FANNIN SH 78 (0279-02-050)

Items: 84

County: FANNIN
Length: 9.2100 MILES
Highway: SH 78
District: PARIS
Control Number: 0279-02-050
DBE Goal: 2.0%
Project: F 2025(825)
Guaranty: $100,000.00
Time: 237 WORKING DAYS
Engineer's Estimate: $18,901,765.52
Date: 06/04/2025 (1 year ago)
Contract Number: 6253004
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00187423
Contract Type: Federal
Project Description: FDR W/OVERLAY
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
AARON BLOOM
MELESE NORCHA
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (8)
E
Engineer's Estimate
$18,901,765.52
Over/Under Est: -18.16% -$3,432,782.53
Over/Under Est: -10.95% -$2,070,246.51
Amt Left: 8.81% $1,362,536.02
$17,198,519.95
Over/Under Est: -9.01% -$1,703,245.57
Amt Left: 11.18% $1,729,536.96
Delta: -2.18% -$367,000.94
$17,946,665.10
Over/Under Est: -5.05% -$955,100.42
Amt Left: 16.02% $2,477,682.11
Delta: -4.35% -$748,145.15
Over/Under Est: -3.07% -$579,835.87
Amt Left: 18.44% $2,852,946.66
Delta: -2.09% -$375,264.55
Over/Under Est: -0.5% -$94,731.09
Amt Left: 21.58% $3,338,051.44
Delta: -2.65% -$485,104.78
$19,141,320.76
Over/Under Est: 1.27% $239,555.24
Amt Left: 23.74% $3,672,337.77
Delta: -1.78% -$334,286.33
Over/Under Est: 15.72% $2,970,880.90
Amt Left: 41.4% $6,403,663.43
Delta: -14.27% -$2,731,325.66
Subcontractor Percentage Amount
RK HALL, LLC 38.11% $5,895,229.42
CATOCON, INC. 2.36% $365,068.00
MOJICA CONSTRUCTION LLC 2.20% $340,317.63
TRAFFIC HIGHWAY MAINTENANCE, LLC 0.95% $146,955.34
SOUTHERN CROSS CONTRACTORS, LLC 0.78% $120,658.07
J. H. ODEN CONTRACTING COMPANY 0.71% $109,829.78
TEXAS TRAFFIC AND BARRICADE, LLC 0.18% $27,844.17
DUSTROL, INC. 0.12% $18,562.78
Total: 45.41% $7,024,465.19

Bid Items & Bid Tabulations

84 Total 0 of 84
FANNIN  |  SH 78  |  PARIS  |  0279-02-050  |  06/04/2025  |  $18,901,765.52  |  F 2025(825)  |  REHAB EXIST ROADWAY  |  237 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
D. L. LENNON INCORPORATED - CONTRACTOR
FOUTSCO PAVING COMPANY, LLC
CDM HOLDINGS
OVERLAND CORPORATION
RICHARD DRAKE CONSTRUCTION COMPANY, L.P.
HIGHWAY 19 CONSTRUCTION LLC
RK HALL, LLC
A. K. GILLIS & SONS, LLC
PREPARING ROW
STA 486.000 $1,400.000 $1,039.000 $1,100.000 $1,000.000 $1,300.000 $790.000 $750.000 $862.500 $1,500.000
REMOV CONC (MOWSTRIP)
SY 2,187.000 $50.000 $10.000 $10.000 $15.000 $11.000 $26.000 $26.000 $25.690 $25.000
REMOV CONC (DRIVEWAYS)
SY 276.000 $20.000 $10.000 $10.000 $50.000 $47.000 $35.000 $35.000 $13.800 $12.000
SUBGR WIDEN (OC)
STA 78.000 $300.000 $224.000 $1,000.000 $1,000.000 $600.000 $1,020.000 $450.000 $529.390 $1,000.000
EMBANK (VEH)(OC)(TY B)
CY 76.000 $65.000 $12.000 $100.000 $50.000 $130.000 $450.000 $450.000 $86.140 $1,000.000
BACKFILL (TY A)
STA 486.000 $400.000 $360.000 $150.000 $425.000 $500.000 $500.000 $500.000 $401.800 $1,000.000
ROAD GRADER WORK (ORD COMP)
STA 486.000 $260.000 $230.000 $75.000 $150.000 $300.000 $450.000 $450.000 $198.800 $1,000.000
BROADCAST SEED (TEMP_WARM)
SY 135,098.000 $0.180 $0.150 $0.150 $0.200 $0.240 $0.170 $0.250 $0.170 $0.250
BROADCAST SEED (TEMP_COOL)
SY 135,098.000 $0.200 $0.150 $0.150 $0.200 $0.250 $0.170 $0.250 $0.170 $0.250
