FALLS SH 53 (0232-02-021)

Items: 53

County: FALLS
Length: N/A
Highway: SH 53
District: WACO
Control Number: 0232-02-021
DBE Goal: N/A
Project: BR 1702(471)
Guaranty: N/A
Time: 128 WORKING DAYS
Engineer's Estimate: $2,158,174.70
Date: 07/12/2017 (8 years ago)
Contract Number: N/A
Type: REPL BR & APPRS
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$2,158,174.70
$1,598,158.58
Over/Under Est: -25.95% -$560,016.12
Over/Under Est: -25.38% -$547,733.05
Amt Left: 0.77% $12,283.07
Over/Under Est: -22.26% -$480,380.00
Amt Left: 4.98% $79,636.12
Delta: -4.18% -$67,353.05
Over/Under Est: -9.72% -$209,705.83
Amt Left: 21.92% $350,310.29
Delta: -16.13% -$270,674.17
$1,999,351.60
Over/Under Est: -7.36% -$158,823.10
Amt Left: 25.1% $401,193.02
Delta: -2.61% -$50,882.73
$2,074,740.85
Over/Under Est: -3.87% -$83,433.85
Amt Left: 29.82% $476,582.27
Delta: -3.77% -$75,389.25
Over/Under Est: 34.95% $754,333.90
Amt Left: 82.24% $1,314,350.02
Delta: -40.38% -$837,767.75

