Show Job Controls
Bid Cobra

ELLIS SH 34 (0568-01-059)

Items: 38

County: ELLIS
Length: N/A
Highway: SH 34
District: DALLAS
Control Number: 0568-01-059
DBE Goal: N/A
Project: BR 2022(639)
Guaranty: N/A
Time: 157 WORKING DAYS
Engineer's Estimate: $3,626,510.70
Date: 06/02/2022 (4 years ago)
Contract Number: N/A
Type: BRIDGE MAINTENANCE
Mail/Deliver Bids To: N/A
JUAN PAREDES
AMANDA MCKITTRICK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (5)
E
Engineer's Estimate
$3,626,510.70
$3,311,895.00
Over/Under Est: -8.68% -$314,615.70
Over/Under Est: -0.84% -$30,318.70
Amt Left: 8.58% $284,297.00
Over/Under Est: 11% $398,884.70
Amt Left: 21.54% $713,500.40
Delta: -11.93% -$429,203.40
Over/Under Est: 19.96% $723,939.25
Amt Left: 31.36% $1,038,554.95
Delta: -8.08% -$325,054.55
$4,391,733.54
Over/Under Est: 21.1% $765,222.84
Amt Left: 32.6% $1,079,838.54
Delta: -0.95% -$41,283.59
Subcontractor Percentage Amount
MOBILE ENTERPRISES, INC. 21.92% $751,644.11
ODUM SERVICES, LLC 1.90% $65,151.63
AREA WIDE PROTECTIVE, INC. 1.11% $38,062.27
TOTAL HIGHWAY MAINTENANCE, LLC 0.97% $33,261.62
TEXAS SWPPP SERVICES 0.17% $5,829.36
Total: 26.07% $893,948.99

Bid Items & Bid Tabulations

38 Total 0 of 38
ELLIS  |  SH 34  |  DALLAS  |  0568-01-059  |  06/02/2022  |  $3,626,510.70  |  BR 2022(639)  |  BRIDGE MAINT  |  157 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
WESSON CONSTRUCTION SERVICES, LLC
BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC
GIBSON & ASSOCIATES, INC.
OLYMPUS PAINTING CONTRACTORS, INC.
ALTUS CONSTRUCTION LLC
REMOVING CONC (CURB)
LF 80.000 $6.500 $13.000 $25.000 $25.300 $50.000 $23.810
REMOVING CONCRETE(MOW STRIP)
LF 1,720.000 $3.750 $5.000 $4.000 $16.500 $14.000 $7.180
APPROACH SLAB (HPC)
CY 48.200 $900.000 $500.000 $750.000 $1,540.000 $850.000 $474.500
PENETRATING CONCRETE SURFACE TREATMENT
SY 17,471.000 $8.500 $6.000 $6.000 $6.500 $14.750 $13.210
CONC STR REPAIR(DECK REP(PART DEPTH))
SF 165.000 $250.000 $130.000 $130.000 $100.000 $150.000 $182.860
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 1,876.000 $230.000 $230.000 $210.000 $310.000 $264.000 $488.120
RIPRAP (MOW STRIP)(4 IN)
CY 106.300 $650.000 $300.000 $700.000 $935.000 $575.000 $372.550
CLEANING AND SEALING EXIST JOINTS(CL7)
LF 3,960.000 $40.000 $55.000 $50.000 $62.000 $60.000 $58.340
RETROFIT RAIL (TY T131RC)
LF 10,510.000 $225.000 $178.000 $215.000 $220.000 $243.000 $188.810
REMOV STR (APPROACH SLAB)
EA 2.000 $17,168.000 $5,000.000 $2,500.000 $9,130.000 $12,000.000 $2,095.300
MOBILIZATION
LS 1.000 $1.000 $250,000.000 $180,000.000 $119,000.000 $225,000.000 $428,584.160
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 10.000 $10,000.000 $1,500.000 $1,000.000 $11,500.000 $8,000.000 $22,403.050
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 115.000 $15.000 $30.000 $25.000 $41.640 $75.000 $17.860
CONSTRUCTION EXITS (REMOVE)
SY 115.000 $5.000 $15.000 $10.000 $22.000 $30.000 $11.910
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 200.000 $4.000 $5.000 $7.000 $6.880 $15.000 $7.140
BIODEG EROSN CONT LOGS (REMOVE)
LF 200.000 $1.000 $3.000 $3.000 $2.480 $10.000 $4.760
PORT CTB (FUR & INST)(F-SHAPE)(TY 1)
LF 480.000 $30.000 $70.000 $80.000 $41.000 $85.000 $81.100
PORT CTB (REMOVE)(F-SHAPE)(TY 1)
LF 480.000 $10.000 $40.000 $15.000 $29.000 $30.000 $22.620
CONC CURB (TY II)
LF 80.000 $35.000 $35.000 $35.000 $27.500 $125.000 $75.430
MTL W-BEAM GD FEN (TIM POST)
LF 1,440.000 $35.000 $30.000 $30.000 $26.400 $30.600 $25.680
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 4.000 $2,200.000 $2,000.000 $2,200.000 $2,090.000 $1,980.000 $3,518.110
REMOVE METAL BEAM GUARD FENCE
LF 1,440.000 $2.200 $5.000 $6.000 $3.300 $2.400 $3.850
REMOVE TERMINAL ANCHOR SECTION
EA 4.000 $200.000 $200.000 $400.000 $165.000 $300.000 $227.760
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $3,500.000 $4,000.000 $4,000.000 $3,190.000 $3,660.000 $3,757.900
CRASH CUSH ATTEN (REMOVE)
EA 4.000 $650.000 $6,000.000 $1,500.000 $935.000 $1,500.000 $1,190.510
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $7,500.000 $9,000.000 $9,000.000 $8,800.000 $8,500.000 $3,334.480
INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)
EA 332.000 $28.000 $30.000 $30.000 $27.500 $35.000 $27.700
PAVEMENT SEALER 4"
LF 20,960.000 $0.300 $0.300 $0.250 $0.280 $0.240 $0.300
REF PROF PAV MRK TY I(W)4"(SLD)(100MIL)
LF 10,480.000 $0.600 $1.000 $0.850 $0.770 $0.900 $0.830
REF PROF PAV MRK TY I(Y)4"(SLD)(100MIL)
LF 10,480.000 $0.600 $1.000 $0.850 $0.770 $0.900 $0.830
REFL PAV MRKR TY II-A-A
EA 132.000 $4.000 $7.000 $6.000 $6.600 $6.300 $7.140
ELIM EXT PAV MRK & MRKS (4")
LF 20,960.000 $0.450 $0.600 $0.550 $0.550 $0.520 $0.600
PAV SURF PREP FOR MRK (4")
LF 20,960.000 $0.070 $0.100 $0.250 $0.110 $0.600 $0.120
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 2.500 $100.000 $140.000 $50.000 $500.000 $200.000 $160.720
CARBON FIBER REINF POLYMER PROTECTION
SF 320.000 $100.000 $125.000 $185.000 $94.000 $138.000 $136.910
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $6,000.000 $3,500.000 $150.000 $15,500.000 $6,000.000 $3,571.530
TMA (STATIONARY)
DAY 80.000 $88.000 $160.000 $200.000 $500.000 $75.000 $142.860
TMA (MOBILE OPERATION)
DAY 12.000 $200.000 $1,200.000 $250.000 $260.000 $500.000 $178.580
Totals: $3,626,510.700 $3,311,895.000 $3,596,192.000 $4,025,395.400 $4,350,449.950 $4,391,733.545