FANNIN FM 68 (0620-01-018)

Items: 93

County: FANNIN
Length: N/A
Highway: FM 68
District: PARIS
Control Number: 0620-01-018
DBE Goal: N/A
Project: STP 2024(080)HES
Guaranty: N/A
Time: 247 WORKING DAYS
Engineer's Estimate: $4,585,160.31
Date: 10/06/2023 (2 years ago)
Contract Number: N/A
Type: REHABILITATE EXISTING ROADWAY
Mail/Deliver Bids To: N/A
AARON BLOOM
MELESE NORCHA
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (2)
E
Engineer's Estimate
$4,585,160.31
Over/Under Est: 35.29% $1,618,111.75
Over/Under Est: 56.36% $2,584,319.53
Amt Left: 15.58% $966,207.78
Subcontractor Percentage Amount
BAHENA CONSTRUCTION CO., INC. 12.42% $755,307.91
MOJICA CONSTRUCTION LLC 7.41% $450,630.57
WITHERS CONSTRUCTION, LLC 2.15% $130,749.76
STRIPING TECHNOLOGY, L.P. 2.11% $128,317.21
TEXANA LAND & ASPHALT, INC. 1.63% $99,126.56
J. H. ODEN CONTRACTING COMPANY 1.60% $97,302.15
PANOLA SIGN & BARRICADE, INC. 0.59% $35,880.17
MORRIS COUNTY CONTRACTORS, L.L.C. 0.44% $26,758.09
Total: 28.35% $1,724,072.42