Bid Items & Bid Tabulations

53 Total 0 of 53
FALLS  |  SH 53  |  WACO  |  0232-02-021  |  07/12/2017  |  $2,158,174.70  |  BR 1702(471)  |  REPL BR & APPRS  |  128 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
JAMES CONSTRUCTION GROUP, L.L.C.
ELLIS-MCGINNIS CONSTRUCTION CO.
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
J.D. ABRAMS, L.P.
PIERCE R & B LLC
HODGES AND SON CONSTRUCTION COMPANY, INC.
EXCAVATION (ROADWAY)
CY 645.000 $20.000 $16.000 $15.000 $15.000 $25.000 $20.000 $24.000 $20.000
EMBANKMENT (FINAL)(DENS CONT)(TY B)
CY 354.000 $22.000 $17.000 $40.000 $16.000 $25.000 $45.000 $36.000 $20.000
FURNISHING AND PLACING TOPSOIL (4")
SY 11,670.000 $1.500 $0.380 $2.000 $2.000 $1.750 $1.000 $3.000 $4.000
BROADCAST SEED (PERM) (RURAL) (CLAY)
SY 11,670.000 $0.700 $0.330 $0.200 $0.300 $0.210 $0.250 $0.270 $0.500
BROADCAST SEED (TEMP) (WARM)
SY 5,835.000 $0.700 $0.250 $0.180 $0.300 $0.190 $0.180 $0.280 $0.500
BROADCAST SEED (TEMP) (COOL)
SY 5,835.000 $0.700 $0.250 $0.180 $0.300 $0.190 $0.180 $0.280 $0.500
VEGETATIVE WATERING
MG 189.600 $30.000 $5.000 $15.000 $14.000 $53.000 $15.000 $50.000 $1.000
SOIL RETENTION BLANKETS (CL 1) (TY A)
SY 11,670.000 $2.000 $1.250 $1.200 $0.900 $1.300 $1.500 $1.000 $1.000
FL BS (CMP IN PLC)(TYD GR1-2)(FNAL POS)
CY 536.000 $50.000 $50.000 $50.000 $50.000 $90.000 $59.000 $80.000 $100.000
REWORK BS MTL (TY C)(4")(ORD COMP)
SY 2,423.000 $3.000 $1.500 $5.000 $2.000 $10.000 $6.000 $8.000 $8.000
PRIME COAT(MC-30 OR AE-P)
GAL 671.000 $5.000 $5.500 $5.500 $4.500 $6.000 $6.000 $25.000 $8.000
ASPH (CRS-2)
GAL 1,020.000 $5.000 $3.200 $4.500 $3.000 $5.000 $5.000 $4.900 $8.000
AGGR(TY-D GR-4 OR TY-L GR-4)
CY 19.000 $400.000 $255.000 $650.000 $515.000 $700.000 $715.000 $705.000 $800.000
D-GR HMA TY-D SAC-B PG64-22
TON 230.000 $125.000 $90.000 $165.000 $110.000 $130.000 $132.000 $129.000 $150.000
PLANE CONC PAV(0" TO 1-1/2")
SY 668.000 $4.000 $6.250 $8.000 $5.500 $7.000 $10.000 $7.500 $10.000
CEM STABIL BKFL
CY 157.000 $140.000 $115.000 $150.000 $190.000 $130.000 $190.000 $200.000 $250.000
DRILL SHAFT (30 IN)
LF 844.000 $200.000 $110.000 $120.000 $125.000 $110.000 $125.000 $130.000 $120.000
CL C CONC (ABUT)
CY 43.400 $1,000.000 $650.000 $650.000 $730.000 $1,100.000 $1,500.000 $985.000 $1,200.000
CL C CONC (CAP)
CY 55.200 $1,200.000 $885.000 $800.000 $750.000 $1,200.000 $1,500.000 $1,150.000 $1,200.000
CL C CONC (COLUMN)
CY 32.600 $1,000.000 $980.000 $800.000 $710.000 $1,300.000 $1,500.000 $1,125.000 $1,200.000
REINF CONC SLAB (BOX BEAM)
SF 15,874.000 $15.000 $8.750 $8.000 $8.500 $10.000 $11.500 $13.000 $20.000
APPROACH SLAB
CY 64.600 $450.000 $350.000 $400.000 $380.000 $495.000 $520.000 $500.000 $800.000
SHEAR KEY
CY 165.100 $600.000 $125.000 $150.000 $245.000 $220.000 $205.000 $325.000 $800.000
PRESTR CONC BOX BEAM (4B34)
LF 1,117.500 $220.000 $192.000 $180.000 $189.000 $180.000 $210.000 $200.000 $230.000
PRESTR CONC BOX BEAM (5B34)
LF 2,235.000 $220.000 $192.000 $180.000 $189.000 $180.000 $210.000 $188.000 $240.000
RIPRAP (CONC)(CL B)(RR8&RR9)
CY 5.900 $500.000 $500.000 $650.000 $650.000 $540.000 $600.000 $1,000.000 $800.000
RIPRAP (STONE PROTECTION)(24 IN)
CY 770.000 $150.000 $78.000 $70.000 $80.000 $180.000 $110.000 $140.000 $250.000
RIPRAP (MOW STRIP)(4 IN)
CY 35.000 $500.000 $425.000 $500.000 $420.000 $510.000 $535.000 $500.000 $800.000
RAIL (TY T401)
LF 794.000 $115.000 $110.000 $90.000 $105.000 $125.000 $120.000 $125.000 $200.000
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
LF 123.000 $100.000 $70.000 $85.000 $90.000 $130.000 $116.000 $95.000 $120.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $60,000.000 $95,000.000 $50,000.000 $90,000.000 $110,000.000 $70,000.000 $105,000.000 $120,000.000
MOBILIZATION
LS 1.000 $180,000.000 $107,000.000 $154,000.000 $150,000.000 $186,000.000 $174,000.000 $205,000.000 $250,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $3,000.000 $1,000.000 $3,000.000 $1,440.000 $2,500.000 $2,600.000 $3,000.000 $40,000.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 395.000 $35.000 $29.000 $22.500 $28.000 $24.000 $29.000 $27.600 $40.000
ROCK FILTER DAMS (REMOVE)
LF 395.000 $10.000 $10.000 $9.000 $8.000 $9.600 $9.000 $8.750 $20.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 168.000 $20.000 $5.000 $11.500 $11.000 $12.000 $11.500 $20.800 $10.000
CONSTRUCTION EXITS (REMOVE)
SY 168.000 $8.000 $1.000 $9.000 $6.000 $9.600 $9.000 $9.000 $5.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 1,905.000 $3.000 $3.500 $2.250 $1.900 $2.400 $3.000 $2.100 $2.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 1,905.000 $1.000 $0.500 $0.500 $1.000 $0.530 $1.000 $0.600 $1.000
MTL W-BEAM GD FEN (STEEL POST)
LF 200.000 $23.000 $22.000 $22.650 $21.500 $24.000 $25.000 $23.500 $30.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $1,600.000 $1,975.000 $1,584.000 $1,450.000 $1,700.000 $2,000.000 $1,575.000 $2,000.000
REMOVE METAL BEAM GUARD FENCE
LF 500.000 $2.500 $4.000 $5.000 $3.600 $5.300 $2.750 $3.000 $4.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,400.000 $2,200.000 $2,231.000 $2,150.000 $2,400.000 $2,600.000 $2,330.000 $2,500.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $250.000 $400.000 $225.000 $280.000 $240.000 $220.000 $330.000 $500.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 2.000 $500.000 $550.000 $531.000 $375.000 $560.000 $600.000 $565.000 $600.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 12.000 $20.000 $26.000 $12.000 $25.000 $13.000 $13.500 $31.500 $50.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 10.000 $30.000 $37.000 $16.000 $36.000 $17.000 $18.000 $43.000 $50.000
PAVEMENT SEALER 4"
LF 900.000 $0.200 $2.350 $2.250 $2.300 $2.400 $2.300 $1.150 $4.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 1,850.000 $0.500 $1.670 $1.600 $1.600 $1.700 $1.700 $3.250 $4.000
RE PM W/RET REQ TY I (Y)4"(BRK)(100MIL)
LF 240.000 $0.500 $3.130 $3.000 $3.000 $3.200 $3.100 $3.500 $4.000
REFL PAV MRKR TY II-A-A
EA 12.000 $8.000 $24.500 $23.500 $23.500 $25.000 $24.000 $13.000 $10.000
PAV SURF PREP FOR MRK (4")
LF 897.000 $0.100 $0.940 $0.900 $0.900 $0.960 $1.000 $0.600 $1.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 28.000 $100.000 $100.000 $114.000 $60.000 $63.000 $175.000 $125.000 $100.000
Totals: $2,158,174.700 $1,598,158.580 $1,610,441.650 $1,677,794.700 $1,948,468.870 $1,999,351.600 $2,074,740.850 $2,912,508.600