STRAW/HAY MLCH SEED(PERM_RURAL_SAND)
SY 270,195.000 $0.300 $0.250 $0.250 $0.300 $0.420 $0.270 $0.350 $0.290 $0.400
VEGETATIVE WATERING
TGL 1,621.000 $25.000 $0.010 $1.000 $50.000 $68.850 $55.000 $10.000 $89.030 $5.000
SOIL RET BLKT(SL_MOD_CLAY_SHORT)
SY 1,000.000 $4.400 $2.000 $2.000 $3.000 $1.500 $2.000 $7.000 $2.300 $5.000
FL BS (CMP IN PLC)(TY A GR 4)
TON 947.000 $65.000 $36.000 $25.000 $75.000 $66.000 $75.000 $65.000 $47.430 $50.820
FL BS (CMP IN PLC)(TY A GR 4) (4")
SY 224,620.000 $18.000 $8.970 $11.000 $11.000 $12.500 $11.000 $9.880 $9.330 $15.460
CEMENT
TON 1,043.000 $270.000 $225.000 $300.000 $280.000 $400.000 $290.000 $350.000 $279.740 $225.000
EMULSION (STANDARD YIELD)
GAL 855,203.000 $3.500 $3.470 $3.150 $3.150 $2.750 $3.400 $4.000 $3.360 $3.760
EMUL TRT(EXIST MATRL & NEW BASE)(10")
SY 217,608.000 $5.300 $4.550 $5.200 $4.800 $7.000 $5.200 $6.500 $8.600 $8.440
SP MIXES SP-C PG64-22
TON 47,663.000 $118.000 $117.080 $125.450 $120.000 $124.500 $116.500 $129.000 $137.890 $146.350
TACK COAT
GAL 10,832.000 $5.480 $6.500 $7.000 $6.800 $3.250 $6.800 $6.800 $7.660 $8.125
PLANE ASPH CONC PAV(0" TO 2")
SY 7,822.000 $4.500 $8.500 $2.500 $8.000 $7.000 $8.000 $7.500 $3.600 $5.250
CUT & RESTORING PAV
SY 34.000 $200.000 $50.000 $50.000 $330.000 $153.000 $350.000 $350.000 $202.010 $100.000
TRENCH EXCAVATION PROTECTION
LF 19.000 $15.000 $5.000 $5.000 $20.000 $5.000 $10.000 $10.000 $17.250 $15.000
RIPRAP (MOW STRIP)(4 IN)
CY 287.000 $650.000 $615.000 $615.000 $990.000 $625.000 $550.000 $550.000 $776.250 $675.000
CLEANING AND SEALING EXIST JOINTS (CL3)
LF 276.000 $25.000 $55.000 $55.000 $48.000 $56.000 $45.000 $75.000 $48.300 $44.000
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 5.000 $700.000 $650.000 $650.000 $1,000.000 $660.000 $1,000.000 $1,000.000 $1,035.000 $900.000
CONC BOX CULV (3 FT X 3 FT)(EXTEND)
LF 3.000 $1,000.000 $700.000 $700.000 $1,050.000 $710.000 $1,000.000 $1,000.000 $1,150.000 $1,000.000
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
LF 7.000 $1,200.000 $800.000 $800.000 $1,200.000 $810.000 $1,200.000 $1,200.000 $1,265.000 $1,100.000
RC PIPE (CL III)(18 IN)
LF 4.000 $100.000 $70.000 $70.000 $100.000 $70.000 $150.000 $150.000 $80.500 $70.000
RC PIPE (CL III)(30 IN)
LF 50.000 $140.000 $115.000 $115.000 $215.000 $115.000 $190.000 $190.000 $172.500 $150.000
WINGWALL (PW - 2) (HW=4 FT)
EA 1.000 $12,000.000 $15,000.000 $15,000.000 $7,500.000 $15,200.000 $16,000.000 $16,000.000 $20,700.000 $18,000.000
WINGWALL (PW - 2) (HW=6 FT)
EA 2.000 $14,000.000 $18,000.000 $18,000.000 $15,200.000 $18,200.000 $24,000.000 $24,000.000 $25,300.000 $22,000.000
SET (REMOV & REINSTALL)
EA 10.000 $750.000 $500.000 $500.000 $1,650.000 $500.000 $1,000.000 $1,000.000 $920.000 $800.000
REMOV STR (WINGWALL)
EA 3.000 $2,000.000 $850.000 $850.000 $2,500.000 $860.000 $1,000.000 $1,000.000 $1,725.000 $1,500.000
REMOV STR (PIPE)
LF 42.000 $18.000 $7.000 $7.000 $55.000 $7.000 $50.000 $50.000 $17.250 $15.000
MOBILIZATION
LS 1.000 $1,718,342.300 $1,047,225.000 $1,400,000.000 $1,820,000.000 $1,775,000.000 $2,640,021.000 $1,900,000.000 $1,339,892.450 $1,673,883.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $6,000.000 $5,340.000 $50,000.000 $13,500.000 $5,000.000 $25,500.000 $10,000.000 $71,394.820 $29,733.333
