Show Job Controls
Bid Cobra

FALLS FM 413 (0808-02-012)

Items: 54

County: FALLS
Length: N/A
Highway: FM 413
District: WACO
Control Number: 0808-02-012
DBE Goal: N/A
Project: BR 2022(559)
Guaranty: N/A
Time: 75 WORKING DAYS
Engineer's Estimate: $928,258.40
Date: 06/01/2022 (4 years ago)
Contract Number: N/A
Type: REPLACE BRIDGE AND APPROACHES
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$928,258.40
$995,631.79
Over/Under Est: 7.26% $67,373.39
$1,028,790.84
Over/Under Est: 10.83% $100,532.44
Amt Left: 3.33% $33,159.05
$1,069,663.10
Over/Under Est: 15.23% $141,404.70
Amt Left: 7.44% $74,031.31
Delta: -3.97% -$40,872.26
Over/Under Est: 26.26% $243,766.50
Amt Left: 17.72% $176,393.11
Delta: -9.57% -$102,361.80

Bid Items & Bid Tabulations

54 Total 0 of 54
FALLS  |  FM 413  |  WACO  |  0808-02-012  |  06/01/2022  |  $928,258.40  |  BR 2022(559)  |  REPLACE BRIDGE AND APPROACHES  |  75 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
PIERCE R & B LLC
ENCINO LANDSCAPE, INC.
HODGES AND SON CONSTRUCTION COMPANY, INC.
PREPARING ROW
STA 7.100 $1,500.000 $3,000.000 $2,200.000 $5,000.000 $3,000.000
PREP ROW (TREE) (18"-36" DIA.)
EA 7.000 $1,600.000 $1,250.000 $650.000 $1,000.000 $1,000.000
REMOVING STAB BASE & ASPH PAV (0-6")
SY 1,406.000 $4.000 $5.000 $8.500 $20.000 $15.000
EXCAVATION (ROADWAY)
CY 61.000 $17.000 $50.000 $14.000 $20.000 $50.000
EXCAVATION (CHANNEL)
CY 1,500.000 $17.000 $14.000 $14.000 $20.000 $15.000
EMBANKMENT (FINAL)(DENS CONT)(TY C)
CY 1,280.000 $17.000 $15.000 $14.000 $20.000 $15.000
FURNISHING AND PLACING TOPSOIL (4")
SY 5,326.000 $2.000 $0.650 $3.000 $1.000 $4.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 5,326.000 $0.700 $0.550 $0.560 $0.050 $1.000
BROADCAST SEED (TEMP)(WARM OR COOL)
SY 5,326.000 $0.700 $0.450 $0.470 $0.050 $0.500
VEGETATIVE WATERING
MG 86.400 $25.000 $20.000 $1.000 $10.000 $1.000
SOIL RETENTION BLANKETS (CL 1) (TY C)
SY 3,471.000 $2.000 $1.500 $1.600 $2.000 $2.500
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 593.000 $60.000 $51.000 $74.000 $80.000 $65.000
PRIME COAT(MC-30 OR AE-P)
GAL 363.000 $7.000 $8.600 $14.900 $15.000 $15.000
ASPH (CRS-2)
GAL 817.000 $6.000 $5.250 $7.440 $8.000 $15.000
AGGR(TY-D GR-4 OR TY-L GR-4)
CY 14.000 $400.000 $500.000 $1,000.000 $300.000 $2,000.000
CEM STABIL BKFL
CY 83.000 $170.000 $188.000 $215.000 $200.000 $225.000
DRILL SHAFT (24 IN)
LF 426.000 $175.000 $215.000 $180.000 $210.000 $135.000
CL B CONC (FLUME)
CY 7.100 $550.000 $1,350.000 $1,000.000 $600.000 $600.000
CL C CONC (ABUT)(HPC)
CY 20.800 $1,000.000 $1,525.000 $1,200.000 $1,500.000 $1,200.000
CL C CONC (CAP)(HPC)
CY 16.000 $1,100.000 $1,625.000 $1,800.000 $1,800.000 $1,200.000
CL C CONC (COLUMN)(HPC)
CY 9.100 $1,100.000 $1,635.000 $1,800.000 $1,800.000 $1,200.000
REINF CONC SLAB (SLAB BEAM)
SF 3,855.000 $20.000 $19.000 $20.000 $20.000 $26.000
