FALLS FM 935 (0752-04-024)

Items: 107

County: FALLS
Length: N/A
Highway: FM 935
District: WACO
Control Number: 0752-04-024
DBE Goal: N/A
Project: STP 1702(621)
Guaranty: N/A
Time: 277 WORKING DAYS
Engineer's Estimate: $3,976,979.45
Date: 08/09/2017 (8 years ago)
Contract Number: N/A
Type: WDN, GR, BS, SURF, ADD SHLDRS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (5)
E
Engineer's Estimate
$3,976,979.45
$3,524,688.87
Over/Under Est: -11.37% -$452,290.58
Over/Under Est: -4.2% -$167,025.23
Amt Left: 8.09% $285,265.35
Over/Under Est: 7.32% $291,076.54
Amt Left: 21.09% $743,367.12
Delta: -12.02% -$458,101.77
Over/Under Est: 48.42% $1,925,616.67
Amt Left: 67.46% $2,377,907.25
Delta: -38.30% -$1,634,540.13
$6,327,951.00
Over/Under Est: 59.11% $2,350,971.55
Amt Left: 79.53% $2,803,262.13
Delta: -7.21% -$425,354.88

Bid Items & Bid Tabulations

107 Total 0 of 107
FALLS  |  FM 935  |  WACO  |  0752-04-024  |  08/09/2017  |  $3,976,979.45  |  STP 1702(621)  |  WDN, GR, BS, SURF, ADD SHLDRS  |  277 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
KNIFE RIVER CORPORATION - SOUTH
JAMES CONSTRUCTION GROUP, L.L.C.
OLDCASTLE MATERIALS TEXAS, INC.
FNH CONSTRUCTION, LLC
PREPARING ROW
STA 51.000 $2,100.000 $500.000 $900.000 $1,500.000 $1,500.000 $7,000.000
EXCAVATION (ROADWAY)
CY 28,176.000 $8.000 $8.000 $6.620 $6.000 $15.000 $20.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 13,796.000 $8.000 $8.000 $4.480 $10.000 $15.000 $30.000
BLOCK SODDING
SY 200.000 $7.000 $7.000 $4.540 $12.000 $15.000 $5.500
DRILL SEEDING (PERM) (RURAL) (CLAY)
SY 198,637.000 $0.100 $0.090 $0.080 $0.100 $0.080 $0.500
DRILL SEEDING (TEMP) (WARM)
SY 99,319.000 $0.100 $0.070 $0.060 $0.080 $0.010 $0.500
DRILL SEEDING (TEMP) (COOL)
SY 99,319.000 $0.100 $0.070 $0.060 $0.080 $0.010 $0.500
VEGETATIVE WATERING
MG 3,230.000 $12.500 $5.000 $1.000 $10.000 $0.010 $15.000
SOIL RETENTION BLANKETS (CL 1) (TY D)
SY 19,863.000 $1.000 $1.000 $0.900 $1.040 $1.100 $1.250
PROOF ROLLING
HR 45.000 $100.000 $110.000 $50.000 $100.000 $101.000 $150.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 16,349.000 $35.000 $42.000 $40.000 $33.000 $49.350 $26.500
REWORK BS MATL (TY C)(9")(ORD COMP)
SY 69,699.000 $1.250 $1.000 $1.220 $2.000 $5.000 $2.500
CEMENT
TON 1,433.000 $150.000 $130.000 $132.000 $140.000 $145.000 $151.000
CEMENT TREAT (EXIST MATL) (7")
SY 99,857.000 $1.500 $1.700 $1.000 $1.500 $5.000 $3.000
EMULS ASPH (BS OR SUBGR TRT)(MS-2)
GAL 23,323.000 $2.500 $2.200 $1.950 $7.000 $2.050 $4.000
ASPH (CRS-2)
GAL 57,921.000 $2.000 $2.000 $1.940 $2.250 $1.850 $3.000
AGGR (TY-PD GR-4 OR TY-PL GR-4)(SAC-B)
CY 772.000 $150.000 $87.000 $125.000 $147.000 $110.000 $225.000
ASPH(AC-15P,AC-20XP,AC10-2TR,AC-12-5TR)
GAL 33,787.000 $3.300 $2.200 $2.250 $2.750 $2.150 $3.000
AGGR(TY D GR 3 OR TY L GR 3)
CY 1,016.000 $100.000 $60.000 $105.000 $147.000 $127.000 $225.000
CEM STABIL BKFL
CY 101.000 $150.000 $120.000 $149.500 $50.000 $125.000 $140.000
