Show Job Controls
Bid Cobra

ELLIS IH 35E (0048-04-094)

Items: 252

County: ELLIS
Length: N/A
Highway: IH 35E
District: DALLAS
Control Number: 0048-04-094
DBE Goal: N/A
Project: C 48-4-94
Guaranty: N/A
Time: 0 X
Engineer's Estimate: $48,339,487.49
Date: 01/06/2022 (4 years ago)
Contract Number: N/A
Type: INTERCHANGE IMPROVEMENT
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (8)
E
Engineer's Estimate
$48,339,487.49
$51,184,067.39
Over/Under Est: 5.88% $2,844,579.90
$51,876,450.00
Over/Under Est: 7.32% $3,536,962.51
Amt Left: 1.35% $692,382.61
$52,849,998.96
Over/Under Est: 9.33% $4,510,511.47
Amt Left: 3.25% $1,665,931.57
Delta: -1.88% -$973,548.96
Over/Under Est: 9.63% $4,655,644.05
Amt Left: 3.54% $1,811,064.15
Delta: -0.27% -$145,132.58
Over/Under Est: 16.36% $7,908,213.57
Amt Left: 9.89% $5,063,633.67
Delta: -6.14% -$3,252,569.52
$56,916,208.21
Over/Under Est: 17.74% $8,576,720.72
Amt Left: 11.2% $5,732,140.82
Delta: -1.19% -$668,507.15
Over/Under Est: 25.88% $12,510,415.53
Amt Left: 18.88% $9,665,835.63
Delta: -6.91% -$3,933,694.81
Over/Under Est: 43.37% $20,964,081.09
Amt Left: 35.4% $18,119,501.19
Delta: -13.89% -$8,453,665.56
Subcontractor Percentage Amount
LOLLAR CONSTRUCTION GROUP LLC 2.26% $1,050,178.82
SLATON BROS, INC. 1.75% $813,191.57
ACT SAW CUTTING & REMOVAL 0.64% $297,395.77
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. 0.60% $278,808.54
KING GEORGE TRAFFIC SOLUTIONS LLC 0.57% $264,868.11
WYLIE DRILLING & DRAINAGE, INC. 0.39% $181,225.55
A R DANIEL CONSTRUCTION SERVICES, INCORPORATED 0.37% $171,931.93
INLET STRUCTURES SPECIALTIES 0.36% $167,285.12
SCOTT DERR PAINTING CO, LLC 0.22% $102,229.80
ANTIGO CONSTRUCTION, INC. 0.22% $102,229.80
USA SWPPP INSPECTIONS, INC.DBA USA EROSION 0.21% $97,582.99
FORTSON CONTRACTING, INC. 0.16% $74,348.94
FARR FOUNDATION, INC. 0.15% $69,702.13
MONARREZ TRUCKING LLC. 0.11% $51,114.90
FREIGHT OPERATION SERVICES, LLC, DBA FOS BROKERAGE SERVICES 0.11% $51,114.90
STRAIGHT LINE SAWING & SEALING, INC. 0.06% $27,880.85
TORO BRAVO CONSTRUCTION, LLC 0.03% $13,940.43
SOUTHEAST GRINDING AND GROOVING LLC 0.02% $9,293.62
BLUE ROCK DRILLING, LLC 0.00% $0.00
BUYERS BARRICADES, INC. 0.00% $0.00
KHONSU ENTERPRISE LLC 0.00% $0.00
Total: 8.23% $3,824,323.77

Bid Items & Bid Tabulations

252 Total 0 of 252
ELLIS  |  IH 35E  |  DALLAS  |  0048-04-094  |  01/06/2022  |  $48,339,487.49  |  C 48-4-94  |  INTERCHANGE IMPRV  |  0 X
Item Code
Description
Unit
Quantity
Engineer's Estimate
AUSTIN BRIDGE & ROAD SERVICES, LP
WEBBER, LLC
FLUOR HEAVY CIVIL, LLC
ZACHRY CONSTRUCTION CORPORATION
JAMES CONSTRUCTION GROUP, LLC
SEMA CONSTRUCTION, INC.
ED BELL CONSTRUCTION COMPANY
MARIO SINACOLA & SONS EXCAVATING, INC.
PREPARING ROW
STA 61.000 $7,500.000 $43,927.000 $21,650.000 $15,211.500 $23,543.520 $54,170.000 $34,645.000 $20,366.000 $20,000.000
REMOVING CONC (PAV)
SY 88,111.000 $9.000 $2.060 $6.500 $7.040 $6.250 $4.780 $10.250 $10.000 $20.000
REMOVING CONC (MEDIANS)
SY 110.000 $20.000 $5.580 $34.500 $5.950 $20.000 $27.630 $9.500 $20.000 $20.000
REMOVING CONC (FOUNDATIONS)
CY 7.000 $225.000 $177.450 $453.000 $244.740 $300.000 $300.760 $110.000 $500.000 $180.000
REMOVING CONC (DRIVEWAYS)
SY 1,559.000 $10.000 $13.830 $14.750 $6.800 $7.000 $26.210 $7.000 $15.000 $20.000
REMOVING CONC (CTB)
LF 7,225.000 $12.500 $4.620 $9.750 $7.850 $6.000 $9.720 $8.600 $30.000 $25.000
REMOVING STAB BASE & ASPH PV(10 TO 16")
SY 127,142.000 $7.000 $1.800 $3.000 $3.210 $2.500 $4.110 $9.750 $0.250 $2.000
EXCAVATION (ROADWAY)
CY 51,123.000 $7.000 $5.150 $10.800 $5.900 $8.000 $5.870 $5.400 $2.500 $20.000
EMBANKMENT (FINAL) (DENS CONT) (TY C1)
CY 18,157.000 $6.000 $14.820 $9.500 $12.500 $13.000 $31.440 $13.100 $14.000 $20.000
EMBANKMENT (FINAL) (DENS CONT) (TY C2)
CY 150,847.000 $20.000 $29.330 $32.750 $35.000 $22.000 $35.010 $28.250 $50.000 $30.000
COMPOST MANUF TOPSOIL (4")
SY 73,075.000 $1.500 $2.140 $1.250 $1.800 $2.000 $0.770 $2.000 $0.900 $0.800
BLOCK SODDING
SY 39,870.000 $4.000 $3.910 $3.300 $2.950 $3.000 $3.250 $3.350 $3.500 $3.000
DRILL SEEDING (PERM) (URBAN) (CLAY)
SY 33,205.000 $0.100 $1.070 $0.150 $0.200 $0.200 $0.410 $0.420 $3.500 $0.140
