ELLIS US 287 (0172-08-106)
Items: 45
County: ELLIS
Length: 1.0100 MILES
Highway: US 287
District: DALLAS
Control Number: 0172-08-106
DBE Goal: 2.0%
Project: STP 2025(973)HES
Guaranty: $20,000.00
Time: 36 WORKING DAYS
Engineer's Estimate: $1,051,194.54
Date: 08/07/2025 (10 months ago)
Contract Number: 8253020
Type: INTERSECTION IMPROVEMENT
Project ID: A00206753
Contract Type: Federal
Project Description: INSTALL MEDIAN BARRIER CLOSE CROSSOVER
Mail/Deliver Bids To:
TEXAS DEPARTMENT OF TRANSPORTATION
ATTN: CONSTRUCTION DIVISION - RM M1C3.02
6230 E STASSNEY LN, AUSTIN, TX 78744
JUAN PAREDES
ELECIA MOORE
ELLIS US 287 (0172-08-106)
Project Name: N/A
Project: STP 2025(973)HES
Length: 1.0100 MILES
Project Type: CONSTRUCTION
Limits From: OFF-RAMP TO US 287 BUS EB
Limits To: US 287 BUS WB
Project Description: INSTALL MEDIAN BARRIER CLOSE CROSSOVER
Bidders (5)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,051,194.54 | |||
| $1,120,428.93 |
6.59%
$69,234.39
|
|||
| $1,229,090.72 |
16.92%
$177,896.18
|
9.7%
$108,661.79
|
||
| $1,261,207.50 |
19.98%
$210,012.96
|
12.56%
$140,778.57
|
-2.61%
-$32,116.78
|
|
| $1,361,955.72 |
29.56%
$310,761.18
|
21.56%
$241,526.79
|
-7.99%
-$100,748.22
|
|
| $1,493,751.08 |
42.1%
$442,556.54
|
33.32%
$373,322.15
|
-9.68%
-$131,795.36
|
E
Engineer's Estimate
$1,051,194.54
1
Awarded
$1,120,428.93
Over/Under Est:
6.59%
$69,234.39
$1,229,090.72
Over/Under Est:
16.92%
$177,896.18
Amt Left:
9.7%
$108,661.79
$1,261,207.50
Over/Under Est:
19.98%
$210,012.96
Amt Left:
12.56%
$140,778.57
Delta:
-2.61%
-$32,116.78
$1,361,955.72
Over/Under Est:
29.56%
$310,761.18
Amt Left:
21.56%
$241,526.79
Delta:
-7.99%
-$100,748.22
$1,493,751.08
Over/Under Est:
42.1%
$442,556.54
Amt Left:
33.32%
$373,322.15
Delta:
-9.68%
-$131,795.36
| Subcontractor | Percentage | Amount |
|---|---|---|
| FORTSON CONTRACTING, INC. | 2.87% | $32,156.31 |
| USA SWPPP INSPECTIONS, INC.DBA USA EROSION | 2.42% | $27,114.38 |
| TRP CONSTRUCTION GROUP, LLC | 1.11% | $12,436.76 |
| TRAFFIC HIGHWAY MAINTENANCE, LLC | 0.57% | $6,386.44 |
| Total: | 6.97% | $78,093.89 |
Bid Items & Bid Tabulations
45
Total
0 of 45
INCLUDES FORCE ACCOUNT WORK AMOUNTS AS FOLLOWS:
| Description | Amount |
|---|---|
| LAW ENFORCEMENT: CONTRACTOR FORCE ACCOUNT WORK (PART) | $25,000.00 |