ELLIS FM 2258 (1599-05-011)

Items: 82

County: ELLIS
Length: 2.5960 MILES
Highway: FM 2258
District: DALLAS
Control Number: 1599-05-011
DBE Goal: 0.0%
Project: C 1599-5-11
Guaranty: $100,000.00
Time: 167 WORKING DAYS
Engineer's Estimate: $5,268,123.10
Date: 11/07/2024 (1 year ago)
Contract Number: 11243212
Type: REHABILITATE EXISTING ROADWAY
Project ID: A00064204
Project Description: RESTORE EXISTING PAVEMENT AND ADD SHOULDERS
Mail/Deliver Bids To: N/A
JUAN PAREDES
ELECIA MOORE
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (6)
E
Engineer's Estimate
$5,268,123.10
$5,747,468.58
Over/Under Est: 9.1% $479,345.48
$5,860,136.02
Over/Under Est: 11.24% $592,012.92
Amt Left: 1.96% $112,667.44
Over/Under Est: 13.32% $701,840.52
Amt Left: 3.87% $222,495.04
Delta: -1.87% -$109,827.60
Over/Under Est: 19.43% $1,023,473.85
Amt Left: 9.47% $544,128.37
Delta: -5.39% -$321,633.33
$7,061,427.00
Over/Under Est: 34.04% $1,793,303.90
Amt Left: 22.86% $1,313,958.42
Delta: -12.24% -$769,830.05
$7,926,661.50
Over/Under Est: 50.46% $2,658,538.40
Amt Left: 37.92% $2,179,192.92
Delta: -12.25% -$865,234.50
Subcontractor Percentage Amount
SITE BARRICADES 0.30% $17,816.07
BEAR CREEK CONSTRUCTION, LLC 0.00% $0.00
CEN-TREE SOLUTIONS LLC 0.00% $0.00
A. E. MOORE CONSTRUCTION, INC. 0.00% $0.00
SYNERGY SIGNS & SERVICES LLC 0.00% $0.00
TEXAS TRAFFIC AND BARRICADE, LLC 0.00% $0.00
TRP CONSTRUCTION GROUP, LLC 0.00% $0.00
Total: 0.30% $17,816.07

Bid Items & Bid Tabulations

82 Total 0 of 82
ELLIS  |  FM 2258  |  DALLAS  |  1599-05-011  |  11/07/2024  |  $5,268,123.10  |  C 1599-5-11  |  REHAB EXIST ROADWAY  |  167 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
KNIFE RIVER CORPORATION - SOUTH
A. L. HELMCAMP, INC.
ED BELL CONSTRUCTION COMPANY
BIG CREEK CONSTRUCTION, LTD.
FNH CONSTRUCTION, LLC
CK NEWBERRY, LLC
PREPARING ROW
STA 135.900 $1,200.000 $1,000.000 $750.000 $1,050.000 $2,675.000 $5,000.000 $745.000
REMOV CONC (DRIVEWAYS)
SY 310.000 $25.000 $24.000 $71.000 $31.500 $28.000 $20.000 $25.000
RMV (2"-6") TRT/UNTRT BASE & ASPH PAV
SY 4,675.000 $10.000 $4.500 $10.000 $10.000 $6.000 $20.000 $15.000
EXCAV (ROADWAY)
CY 222.000 $20.000 $50.000 $50.000 $20.000 $30.000 $30.000 $50.000
SUBGR WIDEN (OC)
STA 135.500 $425.000 $500.000 $350.000 $650.000 $2,500.000 $850.000 $675.000
EMBANK (FNL)(OC)(TY C)
CY 10,088.000 $22.000 $36.000 $60.000 $31.500 $38.000 $40.000 $65.000
BACKFILL (TY A OR B)
STA 135.500 $300.000 $250.000 $160.000 $650.000 $350.000 $450.000 $315.000
COMPOST MANUF TOPSOIL (4")
SY 53,738.000 $1.350 $1.050 $1.700 $0.970 $1.350 $3.000 $1.000
BLOCK SODDING
