ELLIS BI 45G (0092-08-021)
Items: 41
County: ELLIS
Length: 0.0000 MILES
Highway: BI 45G
District: DALLAS
Control Number: 0092-08-021
DBE Goal: 0.0%
Project: STP 2026(226)VRU
Guaranty: $31,000.00
Time: 48 WORKING DAYS
Engineer's Estimate: $1,534,028.60
Date: 01/06/2026 (5 months ago)
Contract Number: 1263026
Type: INSTALL RAISED MEDIAN
Project ID: A00193947
Contract Type: Federal
Project Description: INSTALL RAISED MEDIAN
Mail/Deliver Bids To: N/A
JUAN PAREDES
NOLAN DELHIERRO
ELLIS BI 45G (0092-08-021)
Project Name: N/A
Project: STP 2026(226)VRU
Length: 0.0000 MILES
Project Type: CONSTRUCTION
Limits From: SS 469
Limits To: SH 34
Project Description: INSTALL RAISED MEDIAN
Bidders (9)
| Bidder | Total Amount | Over/Under Est | Amt Left From Low Bid | Delta Between Bidders |
|---|---|---|---|---|
|
E
Engineer's Estimate
|
$1,534,028.60 | |||
| $1,134,486.04 |
-26.05%
-$399,542.56
|
|||
| $1,187,000.00 |
-22.62%
-$347,028.60
|
4.63%
$52,513.96
|
||
| $1,226,264.60 |
-20.06%
-$307,764.00
|
8.09%
$91,778.56
|
-3.31%
-$39,264.60
|
|
| $1,244,413.33 |
-18.88%
-$289,615.27
|
9.69%
$109,927.29
|
-1.48%
-$18,148.73
|
|
| $1,282,830.15 |
-16.38%
-$251,198.45
|
13.08%
$148,344.11
|
-3.09%
-$38,416.82
|
|
| $1,308,027.60 |
-14.73%
-$226,001.00
|
15.3%
$173,541.56
|
-1.96%
-$25,197.45
|
|
| $1,446,457.14 |
-5.71%
-$87,571.46
|
27.5%
$311,971.10
|
-10.58%
-$138,429.54
|
|
| $1,624,574.50 |
5.9%
$90,545.90
|
43.2%
$490,088.46
|
-12.31%
-$178,117.36
|
|
| $1,845,088.50 |
20.28%
$311,059.90
|
62.64%
$710,602.46
|
-13.57%
-$220,514.00
|
E
Engineer's Estimate
$1,534,028.60
1
Awarded
$1,134,486.04
Over/Under Est:
-26.05%
-$399,542.56
$1,187,000.00
Over/Under Est:
-22.62%
-$347,028.60
Amt Left:
4.63%
$52,513.96
$1,226,264.60
Over/Under Est:
-20.06%
-$307,764.00
Amt Left:
8.09%
$91,778.56
Delta:
-3.31%
-$39,264.60
$1,244,413.33
Over/Under Est:
-18.88%
-$289,615.27
Amt Left:
9.69%
$109,927.29
Delta:
-1.48%
-$18,148.73
$1,282,830.15
Over/Under Est:
-16.38%
-$251,198.45
Amt Left:
13.08%
$148,344.11
Delta:
-3.09%
-$38,416.82
$1,308,027.60
Over/Under Est:
-14.73%
-$226,001.00
Amt Left:
15.3%
$173,541.56
Delta:
-1.96%
-$25,197.45
$1,446,457.14
Over/Under Est:
-5.71%
-$87,571.46
Amt Left:
27.5%
$311,971.10
Delta:
-10.58%
-$138,429.54
$1,624,574.50
Over/Under Est:
5.9%
$90,545.90
Amt Left:
43.2%
$490,088.46
Delta:
-12.31%
-$178,117.36
$1,845,088.50
Over/Under Est:
20.28%
$311,059.90
Amt Left:
62.64%
$710,602.46
Delta:
-13.57%
-$220,514.00
| Subcontractor | Percentage | Amount |
|---|---|---|
| ORCA CONCRETE, LLC | 2.64% | $29,950.43 |
| Total: | 2.64% | $29,950.43 |