DRILL SEED (TEMP)(WARM OR COOL)
SY 73,075.000 $0.100 $0.930 $0.100 $0.180 $0.180 $0.270 $0.280 $0.010 $0.090
VEGETATIVE WATERING
MG 21,741.000 $12.000 $0.100 $9.250 $0.010 $0.100 $10.330 $12.000 $1.000 $1.000
FL BS (CMP IN PLC)(TY D GR 1-2)(16")
SY 7,656.000 $20.000 $28.060 $27.250 $16.300 $25.950 $31.730 $26.500 $33.000 $28.000
LIME (HYDRATED LIME (SLURRY))
TON 2,701.000 $145.000 $189.400 $174.000 $172.970 $190.000 $179.380 $160.000 $192.000 $177.000
LIME TRT (EXST MATL) (12")
SY 87,587.000 $3.000 $3.080 $3.750 $3.320 $3.500 $4.140 $4.400 $4.000 $6.500
LIME TRT (EXST MATL)(8")
SY 48,578.000 $3.500 $4.020 $4.000 $3.870 $4.000 $4.550 $3.800 $3.500 $8.500
PRIME COAT(MC-30 OR AE-P)
GAL 1,531.000 $4.500 $3.120 $5.050 $5.050 $5.000 $5.050 $5.150 $7.500 $5.050
CONC PVMT (CONT REINF - CRCP) (13")
SY 83,942.000 $72.000 $74.850 $76.500 $82.440 $84.000 $85.110 $75.500 $75.000 $90.000
CONC PVMT (CONT REINF - CRCP) (11.5")
SY 42,289.000 $65.000 $74.390 $74.500 $81.090 $82.000 $82.960 $77.500 $80.000 $90.000
CEM STABIL BKFL
CY 763.000 $150.000 $148.910 $69.750 $80.000 $140.000 $166.410 $125.000 $250.000 $150.000
CUT & RESTORING PAV
SY 159.000 $110.000 $135.220 $147.750 $130.300 $150.000 $274.830 $140.000 $175.000 $200.000
TRENCH EXCAVATION PROTECTION
LF 3,580.000 $2.500 $10.580 $2.750 $10.000 $7.000 $1.080 $28.000 $7.500 $10.000
TEMPORARY SPL SHORING
SF 41,255.000 $20.000 $8.240 $25.750 $11.570 $17.000 $14.480 $19.000 $20.000 $30.000
DRILL SHAFT (24 IN)
LF 88.000 $125.000 $151.130 $151.250 $151.130 $152.000 $207.000 $180.000 $158.690 $207.000
DRILL SHAFT (30 IN)
LF 108.000 $140.000 $256.180 $256.250 $256.180 $256.000 $213.000 $300.000 $268.990 $213.000
DRILL SHAFT (42 IN)
LF 1,580.000 $250.000 $225.520 $265.000 $238.240 $250.000 $226.740 $250.000 $300.000 $245.000
DRILL SHAFT (48 IN)
LF 32.000 $300.000 $407.380 $407.500 $407.380 $408.000 $589.000 $650.000 $427.750 $589.000
DRILL SHAFT (54 IN)
LF 56.000 $315.000 $490.880 $491.000 $490.880 $491.000 $575.000 $790.000 $515.420 $575.000
DRILL SHAFT (TRF SIG POLE) (36 IN)
LF 15.000 $260.000 $304.330 $304.500 $304.330 $305.000 $297.800 $315.000 $319.550 $470.000
CL A CONC (MISC)
CY 5.000 $800.000 $1,000.000 $800.000 $1,000.000 $275.000 $2,331.150 $830.000 $1,050.000 $775.000
CL B CONC (FLUME)
CY 106.000 $500.000 $461.000 $510.500 $490.320 $500.000 $505.760 $500.000 $840.000 $600.000
CL C CONC (ABUT)(HPC)
CY 169.200 $900.000 $1,010.340 $1,000.000 $889.790 $965.000 $713.230 $1,000.000 $1,000.000 $1,250.000
CL C CONC (CAP)(HPC)
CY 177.000 $1,100.000 $1,022.260 $1,040.000 $1,159.460 $1,250.000 $1,037.020 $1,000.000 $1,000.000 $1,250.000
CL C CONC (COLUMN)(HPC)
CY 110.500 $850.000 $1,000.560 $1,210.000 $984.730 $1,300.000 $760.850 $1,000.000 $1,000.000 $1,250.000
REINF CONC SLAB (HPC)
SF 56,562.000 $18.000 $15.260 $19.000 $15.750 $18.000 $16.360 $16.000 $16.000 $21.000
APPROACH SLAB
CY 343.000 $450.000 $399.170 $375.000 $542.680 $700.000 $476.150 $520.000 $600.000 $700.000
RETAINING WALL (MSE)
SF 59,861.000 $58.000 $32.940 $30.500 $32.460 $38.000 $35.780 $33.500 $45.000 $90.000
PRESTR CONC GIRDER (TX62)
LF 7,100.660 $155.000 $177.740 $187.000 $201.390 $200.000 $216.600 $205.000 $250.000 $210.000
RIPRAP (CONC)(4 IN)
CY 773.000 $350.000 $405.890 $479.000 $450.830 $475.000 $384.110 $475.000 $600.000 $530.000
RIPRAP (STONE COMMON)(DRY)(18 IN)
CY 79.000 $125.000 $513.320 $220.000 $112.500 $125.000 $164.670 $120.000 $350.000 $275.000
RIPRAP (MOW STRIP)(4 IN)
CY 211.000 $425.000 $459.870 $492.000 $519.360 $800.000 $524.370 $500.000 $650.000 $560.000
RAIL (TY SSTR)
LF 6,656.000 $45.000 $53.730 $51.250 $49.550 $55.000 $45.450 $102.000 $60.000 $80.000
RAIL (TY C223)
LF 109.000 $140.000 $241.750 $203.000 $147.260 $375.000 $156.670 $194.000 $150.000 $425.000
RAIL (TY C412)(HPC)
LF 792.000 $215.000 $177.100 $200.000 $125.300 $250.000 $198.300 $205.000 $250.000 $330.000
RAIL (HANDRAIL)(TY F)
LF 278.000 $120.000 $144.720 $130.000 $156.090 $160.000 $131.810 $158.000 $175.000 $230.000
RAIL (TY SSTR) (W/DRAIN SLOTS)
LF 1,300.000 $35.000 $56.400 $57.500 $50.270 $60.000 $50.380 $91.000 $65.000 $115.000
SEALED EXPANSION JOINT (4 IN) (SEJ - A)