SY 535.000 $10.000 $11.000 $7.000 $10.000 $9.000 $10.000 $10.000
DRILL SEED (PERM_RURAL_CLAY)
SY 53,203.000 $0.200 $0.280 $0.400 $0.240 $0.400 $1.000 $1.000
DRILL SEED (TEMP_WARM_COOL)
SY 53,203.000 $0.200 $0.230 $0.390 $0.100 $0.400 $1.000 $1.000
VEGETATIVE WATERING
TGL 15,913.000 $8.000 $0.100 $0.700 $1.000 $1.000 $20.000 $10.000
FL BS (CMP IN PLC)(TY D GR 1-2) (12")
SY 44,158.000 $28.000 $31.000 $30.000 $32.000 $36.000 $25.000 $35.000
FL BS (RDWY DEL) (TY D GR 1-2)
TON 1,932.000 $39.000 $47.000 $47.000 $28.000 $50.000 $60.000 $80.000
REWORK BS MTL (TY B)(6")(ORD COMP)
SY 1,780.000 $2.300 $6.000 $8.000 $15.000 $14.000 $4.000 $30.000
REWORK BS MTL (TY C)(6")(ORD COMP)
SY 30,003.000 $3.150 $3.000 $2.000 $5.000 $4.000 $4.000 $5.000
CEMENT
TON 236.000 $335.000 $245.000 $240.000 $236.000 $225.000 $350.000 $300.000
CEMENT TRT (EXIST MATL & NEW BASE)(6")
SY 46,420.000 $2.900 $3.000 $2.500 $3.000 $4.000 $8.000 $2.750
PRIME COAT(MC-30 OR AE-P)
GAL 12,796.000 $5.200 $4.500 $4.500 $6.300 $5.500 $6.000 $6.000
ASPH (CRS-2P)
GAL 10,665.000 $5.150 $4.400 $4.500 $4.460 $6.000 $6.000 $5.000
ASPH (AC-15P, AC-20-5TR OR AC-20XP)
GAL 8,957.000 $4.500 $4.400 $4.500 $5.670 $6.000 $6.000 $5.000
AGGR (TY-B, GR-3)(SAC-B)
CY 406.000 $220.000 $200.000 $200.000 $275.000 $130.000 $300.000 $215.000
SP MIXES SP-C SAC-B PG64-22
TON 4,641.000 $138.000 $130.000 $140.000 $150.000 $150.000 $165.000 $195.000
PLANE ASPH CONC PAV(5")
SY 30,113.000 $2.750 $3.850 $5.000 $2.000 $3.000 $6.000 $5.000
CUT & RESTORE ASPH PAVING
SY 231.000 $200.000 $1,125.000 $450.000 $855.000 $250.000 $200.000 $350.000
TRENCH EXCAVATION PROTECTION
LF 286.000 $12.000 $16.000 $13.800 $7.500 $30.000 $10.000 $40.000
RIPRAP (MOW STRIP)(4 IN)
CY 30.000 $750.000 $725.000 $1,035.000 $750.000 $850.000 $550.000 $650.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 26.000 $190.000 $380.000 $345.000 $525.000 $240.000 $185.000 $400.000
RC PIPE (CL III)(18 IN)
LF 1,328.000 $95.000 $110.000 $75.000 $75.000 $120.000 $95.000 $150.000
RC PIPE (CL III)(24 IN)
LF 184.000 $105.000 $158.000 $167.000 $105.000 $190.000 $150.000 $200.000
RC PIPE (CL III)(36 IN)
LF 78.000 $145.000 $238.000 $289.000 $275.000 $235.000 $200.000 $225.000
RC PIPE (CL III)(48 IN)
LF 368.000 $310.000 $330.000 $375.000 $300.000 $245.000 $350.000 $305.000
HEADWALL (CH - PW - 0) (DIA= 36 IN)
EA 2.000 $11,000.000 $14,000.000 $12,650.000 $15,000.000 $9,500.000 $3,850.000 $25,000.000
HEADWALL (CH - PW - 0) (DIA= 48 IN)
EA 6.000 $15,750.000 $15,000.000 $17,250.000 $21,000.000 $14,200.000 $8,500.000 $30,000.000
SET (TY II) (18 IN) (RCP) (4: 1) (C)