Bid Items & Bid Tabulations

93 Total 0 of 93
FANNIN  |  FM 68  |  PARIS  |  0620-01-018  |  10/06/2023  |  $4,585,160.31  |  STP 2024(080)HES  |  REHAB EXIST ROADWAY  |  247 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
D. L. LENNON INCORPORATED - CONTRACTOR
A. K. GILLIS & SONS, LLC
PREPARING ROW
STA 227.610 $1,000.000 $1,072.000 $1,150.000
REMOVING CONC (DRIVEWAYS)
SY 118.000 $22.750 $15.000 $15.000
EXCAVATION (CHANNEL)
CY 130.000 $20.000 $25.000 $100.000
SUBGRADE WIDENING (ORD COMP)
STA 227.610 $200.000 $200.000 $400.000
EMBANKMENT (VEHICLE)(ORD COMP)(TY B)
CY 164.000 $20.000 $66.000 $100.000
BACKFILL (TY B)
STA 227.610 $200.000 $250.000 $400.000
ROAD GRADER WORK (ORD COMP)
STA 227.610 $225.000 $300.000 $400.000
BULLDOZER WORK
HR 20.000 $150.000 $247.000 $150.000
SPEC EXCAV WORK (HYD EXCAVATOR)
HR 20.000 $150.000 $247.000 $750.000
BROADCAST SEED (TEMP) (WARM)
SY 59,965.000 $0.120 $0.100 $0.200
BROADCAST SEED (TEMP) (COOL)
SY 59,965.000 $0.120 $0.100 $0.200
STRAW/HAY MLCH SEED(PERM)(RURAL)(CLAY)
SY 119,931.000 $0.500 $0.300 $0.450
VEGETATIVE WATERING
MG 720.000 $20.000 $60.000 $25.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 1,000.000 $1.000 $2.000 $5.000
PROOF ROLLING
HR 30.000 $100.000 $75.000 $105.000
FL BS(CMP IN PLC)(TY D GR 4)(9")
SY 70,811.000 $20.000 $25.570 $28.500
REWRKING BS MATL (TY C)(10")(ORD COMP)
SY 55,638.000 $2.500 $3.690 $3.250
CEMENT
TON 430.000 $225.000 $300.000 $300.000
CEMENT TREAT (NEW BASE) (6")
SY 70,811.000 $1.750 $3.950 $3.750
ASPH (RC-250)
GAL 19,828.000 $4.200 $7.000 $6.000
AGGR (TY-B GR-5 OR TY-L GR-5)
CY 506.000 $130.000 $116.250 $125.000
AGGR (TY-PB GR-4 OR TY-PL GR-4 SAC-A)
CY 590.000 $175.000 $187.500 $180.000
ASPH (AC-20-5TR OR AC-20XP)
GAL 59,482.000 $3.850 $6.500 $6.000
AGGR (TY-B GR-3 OR TY-L GR-3)(SAC-B)
CY 674.000 $125.000 $125.000 $125.000
CUT & RESTORING PAV
SY 826.000 $100.000 $75.000 $100.000
CUT & RESTORE ASPH PAVING
SY 60.000 $150.000 $75.000 $100.000
FLOWABLE BACKFILL
CY 384.000 $175.000 $275.000 $275.000
TRENCH EXCAVATION PROTECTION
LF 605.000 $5.000 $15.000 $15.000
TEMPORARY SPL SHORING
SF 6,068.000 $25.000 $65.000 $45.000
RIPRAP (CONC)(4 IN)
CY 5.000 $500.000 $575.000 $575.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 100.000 $300.000 $265.000 $400.000
RIPRAP (MOW STRIP)(4 IN)
CY 48.000 $400.000 $575.000 $575.000
CONC BOX CULV (5 FT X 3 FT)
LF 50.000 $300.000 $700.000 $700.000
RC PIPE (CL III)(18 IN)
LF 736.000 $50.000 $55.000 $55.000
RC PIPE (CL III)(24 IN)
LF 118.000 $75.000 $85.000 $85.000
RC PIPE (CL III)(30 IN)
LF 407.000 $115.000 $140.000 $140.000
RC PIPE (CL III)(36 IN)
LF 184.000 $175.000 $175.000 $175.000
RC PIPE (CL III)(48 IN)
LF 90.000 $215.000 $250.000 $250.000
HEADWALL (CH - FW - 0) (DIA= 24 IN)
EA 1.000 $4,000.000 $6,500.000 $6,500.000
HEADWALL (CH - FW - 0) (DIA= 36 IN)
EA 1.000 $6,000.000 $9,000.000 $9,000.000
HEADWALL (CH - PW - 0) (DIA= 30 IN)
EA 4.000 $7,000.000 $8,500.000 $8,500.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 3.000 $10,000.000 $10,000.000 $10,000.000
HEADWALL (CH - PW - 0) (DIA= 48 IN)
EA 6.000 $10,500.000 $14,000.000 $14,000.000
WINGWALL (FW - 0) (HW=4 FT)
EA 2.000 $12,500.000 $15,000.000 $15,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 78.000 $900.000 $750.000 $750.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 2.000 $3,000.000 $1,500.000 $1,500.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $1,500.000 $1,600.000 $1,600.000
SET (TY II) (30 IN) (RCP) (4: 1) (C)
EA 7.000 $1,800.000 $2,200.000 $2,200.000
SET (TY II) (30 IN) (RCP) (6: 1) (P)
EA 1.000 $2,500.000 $2,800.000 $2,800.000
SET (TY II) (36 IN) (RCP) (4: 1) (C)
EA 1.000 $2,800.000 $4,500.000 $4,500.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 1.000 $3,500.000 $7,500.000 $7,500.000
SET (REMOV & REINSTALL)
EA 2.000 $1,200.000 $500.000 $500.000
REMOV STR (HEADWALL)
EA 4.000 $2,000.000 $1,000.000 $1,000.000
REMOV STR (PIPE)
LF 1,163.000 $30.000 $10.000 $10.000
MOBILIZATION
LS 1.000 $348,770.060 $256,500.000 $625,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 16.000 $5,500.000 $6,619.000 $15,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 885.000 $35.000 $40.000 $55.000
ROCK FILTER DAMS (REMOVE)
LF 885.000 $5.000 $9.000 $10.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,050.000 $2.250 $3.500 $5.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,050.000 $0.800 $0.100 $2.500
DRIVEWAYS (CONC)
SY 118.000 $75.000 $120.000 $100.000
DRIVEWAYS (ACP)
SY 681.000 $24.000 $68.500 $75.000
TURNOUTS (ACP)
SY 754.000 $57.000 $108.000 $105.000
DRIVEWAYS (BASE)
SY 1,837.000 $21.000 $25.000 $31.500
MTL W-BEAM GD FEN (STEEL POST)
LF 450.000 $26.000 $26.750 $27.500
MTL BM GD FEN (LONG SPAN SYSTEM)
LF 50.000 $30.000 $36.500 $60.000
REMOVE METAL BEAM GUARD FENCE
LF 200.000 $2.500 $2.000 $4.000
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $200.000 $200.000 $400.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,600.000 $2,800.000 $3,200.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 23.000 $190.000 $250.000 $185.000
MAILBOX INSTALL-D (WC-POST) TY 3
EA 3.000 $225.000 $275.000 $225.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 38.000 $430.000 $700.000 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 6.000 $560.000 $780.000 $800.000
IN SM RD SN SUP&AM TY10BWG(2)SA(P)
EA 1.000 $900.000 $970.000 $1,250.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 1.000 $600.000 $1,222.000 $1,100.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 1.000 $1,000.000 $1,738.000 $950.000
REMOVE SM RD SN SUP&AM
EA 44.000 $80.000 $55.000 $100.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 40.000 $55.000 $45.000 $60.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 10.000 $28.000 $25.000 $35.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 45,000.000 $0.250 $0.500 $0.500
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 18,049.000 $0.250 $0.500 $0.500
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 18,229.000 $0.250 $0.500 $0.500
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 8,000.000 $2.250 $2.000 $3.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 212.000 $5.500 $7.000 $7.000
REF PAV MRK TY I(W)36"(YLD TRI)(100MIL)
EA 4.000 $75.000 $100.000 $100.000
REF PROF PAV MRK TY I(W)6"(SLD)(100MIL)
LF 45,000.000 $0.850 $1.100 $1.100
REF PROF PAV MRK TY I(Y)6"(BRK)(100MIL)
LF 9,028.000 $0.850 $1.300 $1.300
REF PROF PAV MRK TY I(Y)6"(SLD)(100MIL)
LF 19,325.000 $0.850 $1.100 $1.100
REFL PAV MRKR TY II-A-A
EA 800.000 $3.500 $4.000 $4.000
GEOGRID BASE REINFORCEMENT (TY II)
SY 76,502.000 $1.400 $5.000 $7.870
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $22,500.000 $18,000.000
TMA (STATIONARY)
DAY 300.000 $200.000 $250.000 $325.000
TMA (MOBILE OPERATION)
HR 50.000 $100.000 $175.000 $250.000
Totals: $4,585,160.310 $6,203,272.060 $7,169,479.840