CUT & RESTORING PAV
SY 108.000 $100.000 $60.000 $85.000 $100.000 $71.050 $200.000
TRENCH EXCAVATION PROTECTION
LF 132.000 $5.000 $25.000 $7.220 $5.000 $10.000 $3.500
TEMPORARY SPL SHORING
SF 2,237.000 $20.000 $25.000 $17.530 $50.000 $20.000 $42.000
RIPRAP (CONC)(4 IN)
CY 2.000 $450.000 $1,000.000 $819.000 $800.000 $500.000 $550.000
RIPRAP (CONC)(5 IN)
CY 8.200 $525.000 $900.000 $560.000 $450.000 $550.000 $650.000
RIPRAP (STONE PROTECTION)(12 IN)
CY 149.000 $110.000 $130.000 $113.000 $120.000 $100.000 $185.000
RIPRAP (STONE PROTECTION)(18 IN)
CY 373.000 $110.000 $100.000 $98.000 $120.000 $150.000 $200.000
RIPRAP (MOW STRIP)(4 IN)
CY 202.000 $445.000 $400.000 $412.000 $380.000 $500.000 $500.000
RETROFIT RAIL (TY T401)
LF 183.670 $100.000 $150.000 $165.000 $160.000 $285.000 $185.000
CONC BOX CULV (3 FT X 2 FT)
LF 72.000 $200.000 $220.000 $221.000 $200.000 $350.000 $250.000
CONC BOX CULV (4 FT X 3 FT)
LF 44.000 $210.000 $260.000 $255.000 $340.000 $400.000 $300.000
CONC BOX CULV (5 FT X 4 FT)
LF 53.500 $270.000 $300.000 $329.000 $350.000 $450.000 $400.000
CONC BOX CULV (3 FT X 2 FT)(EXTEND)
LF 29.000 $450.000 $400.000 $532.000 $460.000 $375.000 $650.000
CONC BOX CULV (4 FT X 3 FT)(EXTEND)
LF 10.000 $470.000 $500.000 $568.000 $520.000 $465.000 $1,500.000
CONC BOX CULV (4 FT X 4 FT)(EXTEND)
LF 95.000 $570.000 $600.000 $421.000 $550.000 $475.000 $650.000
CONC BOX CULV (5 FT X 4 FT)(EXTEND)
LF 23.500 $620.000 $700.000 $577.000 $800.000 $525.000 $880.000
CONC BOX CULV (6 FT X 4 FT)(EXTEND)
LF 13.000 $800.000 $800.000 $642.000 $1,200.000 $600.000 $1,500.000
CONC BOX CULV (6 FT X 6 FT)(EXTEND)
LF 46.000 $850.000 $900.000 $568.000 $750.000 $650.000 $850.000
RC PIPE (CL III)(18 IN)
LF 1,776.000 $55.000 $42.000 $48.000 $55.000 $46.000 $55.000
RC PIPE (CL III)(24 IN)
LF 334.000 $65.000 $58.000 $65.000 $75.000 $86.000 $85.000
RC PIPE (CL III)(36 IN)
LF 456.000 $150.000 $90.000 $114.000 $105.000 $145.000 $125.000
RC PIPE (CL III)(48 IN)
LF 40.000 $200.000 $140.000 $194.000 $180.000 $200.000 $200.000
JCTBOX(COMPL)(PJB)(5FTX5FT)
EA 2.000 $5,800.000 $4,500.000 $4,281.000 $3,000.000 $4,000.000 $5,000.000
HEADWALL (CH - PW - 0) (DIA= 24 IN)
EA 1.000 $5,500.000 $2,500.000 $6,036.000 $4,500.000 $3,000.000 $3,000.000
WINGWALL (FW - 0) (HW=7 FT)
EA 1.000 $15,000.000 $9,500.000 $7,129.000 $9,000.000 $10,000.000 $17,500.000
WINGWALL (PW - 1) (HW=4 FT)
EA 1.000 $9,500.000 $7,500.000 $6,535.000 $8,500.000 $8,000.000 $10,000.000
WINGWALL (PW - 1) (HW=5 FT)
EA 4.000 $11,000.000 $11,500.000 $6,728.000 $9,000.000 $10,000.000 $10,000.000
WINGWALL (PW - 1) (HW=6 FT)
EA 1.000 $16,000.000 $15,000.000 $8,777.000 $15,500.000 $13,000.000 $15,000.000
WINGWALL (PW - 1) (HW=7 FT)
EA 1.000 $19,500.000 $15,500.000 $8,671.000 $13,000.000 $14,000.000 $18,500.000
SET (TY I)(S=3 FT)(HW=2FT)(6:1)(P)
EA 3.000 $5,000.000 $2,600.000 $7,146.000 $4,000.000 $4,500.000 $5,000.000