APPROACH SLAB
CY 48.000 $500.000 $610.000 $800.000 $800.000 $700.000
PRESTR CONC SLAB BEAM (4SB12)
LF 948.000 $180.000 $185.000 $159.000 $180.000 $200.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 714.000 $100.000 $112.000 $125.000 $120.000 $150.000
RIPRAP (MOW STRIP)(4 IN)
CY 38.000 $460.000 $550.000 $600.000 $500.000 $600.000
RAIL (TY T223)
LF 264.000 $120.000 $125.000 $130.000 $140.000 $140.000
ARMOR JOINT (SEALED)
LF 56.000 $110.000 $146.000 $107.000 $120.000 $150.000
REMOV STR (BRIDGE 0 - 99 FT LENGTH)
EA 1.000 $25,000.000 $30,000.000 $22,500.000 $19,999.000 $30,000.000
MOBILIZATION
LS 1.000 $85,000.000 $97,000.000 $95,000.000 $70,000.000 $100,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 5.000 $5,000.000 $2,200.000 $3,500.000 $6,000.000 $7,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 152.000 $30.000 $36.000 $42.000 $40.000 $1.000
ROCK FILTER DAMS (REMOVE)
LF 192.000 $10.000 $10.000 $10.000 $10.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,534.000 $3.000 $6.500 $2.850 $5.000 $1.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,534.000 $1.000 $1.500 $1.100 $1.000 $1.000
RUMBLE STRIPS (SHOULDER)
LF 900.000 $2.000 $4.250 $4.280 $0.300 $10.000
RUMBLE STRIPS (CENTERLINE)
LF 450.000 $2.000 $4.250 $4.360 $0.350 $10.000
MTL W-BEAM GD FEN (STEEL POST)
LF 250.000 $27.000 $30.000 $38.000 $31.000 $35.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,950.000 $2,500.000 $2,275.000 $2,200.000 $2,200.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,800.000 $3,000.000 $3,430.000 $3,400.000 $3,500.000
WIRE FENCE (TY C)
LF 50.000 $19.000 $40.000 $20.000 $20.000 $20.000
WIRE FENCE (WATER GAP)
LF 75.000 $50.000 $75.000 $50.000 $60.000 $80.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 4.000 $700.000 $750.000 $800.000 $800.000 $1,000.000
REMOVE SM RD SN SUP&AM
EA 2.000 $100.000 $62.000 $100.000 $100.000 $100.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 4.000 $25.000 $40.000 $39.000 $30.000 $20.000
REMOVE DELIN & OBJECT MARKER ASSMS
EA 15.000 $25.000 $33.000 $1.000 $25.000 $20.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 11.000 $30.000 $50.000 $50.000 $40.000 $50.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,420.000 $2.000 $2.600 $4.500 $1.000 $3.000
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 178.000 $2.000 $2.600 $3.000 $1.000 $3.000
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 710.000 $2.000 $2.600 $2.750 $1.000 $3.000
REFL PAV MRKR TY II-A-A
EA 18.000 $12.000 $41.000 $45.000 $5.000 $40.000
TACK COAT
GAL 454.000 $4.000 $0.010 $0.020 $6.000 $8.000
D-GR HMA TY-C SAC-B PG64-22 (EXEMPT)
TON 200.000 $130.000 $145.000 $300.000 $210.000 $250.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $2,500.000 $2,000.000 $9,500.000 $16,000.000
Totals: $928,258.400 $995,631.790 $1,028,790.840 $1,069,663.100 $1,172,024.900