ELLIS SH 34 (0568-01-052)

Items: 76

County: ELLIS
Length: N/A
Highway: SH 34
District: DALLAS
Control Number: 0568-01-052
DBE Goal: 500.0%
Project: F 2B24(160)
Guaranty: N/A
Time: 276 WORKING DAYS
Engineer's Estimate: $12,752,088.91
Date: 06/06/2024 (2 years ago)
Contract Number: N/A
Type: REPAIR ROADWAY
Mail/Deliver Bids To: N/A
JUAN PAREDES
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Bidders (3)
E
Engineer's Estimate
$12,752,088.91
$12,687,858.40
Over/Under Est: -0.5% -$64,230.51
Over/Under Est: 18.15% $2,314,517.92
Amt Left: 18.75% $2,378,748.43
$16,253,870.50
Over/Under Est: 27.46% $3,501,781.59
Amt Left: 28.11% $3,566,012.10
Delta: -7.88% -$1,187,263.67
Subcontractor Percentage Amount
WEST TEXAS RUMBLE STRIP LLC 0.24% $30,450.86
NEXT CONSTRUCTION SOLUTIONS LLC 0.01% $1,268.79
JE CASEY, LLC 0.00% $0.00
DALLAS LITE AND BARRICADE, INC. 0.00% $0.00
SYNERGY SIGNS & SERVICES LLC 0.00% $0.00
TRAFFIC HIGHWAY MAINTENANCE, LLC 0.00% $0.00
USA SWPPP INSPECTIONS, INC.DBA USA EROSION 0.00% $0.00
PROFESSIONAL TRAFFIC CONTROL LLC 0.00% $0.00
J & M CONTRACTING, COMPANY 0.00% $0.00
Total: 0.25% $31,719.65