EA 6.000 $1,200.000 $1,485.000 $1,035.000 $630.000 $1,200.000 $1,850.000 $4,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 84.000 $1,300.000 $1,750.000 $1,150.000 $735.000 $1,325.000 $1,500.000 $2,500.000
SET (TY II) (24 IN) (RCP) (4: 1) (C)
EA 4.000 $1,300.000 $1,775.000 $2,300.000 $945.000 $1,850.000 $2,500.000 $3,500.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 4.000 $1,400.000 $2,000.000 $2,875.000 $1,155.000 $2,000.000 $2,500.000 $4,000.000
REMOV STR (SET)
EA 12.000 $200.000 $1,900.000 $920.000 $525.000 $425.000 $500.000 $1,200.000
REMOV STR (WINGWALL)
EA 2.000 $2,000.000 $1,900.000 $2,300.000 $7,000.000 $2,500.000 $2,500.000 $2,500.000
REMOV STR (PIPE)
LF 2,063.000 $22.000 $15.000 $46.000 $31.500 $10.000 $30.000 $40.000
REMOV STR (BOX CULVERT)
LF 120.000 $150.000 $110.000 $403.000 $168.000 $40.000 $150.000 $200.000
MOBILIZATION
LS 1.000 $466,600.000 $570,000.000 $475,000.000 $589,000.000 $600,000.000 $700,000.000 $750,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 11.000 $10,000.000 $16,000.000 $18,000.000 $31,500.000 $3,000.000 $8,500.000 $50,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $12,500.000 $28,000.000 $18,000.000 $7,500.000 $10,000.000 $16,500.000 $15,000.000
TMA (STATIONARY)
DAY 162.000 $200.000 $100.000 $100.000 $157.500 $125.000 $250.000 $400.000
TMA (MOBILE OPERATION)
HR 128.000 $70.000 $50.000 $70.000 $85.000 $88.000 $55.000 $100.000
ROCK FILTER DAMS (INSTALL) (TY 2)
LF 60.000 $70.000 $90.000 $39.000 $78.750 $70.000 $30.000 $40.000
ROCK FILTER DAMS (INSTALL) (TY 3)
LF 40.000 $80.000 $140.000 $69.000 $89.250 $110.000 $30.000 $70.000
ROCK FILTER DAMS (REMOVE)
LF 100.000 $15.000 $22.000 $19.000 $47.250 $20.000 $15.000 $20.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 247.000 $30.000 $25.000 $10.000 $29.400 $35.000 $40.000 $40.000
CONSTRUCTION EXITS (REMOVE)
SY 247.000 $10.000 $10.000 $5.000 $15.750 $13.000 $20.000 $15.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 11,187.000 $4.000 $6.000 $3.250 $2.890 $4.000 $4.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 11,187.000 $1.250 $1.100 $1.000 $1.310 $1.250 $2.000 $2.000
DRIVEWAYS (CONC)
SY 268.000 $125.000 $215.000 $145.000 $135.000 $145.000 $125.000 $155.000
DRIVEWAYS (ACP)
SY 3,749.000 $90.000 $63.000 $95.000 $63.000 $45.000 $45.000 $75.000
MILL RUMBLE STRIPS (ASPHALT) (SHLDR)
LF 27,100.000 $0.250 $0.300 $0.140 $0.420 $0.150 $0.500 $0.500
MILL RUMBLE STRIPS (ASPH) (CENTERLINE)
LF 13,550.000 $0.250 $0.300 $0.200 $0.210 $0.600 $0.500 $0.500
MTL W-BEAM GD FEN (TIM POST)
LF 425.000 $25.000 $28.000 $26.000 $23.630 $30.000 $32.000 $60.000
