9,500.000 $8,500.000 $7,975.550 $7,200.000 $7,200.000
SET (TY II) (12 IN) (CMP) (6: 1) (P)
EA 4.000 $750.000 $550.000 $768.000 $550.000 $550.000
SET (TY II) (12 IN) (RCP) (6: 1) (P)
EA 10.000 $600.000 $474.000 $827.100 $550.000 $550.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 26.000 $800.000 $514.000 $1,004.350 $700.000 $700.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $1,400.000 $1,121.000 $1,181.550 $1,100.000 $1,100.000
SET (TY II) (30 IN) (RCP) (3: 1) (C)
EA 14.000 $1,400.000 $1,187.000 $1,299.700 $1,150.000 $1,150.000
SET (TY II) (36 IN) (CMP) (6: 1) (P)
EA 4.000 $4,500.000 $4,575.000 $6,498.600 $6,000.000 $6,000.000
REMOV STR (PIPE)
LF 1,108.000 $16.000 $50.000 $4.750 $12.000 $12.000
MOBILIZATION
LS 1.000 $126,000.000 $110,000.000 $182,243.750 $144,169.000 $126,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $2,500.000 $1,000.000 $2,613.100 $5,265.000 $6,138.790
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 360.000 $35.000 $36.000 $40.150 $36.000 $36.000
ROCK FILTER DAMS (REMOVE)
LF 360.000 $7.000 $5.000 $7.100 $5.500 $5.500
TEMP SEDMT CONT FENCE (INSTALL)
LF 3,314.000 $2.350 $2.000 $3.100 $2.000 $2.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 480.000 $2.350 $0.500 $0.150 $0.500 $0.500
DRIVEWAYS (CONC)
SY 19.000 $100.000 $150.000 $118.150 $100.000 $125.000
TURNOUTS (ACP)
SY 261.000 $70.000 $55.000 $35.450 $48.310 $90.000
DRIVEWAYS (BASE)
SY 585.000 $16.000 $30.000 $9.850 $27.730 $25.000
MTL W-BEAM GD FEN (STEEL POST)
LF 250.000 $19.000 $25.000 $26.600 $22.500 $25.000
MTL BM GD FEN (LONG SPAN SYSTEM)
EA 1.000 $1,200.000 $1,500.000 $1,388.350 $1,175.000 $1,902.000
REMOVE METAL BEAM GUARD FENCE
LF 300.000 $1.000 $2.000 $1.500 $1.250 $2.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $125.000 $120.000 $206.750 $175.000 $175.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,400.000 $2,180.000 $3,030.700 $2,565.000 $2,700.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 9.000 $185.000 $150.000 $199.700 $169.000 $175.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 62.000 $560.000 $550.000 $554.150 $469.000 $635.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 3.000 $665.000 $780.000 $855.450 $724.000 $1,500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 1.000 $850.000 $850.000 $1,062.250 $899.000 $2,000.000
REMOVE SM RD SN SUP&AM
EA 67.000 $100.000 $150.000 $59.100 $50.000 $65.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 12.000 $65.000 $35.000 $59.100 $50.000 $35.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 10.000 $25.000 $21.000 $23.650 $20.000 $30.000
WK ZN PAV MRK NON-REMOV (W)4"(SLD)
LF 25,710.000 $0.180 $0.300 $0.230 $0.220 $0.220
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 1,810.000 $0.250 $0.300 $0.230 $0.220 $0.220
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 15,947.000 $0.180 $0.300 $0.230 $0.220 $0.220
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 4,020.000 $1.500 $1.000 $0.900 $2.250 $1.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 42.000 $6.000 $20.000 $7.650 $7.250 $7.250
REFL PAV MRK TY II (W) 24" (SLD)
LF 42.000 $4.000 $5.000 $4.250 $4.000 $4.000
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 25,710.000 $0.550 $0.650 $0.550 $0.520 $0.520
REF PROF PAV MRK TY I(Y)4"(BRK)(100MIL)
LF 1,810.000 $0.650 $0.650 $0.550 $0.520 $0.520
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 15,947.000 $0.550 $0.650 $0.550 $0.520 $0.520
REFL PAV MRKR TY II-A-A
EA 290.000 $4.000 $5.000 $4.150 $3.950 $3.950
GEOGRID BASE REINFORCEMENT (TY II)
SY 37,431.000 $1.050 $1.740 $0.930 $1.110 $1.750
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $10,000.000 $10,000.000 $15,000.000 $15,000.000
TMA (STATIONARY)
DAY 96.000 $200.000 $200.000 $225.000 $150.000 $165.000
TMA (MOBILE OPERATION)
HR 20.000 $85.000 $50.000 $95.000 $150.000 $165.000
Totals: $1,641,195.200 $1,844,734.620 $1,845,913.998 $1,846,483.366 $2,003,221.600