LF 294.000 $85.000 $115.580 $113.250 $112.160 $120.000 $90.530 $110.000 $100.000 $170.000
CMP (GAL STL 18 IN)
LF 787.000 $50.000 $51.810 $76.750 $72.740 $80.000 $114.000 $63.000 $75.000 $80.000
CONC BOX CULV (4 FT X 2 FT)
LF 1,714.000 $200.000 $192.180 $200.500 $212.860 $240.000 $224.080 $220.000 $250.000 $220.000
CONC BOX CULV (5 FT X 3 FT)
LF 1,830.000 $240.000 $263.790 $273.500 $302.120 $325.000 $298.890 $310.000 $300.000 $300.000
CONC BOX CULV (9 FT X 5 FT)(EXTEND)
LF 14.000 $500.000 $747.600 $1,760.000 $2,261.930 $1,000.000 $2,080.300 $940.000 $850.000 $1,900.000
RC PIPE (CL III)(24 IN)
LF 9,301.000 $75.000 $78.480 $72.000 $75.000 $130.000 $106.480 $80.000 $70.000 $120.000
RC PIPE (CL III)(30 IN)
LF 655.000 $95.000 $99.480 $90.250 $85.000 $145.000 $135.970 $105.000 $85.000 $105.000
RC PIPE (CL III)(36 IN)
LF 1,062.000 $130.000 $125.560 $131.500 $115.000 $160.000 $152.820 $142.000 $120.000 $140.000
RC PIPE (CL IV)(24 IN)
LF 4,691.000 $180.000 $139.960 $75.000 $135.000 $190.000 $113.270 $100.000 $80.000 $95.000
JCTBOX(COMPL)(PJB)(3FTX3FT)
EA 45.000 $3,700.000 $5,385.810 $3,380.000 $4,812.490 $4,500.000 $3,695.270 $3,500.000 $7,000.000 $5,750.000
JCTBOX(COMPL)(PJB)(5FTX5FT)
EA 3.000 $3,500.000 $6,766.910 $7,300.000 $6,163.810 $6,200.000 $5,168.730 $5,500.000 $9,000.000 $7,500.000
JCTBOX(COMPL)(PJB)(8FTX8FT)
EA 1.000 $4,000.000 $12,526.120 $15,000.000 $13,183.330 $1,100.000 $11,775.130 $9,700.000 $17,000.000 $17,000.000
INLET (COMPL)(PCO)(3FT)(NONE)
EA 3.000 $4,000.000 $5,576.350 $5,060.000 $6,667.890 $5,000.000 $3,875.450 $5,900.000 $8,200.000 $7,150.000
INLET (COMPL)(PCO)(3FT)(LEFT)
EA 18.000 $4,000.000 $5,982.920 $7,000.000 $6,956.020 $7,500.000 $4,275.850 $7,400.000 $8,700.000 $8,000.000
INLET (COMPL)(PCO)(3FT)(RIGHT)
EA 14.000 $4,400.000 $6,219.400 $7,030.000 $7,238.120 $7,500.000 $4,528.160 $7,400.000 $9,000.000 $8,000.000
INLET (COMPL)(PCO)(3FT)(BOTH)
EA 8.000 $5,000.000 $6,444.340 $7,040.000 $8,307.110 $7,800.000 $4,768.440 $7,400.000 $9,200.000 $8,250.000
INLET (COMPL)(PSL)(FG)(4FTX4FT-3FTX3FT)
EA 4.000 $6,500.000 $6,461.670 $5,760.000 $5,039.630 $6,000.000 $5,364.730 $5,300.000 $8,100.000 $7,000.000
INLET(COMPL)(PSL)(SFG)(3FTX3FT-3FTX3FT)
EA 2.000 $3,500.000 $5,962.460 $5,400.000 $4,564.740 $5,000.000 $4,872.240 $4,400.000 $7,500.000 $7,000.000
INLET(COMPL)(PSL)(SFG)(4FTX4FT-4FTX4FT)
EA 3.000 $4,500.000 $6,758.070 $6,130.000 $5,344.640 $6,000.000 $5,681.050 $4,900.000 $8,500.000 $7,000.000
INLET(COMPL)(PAZD)(FG)(5FTX5FT-4FTX4FT)
EA 3.000 $5,500.000 $6,644.660 $7,120.000 $5,415.540 $6,400.000 $5,508.880 $5,800.000 $8,900.000 $7,000.000
INLET (COMPL)(RWI)(TY II)
EA 34.000 $5,500.000 $7,304.220 $5,050.000 $9,241.260 $9,000.000 $8,589.200 $2,900.000 $13,000.000 $10,000.000
HEADWALL (CH - PW - 0) (DIA= 24 IN)
EA 6.000 $4,500.000 $5,299.040 $10,750.000 $4,974.490 $4,600.000 $5,376.480 $5,000.000 $5,800.000 $10,000.000
WINGWALL (PW - 1) (HW=9 FT)
EA 1.000 $50,000.000 $69,946.210 $27,850.000 $55,347.070 $85,000.000 $60,741.330 $79,000.000 $70,000.000 $90,000.000
WINGWALL (PW) (HW=5 FT) (MOD)
EA 1.000 $48,000.000 $22,161.390 $15,850.000 $7,953.280 $11,000.000 $7,215.840 $12,000.000 $16,000.000 $17,500.000
HEADWALL (CH-PW-S)(DIA = 24 IN)(MOD)
EA 2.000 $5,000.000 $13,677.400 $22,000.000 $12,815.670 $10,500.000 $9,629.110 $11,000.000 $15,000.000 $15,000.000
SET (TY I) (24 IN) (3: 1) (C)
EA 1.000 $3,500.000 $1,010.920 $1,820.000 $1,737.140 $9,000.000 $3,410.120 $900.000 $3,000.000 $7,000.000
SET (TY I)(S= 5 FT)(HW= 3 FT)(6:1) (P)
EA 2.000 $9,000.000 $11,886.870 $22,150.000 $4,399.720 $11,000.000 $7,615.020 $11,000.000 $12,500.000 $18,000.000
SET (TY II) (24 IN) (RCP) (6: 1) (P)
EA 17.000 $1,500.000 $1,477.950 $1,590.000 $1,615.030 $1,200.000 $1,885.570 $960.000 $1,300.000 $2,400.000
SLOT DRAIN (GAL STL) (24 IN)
LF 80.000 $520.000 $322.120 $290.000 $285.800 $230.000 $406.610 $242.000 $400.000 $270.000
JACK BOR OR TUN PIPE(24 IN)(RC)(CL IV)
LF 232.000 $690.000 $806.180 $1,640.000 $900.000 $900.000 $907.710 $840.000 $950.000 $940.000
CLEAN EXIST CULVERTS
EA 1.000 $2,000.000 $10,000.000 $6,680.000 $3,522.550 $2,500.000 $25,221.590 $20,000.000 $15,000.000 $100,000.000
