FANNIN CR (0901-32-101)

Items: 36

County: FANNIN
Length: N/A
Highway: CR
District: PARIS
Control Number: 0901-32-101
DBE Goal: N/A
Project: BR 2021(253)
Guaranty: N/A
Time: 112 WORKING DAYS
Engineer's Estimate: $440,593.08
Date: 02/03/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE REPLACEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Documents:
Bidders (5)
E
Engineer's Estimate
$440,593.08
$470,243.93
Over/Under Est: 6.73% $29,650.85
Over/Under Est: 14.02% $61,763.97
Amt Left: 6.83% $32,113.12
Over/Under Est: 28.74% $126,609.77
Amt Left: 20.62% $96,958.92
Delta: -12.91% -$64,845.80
Over/Under Est: 30.4% $133,922.87
Amt Left: 22.17% $104,272.02
Delta: -1.29% -$7,313.10
$632,603.30
Over/Under Est: 43.58% $192,010.22
Amt Left: 34.53% $162,359.37
Delta: -10.11% -$58,087.35

Bid Items & Bid Tabulations

36 Total 0 of 36
FANNIN  |  CR  |  PARIS  |  0901-32-101  |  02/03/2022  |  $440,593.08  |  BR 2021(253)  |  BRIDGE REPL  |  112 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
THK CONSTRUCTION LLC
HIGHWAY 19 CONSTRUCTION LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
EAST TEXAS BRIDGE, INC.
CDM HOLDINGS, LLC
PREPARING ROW
STA 8.000 $3,200.000 $1,500.000 $2,000.000 $3,000.000 $4,000.000 $4,000.000
EXCAVATION (ROADWAY)
CY 111.000 $9.000 $16.000 $25.000 $30.000 $30.000 $15.000
EXCAVATION (CHANNEL)
CY 365.000 $15.000 $15.000 $20.000 $25.000 $30.000 $25.000
EMBANKMENT (FINAL)(ORD COMP)(TY B)
CY 604.000 $8.500 $16.000 $30.000 $20.000 $35.000 $40.000
BROADCAST SEED (TEMP) (WARM)
SY 1,286.000 $1.200 $0.510 $0.500 $1.000 $0.750 $1.000
BROADCAST SEED (TEMP) (COOL)
SY 1,286.000 $1.200 $0.520 $0.500 $1.000 $0.750 $1.000
CELL FBR MLCH SEED(PERM)(RURAL)(CLAY)
SY 2,572.000 $1.300 $1.090 $0.500 $2.000 $0.900 $2.000
VEGETATIVE WATERING
MG 61.600 $22.000 $10.000 $10.000 $1.000 $25.000 $25.000
FL BS (CMP IN PLC)(TY A GR 4) (6")
SY 1,456.000 $7.500 $25.000 $24.000 $30.000 $20.000 $31.000
CEM STABIL BKFL
CY 54.000 $225.000 $250.000 $180.000 $220.000 $275.000 $210.000
DRILL SHAFT (36 IN)
LF 78.000 $250.000 $290.000 $341.000 $250.000 $375.000 $490.000
CL C CONC (ABUT)
CY 38.800 $1,100.000 $950.000 $1,105.000 $1,100.000 $1,350.000 $1,400.000
REINF CONC SLAB
SF 1,820.000 $16.000 $25.000 $26.000 $28.000 $28.000 $31.750
PRESTR CONC GIRDER (TX28)
LF 277.690 $230.000 $273.000 $245.000 $225.000 $235.000 $270.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 36.000 $110.000 $168.000 $150.000 $200.000 $155.000 $190.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 176.000 $115.000 $126.000 $150.000 $200.000 $155.000 $170.000
RAIL (TY T631LS)
LF 180.000 $72.000 $58.000 $65.000 $70.000 $70.000 $80.000
CONC BOX CULV (6 FT X 4 FT)
LF 76.000 $330.000 $625.000 $550.000 $800.000 $700.000 $575.000
RC PIPE (CL III)(24 IN)
LF 40.000 $60.000 $96.500 $100.000 $80.000 $100.000 $100.000
WINGWALL (PW - 2) (HW=6 FT)
EA 2.000 $10,000.000 $13,000.000 $17,597.000 $20,000.000 $12,000.000 $17,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 2.000 $1,025.000 $2,000.000 $1,500.000 $3,000.000 $1,400.000 $1,500.000
REMOV STR (PIPE)
LF 30.000 $15.000 $8.500 $50.000 $20.000 $50.000 $20.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $10,000.000 $4,000.000 $7,500.000 $12,000.000 $12,000.000 $15,000.000
MOBILIZATION
LS 1.000 $35,291.180 $40,000.000 $50,000.000 $45,000.000 $50,000.000 $63,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 7.000 $7,500.000 $1,977.000 $1,500.000 $3,600.000 $3,600.000 $2,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 120.000 $35.000 $26.500 $27.000 $5.000 $45.000 $42.000
ROCK FILTER DAMS (REMOVE)
LF 120.000 $10.000 $5.000 $10.000 $5.000 $12.000 $16.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 900.000 $2.750 $2.500 $0.300 $1.000 $3.500 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 900.000 $1.250 $1.000 $1.000 $1.000 $1.250 $1.000
MTL W-BEAM GD FEN (STEEL POST)
LF 100.000 $25.000 $29.000 $30.000 $30.000 $32.000 $28.000
SHORT RADIUS
LF 25.000 $40.000 $47.500 $50.000 $60.000 $70.000 $50.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 1.000 $900.000 $1,050.000 $1,250.000 $1,200.000 $1,400.000 $1,100.000
GUARDRAIL END TREATMENT (INSTALL)
EA 3.000 $2,600.000 $3,339.000 $2,950.000 $3,200.000 $3,500.000 $3,200.000
REMOVE SM RD SN SUP&AM
EA 4.000 $75.000 $250.000 $100.000 $200.000 $125.000 $100.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 6.000 $95.000 $63.000 $35.000 $75.000 $85.000 $95.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $30.000 $26.250 $35.000 $30.000 $30.000 $40.000
Totals: $440,593.080 $470,243.930 $502,357.050 $567,202.850 $574,515.950 $632,603.300