SET (TY I)(S=3 FT)(HW=3FT)(3:1)(C)
EA 1.000 $5,100.000 $2,000.000 $6,734.000 $3,500.000 $4,000.000 $3,000.000
SET (TY I)(S=3 FT)(HW=3FT)(4:1)(C)
EA 3.000 $5,200.000 $4,800.000 $7,939.000 $5,500.000 $4,000.000 $8,500.000
SET (TY I)(S= 4 FT)(HW= 4 FT)(3:1) (C)
EA 2.000 $7,000.000 $5,800.000 $8,299.000 $7,800.000 $5,000.000 $12,000.000
SET (TY I)(S= 4 FT)(HW= 5 FT)(3:1) (C)
EA 2.000 $7,700.000 $9,100.000 $9,614.000 $8,800.000 $5,500.000 $15,000.000
SET (TY I)(S= 6 FT)(HW= 5 FT)(3:1) (C)
EA 2.000 $8,100.000 $4,500.000 $8,052.000 $5,500.000 $7,000.000 $13,000.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 4.000 $760.000 $650.000 $866.000 $750.000 $750.000 $1,250.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 76.000 $850.000 $800.000 $969.000 $750.000 $750.000 $1,250.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 1.000 $1,000.000 $900.000 $948.000 $800.000 $800.000 $1,500.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 14.000 $1,000.000 $1,100.000 $1,161.000 $1,200.000 $850.000 $2,000.000
SET (TY II) (36 IN) (RCP) (6: 1) (P)
EA 16.000 $3,700.000 $2,100.000 $3,546.000 $2,200.000 $2,800.000 $5,500.000
SET (TY II) (48 IN) (RCP) (6: 1) (P)
EA 2.000 $9,900.000 $7,000.000 $8,262.000 $9,000.000 $5,000.000 $8,000.000
CLEAN EXIST CULVERTS
EA 8.000 $1,500.000 $2,000.000 $567.000 $350.000 $1,000.000 $500.000
REMOV STR (PIPE)
LF 1,975.460 $10.000 $10.000 $10.310 $11.000 $15.000 $30.000
REMOV STR (BOX CULVERT)
LF 59.430 $70.000 $100.000 $64.950 $150.000 $80.000 $100.000
MOBILIZATION
LS 1.000 $310,000.000 $185,000.480 $380,000.000 $405,000.000 $655,520.000 $600,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 13.000 $5,000.000 $3,000.000 $15,000.000 $7,800.000 $41,000.000 $8,500.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 1,131.000 $26.000 $20.000 $30.000 $30.000 $32.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 1,131.000 $3.000 $1.000 $6.000 $10.000 $7.000 $15.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 852.000 $15.000 $10.000 $10.000 $26.040 $25.000 $40.000
CONSTRUCTION EXITS (REMOVE)
SY 852.000 $7.000 $1.000 $3.000 $11.000 $7.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 6,047.000 $3.000 $3.000 $3.250 $4.000 $3.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 6,047.000 $0.500 $0.500 $0.250 $1.000 $0.500 $2.000
ONE-WAY TRAF CONT (PORT TRAF SIG)
MO 2.000 $7,000.000 $6,500.000 $10,000.000 $2,500.000 $5,500.000 $5,000.000
PORT CTB (DES SOURCE)(SGL SLP)(TY 1)
LF 540.000 $13.000 $15.000 $13.750 $17.000 $18.000 $25.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 300.000 $12.000 $10.000 $7.570 $3.000 $10.000 $20.000
PORT CTB (STKPL)(SGL SLP)(TY 1)
LF 540.000 $11.000 $12.000 $12.580 $9.000 $18.000 $20.000
INTERSECTIONS (SURF TREAT)
SY 2,577.000 $30.000 $25.000 $22.410 $45.000 $46.500 $25.000
DRIVEWAYS (SURF TREAT)
SY 4,018.000 $25.000 $17.000 $24.000 $35.000 $50.350 $25.000
MTL W-BEAM GD FEN (STEEL POST)