REMOV STR (INLET)
EA 12.000 $550.000 $482.010 $1,130.000 $512.770 $780.000 $746.300 $725.000 $900.000 $750.000
REMOV STR (MANHOLE)
EA 1.000 $650.000 $958.850 $700.000 $547.530 $1,200.000 $746.320 $780.000 $1,500.000 $2,000.000
REMOV STR (SET)
EA 23.000 $375.000 $782.800 $725.000 $212.560 $700.000 $298.520 $400.000 $400.000 $600.000
REMOV STR (WINGWALL)
EA 3.000 $1,400.000 $7,099.780 $1,200.000 $2,393.840 $2,000.000 $2,795.090 $1,000.000 $3,500.000 $3,500.000
REMOV STR (HEADWALL)
EA 9.000 $1,400.000 $2,565.040 $1,125.000 $1,210.810 $1,300.000 $2,795.090 $1,400.000 $1,800.000 $3,500.000
REMOV STR (PIPE)
LF 4,417.000 $15.000 $26.830 $20.250 $8.400 $20.000 $22.450 $17.000 $21.000 $20.000
REMOV STR (BRIDGE 100 - 499 FT LENGTH)
EA 1.000 $75,000.000 $65,429.730 $110,295.070 $80,829.580 $75,000.000 $250,000.000 $110,000.000 $100,000.000 $125,000.000
REMOV STR (SLOTTED DRAIN INLET)
LF 1,649.000 $15.000 $9.370 $18.250 $10.440 $15.000 $26.870 $16.000 $45.000 $30.000
MOBILIZATION
LS 1.000 $3,500,000.000 $4,584,611.520 $4,700,000.000 $4,699,999.000 $4,000,000.000 $5,000,000.000 $5,010,000.000 $5,000,000.000 $6,620,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 26.000 $15,000.000 $20,000.000 $5,740.000 $7,359.160 $35,000.000 $20,130.800 $17,000.000 $31,500.000 $150,000.000
ROCK FILTER DAMS (INSTALL) (TY 1)
LF 125.000 $10.000 $25.300 $32.000 $22.000 $22.000 $28.100 $29.000 $30.000 $30.000
ROCK FILTER DAMS (REMOVE)
LF 125.000 $8.000 $8.620 $10.250 $7.500 $7.500 $11.000 $11.000 $13.000 $1.000
CONSTRUCTION EXITS (INSTALL) (TY 1)
SY 2,496.000 $21.000 $28.750 $32.500 $25.000 $25.000 $27.830 $28.500 $20.000 $20.000
CONSTRUCTION EXITS (REMOVE)
SY 2,496.000 $7.000 $7.470 $8.000 $6.500 $6.500 $11.000 $11.000 $10.000 $1.000
TEMP SEDMT CONT FENCE (INSTALL)
LF 2,712.000 $2.000 $2.640 $6.000 $2.300 $2.300 $3.500 $3.600 $2.000 $6.000
TEMP SEDMT CONT FENCE (REMOVE)
LF 2,712.000 $0.650 $0.580 $1.250 $0.500 $0.500 $1.000 $1.000 $0.250 $0.100
BIODEG EROSN CONT LOGS (INSTL) (12")
LF 1,921.000 $7.000 $4.310 $4.500 $3.750 $3.750 $4.500 $4.650 $4.000 $5.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 1,921.000 $0.800 $0.580 $1.250 $0.500 $0.500 $1.000 $1.000 $1.500 $0.100
CONSTRUCTING DETOURS
SY 33,282.000 $60.000 $62.360 $70.250 $66.960 $65.000 $65.470 $84.000 $67.500 $90.000
PORT CTB (FUR & INST)(SGL SLOPE)(TY 1)
LF 26,640.000 $25.000 $36.550 $33.500 $36.300 $32.500 $42.170 $37.000 $75.000 $60.000
PORT CTB (FUR & INST)(LOW PROF)(TY 1)
LF 8,310.000 $22.000 $32.400 $28.500 $47.430 $26.000 $35.840 $49.000 $20.000 $50.000
PORT CTB (FUR & INST)(LOW PROF)(TY 2)
LF 180.000 $40.000 $41.870 $35.000 $46.830 $42.000 $68.870 $50.000 $60.000 $50.000
PORT CTB (MOVE)(SGL SLP)(TY 1)
LF 25,080.000 $5.000 $13.560 $6.750 $6.630 $6.000 $2.810 $6.000 $6.000 $10.000
PORT CTB (MOVE)(LOW PROF)(TY 1)
LF 13,440.000 $8.000 $3.380 $2.750 $0.650 $4.500 $3.120 $4.000 $6.000 $10.000
PORT CTB (MOVE)(LOW PROF)(TY 2)
LF 320.000 $8.000 $14.940 $5.500 $0.650 $4.200 $3.260 $7.600 $18.000 $10.000
PORT CTB (REMOVE)(SGL SLP)(TY 1)
LF 26,640.000 $5.000 $8.250 $6.250 $5.460 $6.000 $8.200 $8.300 $7.000 $5.000
PORT CTB (REMOVE)(LOW PROF)(TY 1)
LF 8,310.000 $7.000 $6.380 $7.750 $3.670 $7.500 $10.080 $8.400 $7.000 $5.000
PORT CTB (REMOVE)(LOW PROF)(TY 2)
LF 180.000 $9.000 $9.190 $8.000 $2.840 $8.000 $13.140 $9.400 $21.000 $5.000
PERM CTB (SGL SLOPE) (TY 1) (42 )
LF 3,156.600 $65.000 $63.450 $97.000 $66.280 $67.000 $1.000 $120.000 $80.000 $70.000
PERM CTB (SSCB)(TY 1)(MOD)
LF 1,871.000 $115.000 $328.240 $316.000 $462.320 $350.000 $1.000 $270.000 $500.000 $340.000
PERM CTB (SSCB)(TY 2)(MOD)
LF 2,108.000 $145.000 $221.680 $202.000 $402.230 $350.000 $1.000 $270.000 $495.000 $240.000
CONC CURB (MONO) (TY II)
LF 18,632.000 $4.000 $6.490 $3.000 $1.510 $4.000 $3.550 $4.750 $2.500 $5.000
CONC CURB & GUTTER (TY II)
LF 255.000 $25.000 $61.770 $25.000 $31.680 $47.000 $18.790 $32.000 $60.000 $40.000
DRIVEWAYS (CONC) (HES)
SY 3,122.000 $72.000 $74.790 $80.000 $94.420 $62.000 $68.660 $76.500 $90.000 $75.000
CONC SIDEWALKS (4")
SY 5,495.000 $47.000 $46.390 $55.750 $54.900 $55.000 $44.070 $51.000 $55.000 $58.000
