FALLS CR (0909-38-081)

Items: 43

County: FALLS
Length: N/A
Highway: CR
District: WACO
Control Number: 0909-38-081
DBE Goal: N/A
Project: BR 2018(295)
Guaranty: N/A
Time: 225 WORKING DAYS
Engineer's Estimate: $1,390,650.00
Date: 03/05/2019 (7 years ago)
Contract Number: N/A
Type: REPL BR & APPRS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (6)
E
Engineer's Estimate
$1,390,650.00
$1,340,676.70
Over/Under Est: -3.59% -$49,973.30
Over/Under Est: 2.16% $30,007.45
Amt Left: 5.97% $79,980.75
Over/Under Est: 2.3% $32,052.00
Amt Left: 6.12% $82,025.30
Delta: -0.14% -$2,044.55
Over/Under Est: 10.24% $142,442.20
Amt Left: 14.35% $192,415.50
Delta: -7.76% -$110,390.20
Over/Under Est: 12.83% $178,419.00
Amt Left: 17.04% $228,392.30
Delta: -2.35% -$35,976.80
$1,623,322.20
Over/Under Est: 16.73% $232,672.20
Amt Left: 21.08% $282,645.50
Delta: -3.46% -$54,253.20

Bid Items & Bid Tabulations

43 Total 0 of 43
FALLS  |  CR  |  WACO  |  0909-38-081  |  03/05/2019  |  $1,390,650.00  |  BR 2018(295)  |  REPL BR & APPRS  |  225 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
ELLIS-MCGINNIS CONSTRUCTION CO.
JAMES CONSTRUCTION GROUP, L.L.C.
HODGES AND SON CONSTRUCTION COMPANY, INC.
PROJECT ALLIED RESOURCES, LLC
KNIFE RIVER CORPORATION - SOUTH
PIERCE R & B LLC
PREPARING ROW
STA 12.500 $2,000.000 $1,000.000 $3,350.000 $2,900.000 $3,680.000 $1,850.000 $2,000.000
EXCAVATION (ROADWAY)
CY 214.000 $15.000 $14.000 $16.390 $15.000 $17.200 $50.000 $20.000
EXCAVATION (CHANNEL)
CY 517.000 $15.000 $14.000 $8.310 $10.000 $17.200 $20.000 $20.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 563.000 $15.000 $18.000 $32.880 $20.000 $22.100 $40.000 $25.000
BROADCAST SEED (TEMP) (WARM)
SY 670.000 $0.500 $1.000 $1.240 $1.000 $2.200 $2.000 $2.500
BROADCAST SEED (TEMP) (COOL)
SY 670.000 $0.500 $1.000 $1.240 $1.000 $2.200 $2.000 $2.500
DRILL SEEDING (PERM) (RURAL) (SANDY)
SY 1,340.000 $1.000 $1.200 $1.550 $2.000 $3.300 $3.000 $3.500
VEGETATIVE WATERING
MG 22.000 $20.000 $1.600 $75.380 $1.000 $86.000 $50.000 $25.000
SOIL RETENTION BLANKETS (CL 1) (TY B)
SY 766.000 $1.500 $2.000 $1.860 $2.000 $4.400 $4.250 $3.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 498.000 $60.000 $52.000 $44.580 $70.000 $90.000 $58.000 $65.000
REWORK BS MTL (TY A) (6") (ORD COMP)
SY 1,380.000 $3.000 $3.000 $5.760 $3.000 $5.100 $1.750 $8.000
CEM STABIL BKFL
CY 104.000 $160.000 $210.000 $241.130 $200.000 $145.000 $170.000 $200.000
TEMPORARY SPL SHORING (COFFERDAM)
SF 480.000 $30.000 $2.000 $18.170 $20.000 $15.800 $20.000 $30.000
DRILL SHAFT (24 IN)
LF 1,281.000 $150.000 $150.000 $106.210 $90.000 $120.000 $125.000 $124.000
DRILL SHAFT (36 IN)
LF 468.000 $180.000 $250.000 $178.190 $160.000 $249.000 $240.000 $240.000
CL C CONC (ABUT)
CY 72.400 $1,000.000 $960.000 $817.370 $1,100.000 $947.000 $1,200.000 $1,100.000
CL C CONC (CAP)
CY 48.400 $1,000.000 $970.000 $994.430 $1,100.000 $1,270.000 $1,500.000 $1,400.000