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $15,000.000 $25,000.000 $40,000.000 $12,500.000 $25,000.000 $30,000.000 $17,000.000 $9,940.370 $17,500.000
TMA (STATIONARY)
DAY 205.000 $150.000 $250.000 $150.000 $250.000 $185.000 $450.000 $1,000.000 $586.630 $750.000
TMA (MOBILE OPERATION)
DAY 80.000 $150.000 $250.000 $1.000 $125.000 $850.000 $995.000 $1,000.000 $1,481.130 $750.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 1,890.000 $50.000 $45.000 $20.000 $55.000 $55.000 $49.000 $85.000 $51.750 $65.000
ROCK FILTER DAMS (REMOVE)
LF 1,890.000 $15.000 $9.000 $5.000 $17.000 $18.000 $10.000 $10.000 $10.350 $9.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,930.000 $5.500 $4.000 $3.500 $5.000 $3.600 $4.400 $4.000 $4.600 $5.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,930.000 $2.000 $0.500 $0.300 $2.000 $1.250 $0.600 $1.000 $0.580 $2.000
INTERSECTIONS (ACP)
SY 1,033.000 $55.000 $70.600 $50.000 $100.000 $70.000 $96.700 $93.000 $64.880 $63.250
DRIVEWAYS (CONC)
SY 276.000 $100.000 $115.000 $95.000 $250.000 $97.000 $200.000 $120.000 $115.000 $100.000
DRIVEWAYS (ACP)
SY 318.000 $70.000 $76.600 $65.000 $80.000 $160.000 $78.500 $90.000 $71.370 $63.250
DRIVEWAYS (BASE)
SY 5,583.000 $35.000 $33.000 $15.000 $35.000 $19.000 $14.600 $45.000 $18.480 $55.150
TURNOUTS (ACP)
SY 730.000 $105.000 $152.500 $75.000 $125.000 $85.000 $130.000 $120.000 $191.680 $165.625
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 97,270.000 $0.300 $0.206 $0.150 $0.150 $0.200 $0.160 $0.350 $0.320 $0.160
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 48,635.000 $0.300 $0.208 $0.150 $0.150 $0.200 $0.160 $0.350 $0.400 $0.160
MTL W-BEAM GD FEN (STEEL POST)
LF 1,375.000 $25.000 $25.690 $26.000 $26.500 $50.460 $25.690 $27.000 $37.440 $25.690
MTL W-BEAM GD FEN ADJUSTMENT
LF 2,325.000 $10.000 $14.890 $15.000 $16.000 $32.380 $14.890 $15.000 $15.420 $14.890
REMOVE METAL BEAM GUARD FENCE
LF 50.000 $6.000 $2.500 $2.500 $2.750 $15.000 $2.500 $2.500 $18.500 $2.500
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $3,000.000 $3,190.000 $3,000.000 $3,300.000 $3,050.000 $3,190.000 $3,190.000 $3,762.480 $3,190.000
GUARDRAIL END TREATMENT (MOVE & RESET)
EA 42.000 $1,400.000 $690.000 $690.000 $725.000 $1,050.000 $690.000 $690.000 $1,295.280 $690.000
GUARDRAIL END TREATMENT (REMOVE)
EA 2.000 $350.000 $250.000 $250.000 $265.000 $300.000 $250.000 $250.000 $370.080 $250.000
MAILBOX INSTALL-M (TWG-POST) TY 1
EA 4.000 $550.000 $700.000 $500.000 $550.000 $638.000 $525.000 $900.000 $632.500 $550.000
MAILBOX INSTALL-S (WC-POST) TY 3
EA 132.000 $275.000 $170.000 $200.000 $200.000 $243.000 $190.000 $318.000 $172.500 $150.000
MAILBOX INSTALL-D (WC-POST) TY 3
EA 6.000 $300.000 $220.000 $250.000 $250.000 $348.000 $225.000 $510.000 $230.000 $200.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 132.000 $720.000 $710.000 $530.000 $700.000 $640.000 $635.000 $650.000 $701.500 $610.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 34.000 $850.000 $764.000 $620.000 $850.000 $741.000 $725.000 $770.000 $805.000 $700.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U)