CURB RAMPS (TY 1)
EA 8.000 $1,800.000 $1,423.000 $1,540.000 $2,124.360 $2,400.000 $1,862.460 $1,550.000 $2,000.000 $2,500.000
CURB RAMPS (TY 5)
EA 2.000 $2,600.000 $1,700.000 $2,240.000 $2,396.740 $5,000.000 $3,639.490 $1,850.000 $4,000.000 $2,500.000
CURB RAMPS (TY 21)
EA 2.000 $2,000.000 $2,365.000 $2,660.000 $2,239.340 $3,200.000 $2,076.010 $2,550.000 $2,000.000 $2,500.000
CONC MEDIAN
SY 1,061.000 $55.000 $50.500 $60.250 $54.060 $52.000 $38.790 $55.000 $63.000 $65.000
MTL W-BEAM GD FEN (TIM POST)
LF 1,137.500 $22.000 $21.500 $25.900 $21.500 $21.500 $25.200 $22.500 $22.570 $23.000
MTL BEAM GD FEN TRANS (THRIE-BEAM)
EA 10.000 $1,750.000 $1,700.000 $1,790.000 $1,700.000 $1,699.940 $1,954.000 $1,780.000 $1,785.000 $1,900.000
DOWNSTREAM ANCHOR TERMINAL SECTION
EA 3.000 $1,200.000 $1,100.000 $1,460.000 $1,100.000 $1,099.960 $1,738.000 $1,140.000 $1,155.000 $1,600.000
REMOVE METAL BEAM GUARD FENCE
LF 3,730.000 $2.750 $2.000 $1.650 $2.000 $2.000 $4.000 $2.100 $2.100 $3.000
REMOVE TERMINAL ANCHOR SECTION
EA 6.000 $200.000 $125.000 $138.000 $125.000 $125.000 $400.000 $130.000 $131.250 $250.000
REMOVE DOWNSTREAM ANCHOR TERMINAL
EA 14.000 $250.000 $50.000 $138.000 $50.000 $50.000 $400.000 $52.000 $52.500 $250.000
RM MTL BM GD FENCE TRANS (THRIE-BEAM)
EA 3.000 $220.000 $200.000 $165.000 $200.000 $199.990 $400.000 $210.000 $210.000 $250.000
GUARDRAIL END TREATMENT (INSTALL)
EA 7.000 $2,500.000 $2,700.000 $165.000 $2,700.000 $2,699.900 $2,748.000 $2,800.000 $2,835.000 $3,142.000
GUARDRAIL END TREATMENT (REMOVE)
EA 15.000 $270.000 $200.000 $165.000 $200.000 $199.990 $400.000 $210.000 $210.000 $350.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 5.000 $1,300.000 $926.050 $1,920.000 $1,200.000 $1,199.950 $1,000.000 $1,000.000 $2,100.000 $1,000.000
CRASH CUSH ATTEN (REMOVE)
EA 2.000 $800.000 $617.680 $1,120.000 $750.000 $749.970 $600.000 $750.000 $1,050.000 $1,000.000
CRASH CUSH ATTEN (INSTL)(L)(W)(TL3)
EA 1.000 $45,000.000 $36,788.090 $50,600.000 $44,725.000 $44,723.300 $49,460.000 $42,000.000 $50,000.000 $35,000.000
CRASH CUSH ATTEN (INSTL)(S)(N)(TL3)
EA 4.000 $7,500.000 $8,811.050 $8,990.000 $7,950.000 $7,949.700 $10,810.000 $7,800.000 $10,500.000 $10,000.000
IN RD IL (U/P) (TY 1) (150W EQ) LED
EA 8.000 $1,300.000 $914.300 $925.000 $914.300 $914.270 $1,567.500 $927.000 $960.020 $1,815.000
IN RD IL (TY SA) 40B-8 (250W EQ) LED
EA 20.000 $3,200.000 $3,016.550 $3,016.550 $3,016.550 $3,016.440 $3,861.000 $3,075.000 $3,167.380 $4,495.000
IN RD IL (TY SA) 40T-8 (250W EQ) LED
EA 9.000 $2,100.000 $3,484.600 $3,484.600 $3,484.600 $3,484.470 $4,079.000 $3,550.000 $3,658.830 $4,045.000
CONDT (PVC) (SCH 40) (2")
LF 9,200.000 $9.000 $9.180 $9.180 $9.180 $9.180 $9.850 $9.300 $9.640 $21.000
CONDT (PVC) (SCH 40) (3")
LF 9,872.000 $16.000 $14.700 $13.800 $14.700 $14.700 $15.600 $14.900 $15.440 $26.750
CONDT (PVC) (SCH 40) (3") (BORE)
LF 2,122.000 $25.000 $20.190 $20.190 $20.190 $20.190 $30.200 $20.800 $21.200 $50.500
CONDT (PVC) (SCH 80) (2") (BORE)
LF 1,350.000 $10.000 $16.740 $16.740 $16.740 $16.740 $20.500 $17.000 $17.580 $47.500
CONDT (RM) (3/4")
LF 275.000 $25.000 $18.070 $18.070 $18.070 $18.070 $21.000 $18.400 $18.970 $46.950
CONDT (RM) (1")
LF 40.000 $20.000 $29.120 $29.120 $29.120 $29.120 $31.500 $29.800 $30.580 $43.900
CONDT (RM) (2")
LF 220.000 $32.000 $47.070 $47.070 $47.070 $47.070 $42.000 $48.000 $49.420 $67.150
ELEC CONDR (NO.12) BARE
LF 315.000 $1.000 $1.030 $1.030 $1.030 $1.030 $0.930 $1.050 $1.080 $1.900
ELEC CONDR (NO.12) INSULATED
LF 615.000 $1.000 $1.170 $1.170 $1.170 $1.170 $0.990 $1.200 $1.230 $2.100
ELEC CONDR (NO.8) BARE
LF 11,245.000 $1.200 $1.150 $1.350 $1.150 $1.150 $1.360 $1.180 $1.210 $2.310
ELEC CONDR (NO.8) INSULATED
LF 29,126.000 $1.250 $1.220 $1.220 $1.220 $1.220 $1.520 $1.250 $1.280 $2.420
ELEC CONDR (NO.6) BARE
LF 385.000 $1.250 $1.700 $1.700 $1.700 $1.700 $1.630 $1.750 $1.790 $2.700
ELEC CONDR (NO.6) INSULATED
LF 1,155.000 $1.400 $1.800 $1.800 $1.800 $1.800 $1.790 $1.850 $1.890 $2.750
GROUND BOX TY A (122311)
EA 18.000 $1,000.000 $875.250 $875.250 $875.250 $875.220 $1,170.000 $900.000 $919.010 $1,430.000