LF 2,387.500 $25.000 $25.000 $21.650 $18.350 $18.350 $30.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,500.000 $1,500.000 $2,005.000 $1,260.000 $1,260.000 $1,850.000
SHORT RADIUS
LF 142.000 $35.000 $30.000 $21.650 $24.780 $24.800 $35.000
DRIVEWAY TERMINAL ANCHOR SECTION
EA 6.000 $650.000 $700.000 $515.000 $686.000 $686.000 $1,850.000
MTL W - BEAM GD FEN (LOW FILL CULVERT)
LF 50.000 $55.000 $60.000 $41.410 $53.330 $53.350 $45.000
REMOVE METAL BEAM GUARD FENCE
LF 1,972.000 $2.250 $2.000 $3.870 $1.000 $1.000 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 20.000 $200.000 $150.000 $180.000 $125.000 $125.000 $500.000
GUARDRAIL END TREATMENT (INSTALL)
EA 20.000 $2,100.000 $2,500.000 $2,113.000 $2,327.000 $2,327.000 $2,850.000
CRASH CUSH ATTEN (DES SOURCE)
EA 4.000 $2,000.000 $2,500.000 $1,760.000 $2,250.000 $2,250.000 $7,000.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 2.000 $2,000.000 $2,500.000 $1,795.000 $2,250.000 $2,250.000 $5,000.000
CRASH CUSH ATTEN (STKPL)
EA 4.000 $900.000 $1,500.000 $678.000 $1,250.000 $1,250.000 $2,500.000
MAILBOX INSTALL-S (TWG-POST) TY 2
EA 33.000 $250.000 $150.000 $190.000 $135.000 $135.000 $650.000
MAILBOX INSTALL-D (TWG-POST) TY 2
EA 5.000 $300.000 $190.000 $195.000 $170.000 $170.000 $650.000
MAILBOX INSTALL-M (TWG-POST) TY 2
EA 1.000 $375.000 $375.000 $463.000 $425.000 $425.000 $650.000
IN SM RD SN SUP&AM TY10BWG(1)SA(U-EXAL)
EA 1.000 $875.000 $800.000 $618.000 $720.000 $720.000 $650.000
IN SM RD SN SUP&AM TYTWT(1)WS(P)
EA 80.000 $300.000 $330.000 $309.000 $318.000 $318.000 $650.000
IN SM RD SN SUP&AM TYTWT(1)WS(T)
EA 1.000 $415.000 $400.000 $335.000 $367.000 $367.000 $650.000
REMOVE SM RD SN SUP&AM
EA 30.000 $100.000 $80.000 $77.000 $75.000 $75.000 $150.000
RELOCATE SM RD SN SUP & AM TY TEMP
EA 47.000 $200.000 $200.000 $180.000 $175.000 $175.000 $500.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 7.000 $21.000 $15.000 $25.000 $12.000 $12.000 $100.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 50.000 $21.000 $16.000 $25.000 $13.500 $15.000 $100.000
WK ZN PAV MRK NON-REMOV (Y)4"(BRK)
LF 5,330.000 $0.190 $0.260 $0.310 $0.300 $0.300 $1.000
WK ZN PAV MRK NON-REMOV (Y)4"(SLD)
LF 27,858.000 $0.200 $0.260 $0.260 $0.250 $0.250 $1.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 3,294.000 $1.000 $1.000 $1.000 $1.000 $1.200 $5.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 124.000 $7.000 $10.000 $12.780 $12.400 $12.400 $10.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 59,044.000 $0.300 $0.360 $0.330 $0.320 $0.320 $0.500
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 5,330.000 $0.300 $0.360 $0.390 $0.380 $0.380 $0.500
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 27,858.000 $0.300 $0.360 $0.370 $0.360 $0.360 $0.500
REFL PAV MRKR TY II-A-A
EA 653.000 $3.500 $4.000 $4.480 $4.350 $4.350 $15.000
Totals: $3,976,979.450 $3,524,688.870 $3,809,954.236 $4,268,055.995 $5,902,596.125 $6,327,951.000