CL C CONC (COLUMN)
CY 49.700 $1,000.000 $1,000.000 $1,475.560 $1,200.000 $1,140.000 $975.000 $1,150.000
REINF CONC SLAB
SF 4,030.000 $18.000 $17.800 $19.840 $24.000 $17.100 $24.000 $26.000
REINF CONC SLAB (SLAB BEAM)
SF 4,810.000 $15.000 $13.000 $14.310 $18.000 $16.700 $18.000 $21.000
PRESTR CONC SLAB BEAM (5SB12)
LF 910.000 $160.000 $150.000 $167.700 $170.000 $164.000 $190.000 $172.000
PRESTR CONC GIRDER (TX28)
LF 614.000 $150.000 $155.000 $160.890 $180.000 $157.000 $220.000 $188.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 882.000 $85.000 $85.000 $59.450 $140.000 $109.000 $81.000 $121.000
RAIL (TY T223)
LF 760.000 $110.000 $120.000 $90.770 $110.000 $108.000 $115.000 $116.000
ARMOR JOINT (SEALED)
LF 132.000 $100.000 $85.000 $87.940 $75.000 $71.000 $90.000 $90.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 2.000 $20,000.000 $12,000.000 $9,045.180 $8,000.000 $13,600.000 $9,500.000 $8,000.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $30,000.000 $28,500.000 $13,963.410 $12,000.000 $27,900.000 $19,500.000 $50,000.000
MOBILIZATION
LS 1.000 $120,000.000 $100,000.000 $140,000.000 $120,000.000 $170,000.000 $156,000.000 $154,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 15.000 $1,000.000 $770.000 $7,000.000 $2,500.000 $1,080.000 $850.000 $2,000.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 208.000 $45.000 $60.000 $60.000 $5.000 $66.000 $60.000 $35.000
ROCK FILTER DAMS (REMOVE)
LF 208.000 $10.000 $10.000 $20.000 $1.000 $22.000 $20.000 $9.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,440.000 $3.000 $3.100 $3.500 $1.000 $3.850 $5.000 $3.500
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,440.000 $1.000 $1.400 $1.500 $0.250 $1.650 $1.500 $1.000
MTL W-BEAM GD FEN (STEEL POST)
LF 325.000 $23.000 $21.300 $22.000 $26.000 $31.700 $23.000 $22.500
MTL BEAM GD FEN TRANS (TL2)
EA 6.000 $900.000 $890.000 $850.000 $1,200.000 $1,380.000 $1,035.000 $943.950
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 6.000 $1,100.000 $900.000 $1,050.000 $1,200.000 $1,550.000 $1,035.000 $954.000
MTL BM GD FEN TRANS (NON - SYM)
EA 6.000 $900.000 $445.000 $650.000 $800.000 $978.000 $1,035.000 $475.000
GUARDRAIL END TREATMENT (INSTALL)
EA 6.000 $2,500.000 $2,475.000 $2,430.000 $2,800.000 $2,930.000 $2,550.000 $2,600.000
WIRE FENCE (TY C)
LF 330.000 $12.000 $8.300 $4.000 $12.000 $14.700 $13.000 $12.000
REMOVE SM RD SN SUP&AM
EA 4.000 $84.000 $20.000 $10.000 $50.000 $67.000 $50.000 $250.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 8.000 $25.000 $21.000 $20.000 $15.000 $75.000 $26.000 $30.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 12.000 $30.000 $36.000 $22.000 $30.000 $52.000 $26.000 $40.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 56.000 $100.000 $65.000 $65.890 $85.000 $86.000 $75.000 $124.000
Totals: $1,390,650.000 $1,340,676.700 $1,420,657.462 $1,422,702.000 $1,533,092.200 $1,569,069.000 $1,623,322.200