GROUND BOX TY A (122311)W/APRON
EA 15.000 $1,000.000 $1,042.250 $1,042.250 $1,042.250 $1,042.210 $1,242.000 $1,060.000 $1,094.360 $2,186.000
TIMBER POLE (CL 2) 40 FT
EA 38.000 $1,800.000 $1,122.500 $1,122.500 $1,122.500 $1,122.460 $1,045.000 $1,150.000 $1,178.630 $1,999.000
ELC SRV TY A 240/480 060(NS)SS(E)SP(U)
EA 1.000 $8,000.000 $6,595.550 $7,500.000 $6,595.550 $6,595.300 $5,750.000 $6,690.000 $6,925.330 $10,590.000
ELC SRV TY D 120/240 060(NS)SS(N)PS(U)
EA 1.000 $6,500.000 $5,680.250 $5,680.250 $5,680.250 $5,680.030 $7,180.000 $5,780.000 $5,964.260 $10,425.000
ALUMINUM SIGNS (TY G)
SF 740.000 $22.000 $30.790 $30.790 $30.790 $30.790 $28.700 $31.400 $32.330 $27.250
ALUMINUM SIGNS (TY O)
SF 746.000 $27.000 $30.210 $30.210 $30.210 $30.210 $28.700 $30.800 $31.720 $26.750
REFURBISH ALUMINUM SIGNS (TY O)
EA 1.000 $180.000 $3,422.500 $3,422.500 $3,422.500 $3,422.370 $3,750.000 $3,480.000 $3,593.630 $3,500.000
REPLACE EXISTING ALUMINUM SIGNS(TY O)
SF 640.000 $28.000 $32.950 $32.950 $32.950 $32.950 $198.700 $33.500 $34.600 $26.750
IN SM RD SN SUP&AM TY10BWG(1)SA(P)
EA 7.000 $550.000 $665.080 $665.080 $665.080 $665.050 $807.000 $675.000 $698.330 $825.000
IN SM RD SN SUP&AM TY10BWG(1)SA(T)
EA 47.000 $575.000 $731.890 $731.890 $731.890 $731.860 $873.000 $745.000 $768.480 $910.000
IN SM RD SN SUP&AM TYS80(1)SA(P-BM)
EA 6.000 $800.000 $1,149.560 $1,149.560 $1,149.560 $1,149.520 $1,299.000 $1,166.000 $1,207.040 $1,350.000
IN SM RD SN SUP&AM TYS80(1)SA(T)
EA 3.000 $700.000 $1,150.190 $1,150.190 $1,150.190 $1,150.150 $1,299.000 $1,166.000 $1,207.700 $1,350.000
IN SM RD SN SUP&AM TYS80(1)SA(U)
EA 2.000 $1,000.000 $1,260.720 $1,260.720 $1,260.720 $1,260.670 $1,410.000 $1,280.000 $1,323.760 $1,500.000
IN SM RD SN SUP&AM TYS80(1)SA(U-1EXT)
EA 4.000 $1,000.000 $1,294.660 $1,294.660 $1,294.660 $1,294.610 $1,462.000 $1,315.000 $1,359.390 $1,575.000
IN SM RD SN SUP&AM TYS80(2)SA(P-EXAL)
EA 2.000 $1,800.000 $1,700.350 $1,700.350 $1,700.350 $1,700.290 $2,050.000 $1,740.000 $1,785.370 $2,000.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY N)
EA 2.000 $400.000 $2,054.000 $2,054.000 $2,054.000 $2,053.920 $2,430.000 $2,100.000 $2,156.700 $1,850.000
IN BRIDGE MNT CLEARANCE SGN ASSM(TY S)
EA 2.000 $2,450.000 $2,146.000 $2,146.000 $2,146.000 $2,145.920 $2,540.000 $2,190.000 $2,253.300 $1,900.000
INSTALL LRSS (STRUCT STEEL)
LB 2,846.000 $6.000 $5.090 $5.090 $5.090 $5.090 $6.300 $5.200 $5.340 $5.750
RELOCATE LRSA
EA 4.000 $5,000.000 $1,987.500 $1,987.500 $1,987.500 $1,987.420 $1,500.000 $2,050.000 $2,086.880 $3,500.000
INS OH SN SUP(35 FT CANT)
EA 2.000 $21,615.000 $28,119.690 $28,119.690 $28,119.690 $28,118.620 $28,200.000 $28,600.000 $29,525.680 $27,185.000
INS OH SN SUP(40 FT CANT)
EA 2.000 $18,000.000 $63,797.270 $63,797.270 $63,797.270 $63,794.840 $61,200.000 $64,700.000 $66,987.140 $59,000.000
REMOVE OVERHD SIGN SUP
EA 7.000 $8,000.000 $2,332.500 $2,332.500 $2,332.500 $2,332.410 $3,500.000 $2,375.000 $2,449.130 $8,500.000
INSTL DEL ASSM (D-SW)SZ (BRF)CTB
EA 78.000 $30.000 $39.500 $21.000 $38.920 $35.000 $20.850 $18.500 $18.900 $13.000
INSTL DEL ASSM (D-SW)SZ (BRF)GF1
EA 17.000 $23.500 $24.500 $27.000 $22.420 $24.000 $41.300 $18.500 $18.900 $13.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB
EA 18.000 $21.000 $21.000 $21.000 $10.160 $20.000 $20.850 $18.500 $18.900 $13.000
INSTL DEL ASSM (D-SY)SZ (BRF)CTB (BI)
EA 72.000 $23.000 $18.650 $23.000 $18.790 $20.000 $20.850 $19.000 $19.430 $13.000
INSTL DEL ASSM (D-SY)SZ (BRF)GF1
EA 6.000 $16.500 $16.000 $27.000 $17.230 $30.000 $20.850 $18.500 $18.900 $13.000
INSTL OM ASSM (OM-2Y)(WC)GND
EA 8.000 $65.000 $63.000 $67.850 $65.530 $67.000 $77.500 $47.000 $47.250 $45.000
REFL PAV MRK TY I (W)8"(SLD)(100MIL)
LF 2,598.000 $1.000 $1.220 $1.250 $1.240 $1.220 $1.220 $1.410 $1.280 $1.200
REFL PAV MRK TY I (W)12"(SLD)(100MIL)
LF 2,031.000 $3.000 $3.450 $3.500 $3.490 $3.450 $3.450 $4.000 $3.620 $4.550
REFL PAV MRK TY I (W)24"(SLD)(100MIL)
LF 250.000 $6.000 $6.400 $6.500 $6.480 $6.400 $6.400 $7.400 $6.720 $8.200
REFL PAV MRK TY I (Y)8"(SLD)(100MIL)
LF 342.000 $0.850 $1.100 $1.100 $1.110 $1.100 $1.100 $1.270 $1.160 $1.250
REFL PAV MRK TY II (W) 4" (BRK)