EA 11.000 $950.000 $917.000 $600.000 $1,000.000 $837.000 $940.000 $740.000 $862.500 $750.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 2.000 $1,000.000 $1,170.000 $800.000 $800.000 $972.000 $760.000 $980.000 $1,006.250 $875.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 4.000 $1,150.000 $1,272.000 $800.000 $1,250.000 $1,062.000 $1,143.000 $1,250.000 $1,035.000 $900.000
RELOCATE SM RD SN SUP&AM(HIST MRKR)
EA 1.000 $100.000 $2,000.000 $700.000 $5,000.000 $110.000 $650.000 $655.000 $632.500 $550.000
REMOVE SM RD SN SUP&AM
EA 173.000 $120.000 $76.000 $100.000 $125.000 $99.000 $75.000 $95.000 $115.000 $100.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 67.000 $30.000 $25.000 $25.000 $30.000 $45.000 $30.000 $45.000 $55.510 $25.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 64.000 $75.000 $39.000 $70.000 $60.000 $76.000 $60.000 $79.000 $69.000 $60.000
WK ZN PAV MRK NON-REMOV (W)6"(SLD)
LF 97,617.000 $0.300 $0.210 $0.200 $0.250 $0.210 $0.210 $0.210 $0.400 $0.210
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 18,460.000 $0.500 $0.270 $0.280 $0.300 $0.270 $0.270 $0.270 $0.400 $0.270
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 87,284.000 $0.500 $0.210 $0.200 $0.250 $0.210 $0.210 $0.210 $0.400 $0.210
WK ZN PAV MRK REMOV (REFL) TY II-A-A
EA 903.000 $5.000 $5.000 $4.000 $5.000 $5.000 $5.000 $5.000 $5.750 $5.000
WK ZN PAV MRK REMOV (W)6"(BRK)
LF 2,960.000 $1.750 $1.500 $0.340 $0.400 $1.500 $1.500 $1.500 $3.690 $1.500
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 1,776.000 $2.000 $2.500 $0.100 $1.000 $2.500 $1.800 $2.000 $2.070 $2.450
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 12,484.000 $2.200 $2.500 $0.100 $1.000 $2.500 $1.800 $2.000 $2.070 $2.450
REFL PAV MRK TY I (W)8"(SLD)(090MIL)
LF 449.000 $1.000 $1.200 $1.000 $1.100 $1.200 $1.200 $1.200 $2.300 $1.200
REFL PAV MRK TY I (W)24"(SLD)(090MIL)
LF 222.000 $11.000 $7.550 $8.000 $8.250 $7.550 $7.550 $7.550 $8.050 $7.550
REF PAV MRK TY I(W)36"(YLD TRI)(090MIL)
EA 26.000 $55.000 $75.000 $40.000 $50.000 $75.000 $80.000 $76.000 $74.750 $75.000
REFL PAV MRK TY I (W)6"(BRK)(090MIL)
LF 2,958.000 $0.760 $0.600 $0.600 $0.650 $0.600 $0.700 $0.600 $0.980 $0.600
REFL PAV MRK TY I (W)6"(SLD)(090MIL)
LF 97,617.000 $0.850 $0.530 $0.540 $0.550 $0.530 $0.580 $0.530 $0.810 $0.530
REFL PAV MRK TY I (Y)6"(BRK)(090MIL)
LF 10,710.000 $0.850 $0.600 $0.560 $0.600 $0.600 $0.650 $0.600 $0.980 $0.600
REFL PAV MRK TY I (Y)6"(SLD)(090MIL)
LF 43,917.000 $0.870 $0.530 $0.540 $0.550 $0.530 $0.580 $0.530 $0.810 $0.530
REFL PAV MRKR TY II-A-A
EA 903.000 $6.000 $4.450 $3.850 $4.000 $4.450 $4.450 $5.000 $5.750 $4.450
REFL PAV MRKR TY II-C-R
EA 148.000 $6.000 $4.450 $4.000 $5.000 $4.450 $4.450 $5.000 $5.750 $4.450
Totals: $18,901,765.520 $15,468,982.990 $16,831,519.010 $17,198,519.950 $17,946,665.100 $18,321,929.650 $18,807,034.330 $19,141,320.760 $21,872,646.415
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
Description Amount
SAFETY CONTINGENCY: CONTRACTOR FORCE ACCOUNT WORK (PART) $343,668.50
EROSION CONTROL MAINTENANCE: CONTRACTOR FORCE ACCOUNT WORK (PART) $171,834.20
Total: $515,502.70