REMOVE METAL BEAM GUARD FENCE
LF 100.000 $4.750 $5.750 $3.500 $3.150 $7.000 $5.000 $12.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $2,800.000 $3,500.000 $2,274.000 $2,076.380 $3,500.000 $3,850.000 $3,000.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $245.000 $300.000 $287.000 $262.500 $400.000 $1,500.000 $1,200.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 16.000 $350.000 $315.000 $448.000 $409.500 $330.000 $850.000 $350.000
MAILBOX INSTALL-D (TWW-POST) TY 4
EA 4.000 $400.000 $325.000 $563.000 $514.500 $525.000 $850.000 $375.000
MAILBOX INSTALL-M (TWW-POST) TY 4
EA 3.000 $725.000 $900.000 $822.000 $750.750 $850.000 $850.000 $825.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 13.000 $800.000 $750.000 $862.000 $787.500 $750.000 $1,500.000 $875.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P-BM)
EA 1.000 $850.000 $800.000 $891.000 $813.750 $1,100.000 $1,500.000 $1,000.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 2.000 $850.000 $850.000 $1,035.000 $945.000 $850.000 $1,500.000 $1,000.000
IN SM RD SN SUP&AM TYS80(1)SA(U-BM)
EA 1.000 $900.000 $1,400.000 $1,265.000 $1,155.000 $1,700.000 $1,500.000 $1,500.000
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 6.000 $28.000 $35.000 $29.000 $26.250 $30.000 $100.000 $35.000
INSTL OM ASSM (OM-2Z)(WFLX)GND
EA 3.000 $85.000 $85.000 $52.000 $47.250 $65.000 $100.000 $110.000
WK ZN PAV MRK NON-REMOV (Y)6"(BRK)
LF 890.000 $0.750 $0.470 $0.470 $1.050 $2.500 $3.000 $3.000
WK ZN PAV MRK NON-REMOV (Y)6"(SLD)
LF 23,420.000 $0.860 $0.470 $0.470 $0.580 $2.500 $1.000 $3.000
WK ZN PAV MRK SHT TERM (TAB)TY Y
EA 1,445.000 $1.600 $1.500 $0.770 $4.200 $2.500 $6.000 $2.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 18.000 $10.000 $9.000 $35.000 $23.100 $17.000 $20.000 $20.000
PAVEMENT SLER 6"
LF 640.000 $0.750 $0.210 $0.210 $1.050 $1.250 $3.000 $2.000
REFL PAV MRK TY I (W)6"(SLD)(100MIL)
LF 27,200.000 $1.150 $0.750 $0.760 $0.840 $1.750 $1.000 $2.000
REFL PAV MRK TY I (Y)6"(BRK)(100MIL)
LF 890.000 $1.100 $0.850 $0.850 $1.050 $1.750 $3.000 $2.000
REFL PAV MRK TY I (Y)6"(SLD)(100MIL)
LF 23,420.000 $1.100 $0.750 $0.760 $0.840 $1.750 $1.000 $2.000
REFL PAV MRKR TY II-A-A
EA 337.000 $5.500 $5.500 $5.750 $8.140 $7.000 $6.000 $7.000
PAV SURF PREP FOR MRK (6")
LF 640.000 $0.750 $0.230 $0.230 $1.050 $1.200 $3.000 $2.000
FULL - WIDTH MOWING
CYC 2.000 $3,500.000 $3,000.000 $9,000.000 $7,500.000 $4,800.000 $3,500.000 $1,100.000
Totals: $5,268,123.100 $5,747,468.580 $5,860,136.020 $5,969,963.620 $6,291,596.950 $7,061,427.000 $7,926,661.500