LF 18,540.000 $0.150 $0.250 $0.250 $0.250 $0.250 $0.250 $0.290 $0.260 $0.250
REFL PAV MRK TY II (W) 4" (SLD)
LF 63,498.000 $0.100 $0.200 $0.200 $0.200 $0.200 $0.200 $0.290 $0.210 $0.250
REFL PAV MRK TY II (W) 8" (SLD)
LF 438.000 $0.650 $0.450 $0.450 $0.460 $0.450 $0.450 $0.520 $0.470 $0.500
REFL PAV MRK TY II (W) 12" (SLD)
LF 220.000 $1.800 $1.000 $1.000 $1.010 $1.000 $1.000 $1.160 $1.050 $2.500
REFL PAV MRK TY II (Y) 4" (SLD)
LF 66,771.000 $0.110 $0.200 $0.200 $0.200 $0.200 $0.200 $0.240 $0.210 $0.250
PAVEMENT SEALER 4"
LF 62,154.000 $0.150 $0.130 $0.150 $0.130 $0.130 $0.130 $0.160 $0.140 $0.200
PAVEMENT SEALER 6"
LF 8,976.000 $0.200 $0.160 $0.150 $0.160 $0.160 $0.160 $0.190 $0.170 $0.250
PAVEMENT SEALER 8"
LF 2,793.000 $0.350 $0.410 $0.400 $0.420 $0.410 $0.410 $0.480 $0.430 $0.400
PAVEMENT SEALER 12"
LF 2,191.000 $1.000 $1.000 $1.000 $1.010 $1.000 $1.000 $1.160 $1.050 $1.500
PAVEMENT SEALER 24"
LF 250.000 $1.450 $2.000 $2.050 $2.030 $2.000 $2.000 $2.320 $2.100 $2.250
PAVEMENT SEALER (ARROW)
EA 14.000 $45.000 $5.000 $5.050 $5.070 $5.000 $5.000 $5.800 $5.250 $29.000
PAVEMENT SEALER (WORD)
EA 11.000 $46.000 $5.000 $5.050 $5.070 $5.000 $5.000 $5.800 $5.250 $35.000
PAVEMENT SEALER (DBL ARROW)
EA 4.000 $68.000 $5.000 $5.050 $5.070 $5.000 $5.000 $5.800 $5.250 $42.000
PAVEMENT SEALER (UTURN ARROW)
EA 4.000 $85.000 $5.000 $5.050 $5.070 $5.000 $5.000 $5.800 $5.250 $45.000
PAVEMENT SEALER (ENTR GORE)
EA 5.000 $250.000 $5.000 $5.050 $5.070 $5.000 $5.000 $5.800 $5.250 $236.000
PAVEMENT SEALER (EXIT GORE)
EA 4.000 $275.000 $5.000 $5.050 $5.070 $5.000 $5.000 $5.800 $5.250 $244.000
PAVEMENT SEALER (NUMBER)
EA 2.000 $3.000 $5.000 $5.050 $5.070 $5.000 $5.000 $5.800 $5.250 $20.000
RE PM W/RET REQ TY I (W)4"(BRK)(100MIL)
LF 2,664.000 $0.400 $0.550 $0.550 $0.560 $0.550 $0.550 $0.650 $0.580 $0.600
RE PM W/RET REQ TY I (W)4"(SLD)(100MIL)
LF 31,251.000 $0.300 $0.510 $0.500 $0.520 $0.510 $0.510 $0.600 $0.540 $0.550
RE PM W/RET REQ TY I (W)6"(BRK)(100MIL)
LF 8,976.000 $0.500 $0.670 $0.700 $0.680 $0.670 $0.670 $0.800 $0.700 $0.800
RE PM W/RET REQ TY I (Y)4"(SLD)(100MIL)
LF 32,320.000 $0.350 $0.510 $0.500 $0.520 $0.510 $0.510 $0.600 $0.540 $0.550
REFL PAV MRK TY I (W)12"(DOT)(100MIL)
LF 160.000 $3.000 $3.650 $3.700 $3.700 $3.650 $3.650 $4.250 $3.830 $5.000
PREFAB PAV MRK TY C (W) (ARROW)
EA 16.000 $200.000 $245.000 $248.000 $248.190 $244.990 $245.000 $284.000 $257.250 $316.000
PREFAB PAV MRK TY C (W) (DBL ARROW)
EA 6.000 $350.000 $445.000 $451.000 $450.790 $444.980 $445.000 $515.000 $467.250 $526.000
PREFAB PAV MRK TY C (W) (UTURN ARROW)
EA 4.000 $370.000 $400.000 $405.000 $405.210 $399.980 $400.000 $463.000 $420.000 $546.000
PREFAB PAV MRK TY C (W) (NUMBER)
EA 2.000 $250.000 $200.000 $203.000 $202.610 $199.990 $200.000 $232.000 $210.000 $365.000
PREFAB PAV MRK TY C (W) (WORD)
EA 14.000 $400.000 $295.000 $299.000 $298.840 $294.990 $295.000 $342.000 $309.750 $423.000
PREFAB PAV MRK TY C (W) (ENTR GORE)
EA 5.000 $250.000 $245.000 $248.000 $248.190 $244.990 $245.000 $285.000 $257.250 $3,150.000
PREFAB PAV MRK TY C (W) (EXIT GORE)
EA 4.000 $2,750.000 $2,200.000 $2,230.000 $2,228.630 $2,199.920 $2,200.000 $2,540.000 $2,310.000 $3,550.000
REFL PAV MRKR TY II-C-R
EA 841.000 $4.000 $4.000 $4.050 $4.050 $4.000 $4.000 $4.650 $4.200 $5.000
ELIM EXT PAV MRK & MRKS (4")
LF 142,331.000 $0.400 $0.380 $0.400 $0.380 $0.380 $0.380 $0.450 $0.400 $0.500
ELIM EXT PAV MRK & MRKS (8")
LF 438.000 $1.000 $0.580 $0.600 $0.590 $0.580 $0.580 $0.680 $0.610 $0.850
ELIM EXT PAV MRK & MRKS (12")
LF 78.000 $2.000 $2.000 $2.050 $2.030 $2.000 $2.000 $2.320 $2.100 $3.000
PAV SURF PREP FOR MRK (4")
LF 62,154.000 $0.070 $0.110 $0.100 $0.110 $0.110 $0.110 $0.130 $0.120 $0.150
PAV SURF PREP FOR MRK (6")
LF 8,976.000 $0.120 $0.140 $0.150 $0.140 $0.140 $0.140 $0.170 $0.150 $0.200
PAV SURF PREP FOR MRK (8")
LF 2,793.000 $0.160 $0.220 $0.200 $0.220 $0.220 $0.220 $0.260 $0.230 $0.300
PAV SURF PREP FOR MRK (12")
LF 2,191.000 $0.400 $1.000 $1.000 $1.010 $1.000 $1.000 $1.170 $1.050 $1.000
PAV SURF PREP FOR MRK (24")
LF 250.000 $1.200 $2.000 $2.050 $2.030 $2.000 $2.000 $2.350 $2.100 $2.000
PAV SURF PREP FOR MRK (ARROW)