Bid Items & Bid Tabulations

76 Total 0 of 76
ELLIS  |  SH 34  |  DALLAS  |  0568-01-052  |  06/06/2024  |  $12,752,088.91  |  F 2B24(160)  |  REPAIR ROADWAY  |  276 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
BIG CREEK CONSTRUCTION, LTD.
TEXAS MATERIALS GROUP, INC.
FNH CONSTRUCTION, LLC
REMOVING CONC (MEDIANS)
SY 40.000 $55.000 $50.000 $58.000 $20.000
REMOVING CONC (DRIVEWAYS)
SY 193.000 $15.500 $25.000 $66.000 $20.000
REMOVING STAB BASE AND ASPH PAV (2"-8")
SY 51.000 $12.500 $50.000 $12.000 $20.000
REMOVING STAB BASE & ASPH PAV (12"-14")
SY 11,451.000 $10.000 $15.000 $12.900 $20.000
EXCAVATION (ROADWAY)
CY 1,459.000 $25.000 $32.000 $41.000 $20.000
EMBANKMENT (FINAL)(ORD COMP)(TY C)
CY 974.000 $35.000 $32.000 $61.000 $35.000
BACKFILL (TY A OR B)
STA 966.050 $160.000 $250.000 $200.000 $250.000
ROAD GRADER WORK (ORD COMP)
STA 74.150 $275.000 $250.000 $1,300.000 $250.000
BLOCK SODDING
SY 7,149.000 $4.250 $7.000 $6.500 $10.000
DRILL SEED (TEMP)(WARM OR COOL)
SY 7,149.000 $0.300 $1.000 $0.250 $1.000
VEGETATIVE WATERING
MG 2,136.000 $10.000 $35.000 $15.000 $20.000
LIME (HYDRATED LIME (SLURRY))
TON 270.000 $310.000 $350.000 $245.000 $350.000
LIME TRT (SUBGRADE)(6")
SY 18,805.000 $5.000 $7.500 $6.500 $8.000
PRIME COAT(MC-30 OR AE-P)
GAL 3,764.000 $8.000 $7.000 $5.000 $6.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(6")
SY 117.000 $65.000 $70.000 $130.000 $75.000
FLEXIBLE PAVEMENT STRUCTURE REPAIR(12")
SY 2,835.000 $105.000 $120.000 $135.000 $120.000
PLAN & TEXT ASPH CONC PAV(0" TO 2")
SY 451,156.000 $2.000 $2.000 $2.000 $3.000
PLAN & TEXT ASPH CONC PAV(0" TO 4")
SY 29,817.000 $2.500 $4.000 $3.000 $5.000
CUT & RESTORE ASPH PAVING
SY 41.000 $110.000 $275.000 $200.000 $200.000
RIPRAP (MOW STRIP)(4 IN)
CY 350.300 $550.000 $1,250.000 $750.000 $500.000
RC PIPE (CL III)(12 IN)
LF 256.000 $80.000 $70.000 $88.934 $65.000
RC PIPE (CL III)(18 IN)
LF 80.000 $110.000 $75.000 $124.739 $85.000
SET (TY II) (12 IN) (RCP) (6: 1) (P)
EA 8.000 $1,000.000 $1,100.000 $1,385.989 $1,000.000
SET (TY II) (18 IN) (RCP) (6: 1) (P)
EA 14.000 $1,250.000 $1,400.000 $2,148.284 $1,000.000
REMOV STR (PIPE)
LF 229.000 $25.750 $65.000 $17.325 $50.000
MOBILIZATION
LS 1.000 $1,159,280.810 $1,200,000.000 $979,000.000 $1,600,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 17.000 $10,000.000 $3,450.000 $9,000.000 $8,500.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 234.000 $33.000 $35.000 $30.000 $45.000
CONSTRUCTION EXITS (REMOVE)
SY 234.000 $11.500 $15.000 $12.000 $20.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 4,404.000 $3.000 $4.000 $4.000 $4.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 4,404.000 $0.750 $1.500 $0.500 $2.000
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 11.000 $5.500 $15.000 $8.000 $18.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 11.000 $1.250 $6.000 $1.000 $9.000
DRIVEWAYS (ACP)
SY 97.000 $58.000 $60.000 $225.000 $45.000
DRIVEWAYS (CONC) (HES)
SY 133.000 $140.000 $250.000 $250.000 $125.000
RUMBLE STRIPS (SHOULDER) ASPHALT
LF 144,350.000 $0.350 $0.200 $0.110 $0.250
RUMBLE STRIPS (CENTERLINE) ASPHALT
LF 70,414.000 $0.350 $0.200 $0.100 $0.250
MTL W-BEAM GD FEN (TIM POST)
LF 4,000.000 $25.750 $35.000 $25.000 $26.000
GUARDRAIL END TREATMENT (INSTALL)
EA 32.000 $3,000.000 $3,000.000 $3,600.000 $3,250.000
MAILBOX INSTALL-S (TWW-POST) TY 4
EA 4.000 $400.000 $350.000 $300.000 $1,150.000
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 17.000 $750.000 $750.000 $700.000 $1,500.000
RELOCATE SM RD SN SUP&AM TY 10BWG
EA 34.000 $625.000 $600.000 $600.000 $1,000.000
RELOCATE SM RD SN SUP&AM TY S80
EA 21.000 $700.000 $700.000 $750.000 $1,000.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB (BI)
EA 190.000 $20.000 $50.000 $20.000 $100.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1 (BI)
EA 105.000 $23.000 $25.000 $20.000 $100.000
WK ZN PAV MRK SHT TERM (TAB)TY W
EA 847.000 $1.000 $1.500 $0.750 $6.000
WK ZN PAV MRK SHT TERM (TAB)TY Y-2
EA 15,797.000 $1.000 $1.500 $0.750 $6.000
REFL PAV MRK TY I (W)8"(DOT)(100MIL)
LF 276.000 $4.000 $3.000 $1.000 $2.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 7,248.000 $1.450 $1.500 $0.800 $2.000
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 1,067.000 $8.750 $12.000 $6.250 $10.000
REFL PAV MRK TY I (W)(ARROW)(100MIL)
EA 87.000 $190.000 $250.000 $140.000 $250.000
REFL PAV MRK TY I (W)(WORD)(100MIL)
EA 41.000 $200.000 $350.000 $150.000 $250.000
REFL PAV MRK TY I (W)(RR XING)(100MIL)
EA 4.000 $500.000 $1,000.000 $350.000 $500.000
RE PM TY II(ACC PRK)(WHT)(SYMBOL ONLY)
EA 9.000 $500.000 $750.000 $75.000 $250.000
PAVEMENT SEALER 6"
LF 20,815.000 $0.350 $0.400 $0.350 $0.500
PAVEMENT SEALER 24"
LF 118.000 $2.500 $3.500 $2.000 $5.000
PAVEMENT SEALER (RR XING)
EA 2.000 $150.000 $300.000 $125.000 $150.000
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 2,842.000 $0.600 $0.600 $0.800 $1.000
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 320.000 $0.600 $1.100 $0.650 $1.000
RE PM W/RET REQ TY I (W)6"(SLD)(100MIL)
LF 216,048.000 $0.600 $0.700 $0.580 $1.000
RE PM W/RET REQ TY I (Y)6"(BRK)(100MIL)
LF 16,900.000 $0.600 $0.900 $0.620 $1.000
RE PM W/RET REQ TY I (Y)6"(SLD)(100MIL)
LF 148,159.000 $0.600 $0.700 $0.580 $1.000
REFL PAV MRKR TY I-C
EA 398.000 $3.750 $6.000 $3.900 $6.000
REFL PAV MRKR TY II-A-A
EA 4,180.000 $4.500 $6.000 $3.800 $6.000
ELIM EXT PAV MRK & MRKS (4")
LF 20,815.000 $0.500 $0.700 $0.600 $1.000
ELIM EXT PAV MRK & MRKS (24")
LF 118.000 $3.000 $7.000 $5.000 $5.000
ELIM EXT PAV MRK & MRKS (RR XING)
EA 2.000 $275.000 $300.000 $150.000 $250.000
PAV SURF PREP FOR MRK (6")
LF 20,815.000 $0.250 $0.100 $0.400 $0.500
PAV SURF PREP FOR MRK (24")
LF 118.000 $1.000 $3.000 $0.500 $1.250
PAV SURF PREP FOR MRK (RR XING)
EA 2.000 $45.000 $75.000 $40.000 $100.000
SP MIXES SP-B PG64-22
TON 11,735.000 $120.000 $110.000 $148.000 $135.000
SP MIXES SP-C SAC-B PG70-22
TON 54,936.000 $123.000 $112.000 $149.000 $155.000
TACK COAT
GAL 52,729.000 $3.750 $4.000 $4.000 $4.000
PORTABLE CHANGEABLE MESSAGE SIGN
EA 2.000 $10,000.000 $12,000.000 $17,000.000 $16,500.000
TMA (STATIONARY)
DAY 191.000 $600.000 $400.000 $2,100.000 $250.000
TMA (MOBILE OPERATION)
HR 418.000 $75.000 $85.000 $175.000 $55.000
Totals: $12,752,088.910 $12,687,858.400 $15,066,606.847 $16,253,870.500