EA 14.000 $20.000 $27.000 $27.400 $27.350 $27.000 $27.000 $31.400 $28.350 $15.000
PAV SURF PREP FOR MRK (DBL ARROW)
EA 4.000 $24.000 $33.000 $33.500 $33.430 $33.000 $33.000 $38.250 $34.650 $20.000
PAV SURF PREP FOR MRK (UTURN ARR)
EA 4.000 $15.000 $44.000 $44.500 $44.570 $44.000 $44.000 $51.000 $46.200 $25.000
PAV SURF PREP FOR MRK (NUMBER)
EA 2.000 $20.000 $25.000 $25.300 $25.330 $25.000 $25.000 $29.000 $26.250 $20.000
PAV SURF PREP FOR MRK (WORD)
EA 11.000 $30.000 $37.000 $37.500 $37.480 $37.000 $37.000 $43.000 $38.850 $20.000
PAV SURF PREP FOR MRK (ENTR GORE)
EA 5.000 $155.000 $50.000 $50.750 $50.650 $50.000 $50.000 $58.000 $52.500 $195.000
PAV SURF PREP FOR MRK (EXIT GORE)
EA 4.000 $200.000 $350.000 $355.000 $354.560 $349.990 $350.000 $405.000 $367.500 $210.000
REMOVAL OF TIMBER POLES
EA 38.000 $215.000 $547.500 $547.500 $547.500 $547.480 $1,000.000 $556.000 $574.880 $495.000
INSTL DOWN GUY W/GUARD
EA 2.000 $155.000 $1,325.000 $1,325.000 $1,325.000 $1,324.950 $150.000 $1,350.000 $1,391.250 $1,293.000
REMOVE DOWN GUY W/GUARD
EA 2.000 $155.000 $1,095.000 $1,095.000 $1,095.000 $1,094.960 $150.000 $1,150.000 $1,149.750 $495.000
NO. OF WORKING DAYS
$/D 10,000.000 $676.000 $520.000 $520.000 $585.000 $520.000 $591.000 $676.000 $676.000 $550.000
SP MIXES SP-B PG64-22
TON 31,236.000 $70.000 $89.030 $82.500 $82.500 $82.500 $82.500 $85.000 $86.500 $82.500
SP MIXES SP-C SAC-B PG70-22
TON 1,968.000 $85.000 $102.350 $140.000 $140.000 $140.000 $140.000 $143.000 $150.000 $140.000
TACK COAT
GAL 16,300.000 $2.500 $0.100 $5.650 $5.650 $6.000 $5.650 $5.800 $5.750 $5.650
PORTABLE CHANGEABLE MESSAGE SIGN
EA 4.000 $10,000.000 $19,485.000 $15,000.000 $1,029.570 $18,000.000 $5,338.630 $15,000.000 $20,000.000 $12,000.000
FIBER OPTIC CBL (SNGLE-MODE)(6 FIBER)
LF 1,226.000 $2.500 $8.220 $8.220 $8.220 $8.220 $2.210 $8.400 $8.630 $9.800
FIBER OPTIC CBL (SNGLE-MODE)(36 FIBER)
LF 12,482.000 $3.000 $5.500 $5.500 $5.500 $5.500 $2.900 $5.600 $5.780 $2.170
FO CBL (72 SMF)(ADSS)(AERIAL)
LF 7,737.000 $17.000 $9.350 $9.350 $9.350 $9.350 $5.200 $9.500 $9.820 $16.860
FO SPLICE ENCLOSURE (TYPE 1)
EA 7.000 $2,250.000 $2,448.600 $2,448.600 $2,448.600 $2,448.510 $890.000 $2,480.000 $2,571.030 $2,199.000
FIBER OPTIC FUSION SPLICE
EA 324.000 $17.000 $35.600 $35.600 $35.600 $35.600 $63.500 $36.100 $37.380 $51.800
RELOCATE FIBER OPTIC CABLE
LF 2,450.000 $10.000 $4.820 $4.820 $4.820 $4.820 $2.000 $4.900 $5.060 $4.050
REMOVE FIBER OPTIC CABLE
LF 7,737.000 $1.500 $1.740 $1.740 $1.740 $1.740 $1.500 $1.800 $1.830 $1.300
RELOCATE EXISTING COMMUNICATION CABINET
EA 1.000 $12,000.000 $9,072.500 $9,072.500 $9,072.500 $9,072.160 $3,160.000 $9,200.000 $9,526.130 $12,888.000
RELOCATE CCTV FIELD EQUIPMENT
EA 1.000 $1,700.000 $2,477.500 $2,477.500 $2,477.500 $2,477.410 $2,000.000 $2,550.000 $2,601.380 $4,227.000
ITS MULTI-DUCT CND (PVC-40)
LF 4,936.000 $35.000 $25.570 $25.570 $25.570 $25.570 $28.500 $26.000 $26.850 $36.050
ITS MULTI-DUCT CND (PVC-40)(BORE)
LF 1,016.000 $50.000 $41.210 $41.210 $41.210 $41.210 $45.200 $42.000 $43.270 $63.250
GROUND BOX (PREPARE)
EA 2.000 $350.000 $328.500 $328.500 $328.500 $328.490 $450.000 $340.000 $344.930 $814.000
ITS POLE (60 FT)(REL)
EA 1.000 $350.000 $2,874.510 $2,874.510 $2,874.510 $2,874.400 $2,500.000 $3,000.000 $3,018.240 $5,382.000
ITS POLE MNT CAB (TY 2)(CONF 2)(REL)
EA 1.000 $25.000 $1,930.000 $1,930.000 $1,930.000 $1,929.930 $1,200.000 $2,000.000 $2,026.500 $2,723.000
TMA (STATIONARY)
DAY 1,600.000 $190.000 $0.100 $140.000 $56.120 $300.000 $177.360 $275.000 $73.500 $55.000
ITS GND BOX(PCAST) TY 1 (243660)W/APRN
EA 13.000 $5,500.000 $5,071.800 $5,071.800 $5,071.800 $5,071.610 $5,720.000 $5,150.000 $5,325.390 $4,510.000
ITS GND BOX(PCAST) TY 2 (366060)W/APRN
EA 1.000 $6,000.000 $7,097.450 $7,097.450 $7,097.450 $7,097.180 $6,900.000 $7,200.000 $7,452.320 $6,505.000
ITS RVSD (DC & WWA) (RELOCATE)
EA 1.000 $1,600.000 $2,190.000 $2,190.000 $2,191.740 $2,189.920 $1,300.000 $2,250.000 $2,299.500 $8,445.000
Totals: $48,339,487.490 $51,184,067.406 $51,876,450.000 $52,849,998.988 $52,995,131.540 $56,247,701.077 $56,916,208.210 $60,849,903.025 $69,303,568.580