EL PASO IH0010 (6463-91-001)

Items: 25

County: EL PASO
Length: 0.0100 MILES
Highway: IH0010
District: EL PASO
Control Number: 6463-91-001
DBE Goal: 0.0%
Project: BPM - A00207380
Guaranty: $0.00
Time: 104 WORKING DAYS
Engineer's Estimate: $861,118.00
Date: 12/09/2025 (6 months ago) Changed
Contract Number: 12252407
Type: BRIDGE PREVENTATIVE MAINTENANCE
Project ID: A00207380
Project Description: FY 2026 BPM
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice Questions HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (7)
E
Engineer's Estimate
$861,118.00
$555,941.00
Over/Under Est: -35.44% -$305,177.00
Over/Under Est: -20.87% -$179,743.00
Amt Left: 22.56% $125,434.00
Over/Under Est: -9.61% -$82,741.00
Amt Left: 40.01% $222,436.00
Delta: -14.24% -$97,002.00
Over/Under Est: -3.53% -$30,384.19
Amt Left: 49.43% $274,792.81
Delta: -6.73% -$52,356.81
$857,040.50
Over/Under Est: -0.47% -$4,077.50
Amt Left: 54.16% $301,099.50
Delta: -3.17% -$26,306.69
Over/Under Est: 1.95% $16,808.00
Amt Left: 57.92% $321,985.00
Delta: -2.44% -$20,885.50
Over/Under Est: 6.15% $52,990.00
Amt Left: 64.43% $358,167.00
Delta: -4.12% -$36,182.00

Bid Items & Bid Tabulations

25 Total 0 of 25
EL PASO  |  IH0010  |  EL PASO  |  6463-91-001  |  12/09/2025  |  $861,118.00  |  BPM - A00207380  |  BRIDGE PREVENT MAINT  |  104 WORKING DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
PREMIER CONTRACTORS LLC
ICOS MANAGEMENT, LLC
SCR CIVIL CONSTRUCTION, LLC
SYNERGY PROJECT CONTRACTORS, INC.
HAWK CONSTRUCTION
INTERNATIONAL EAGLE ENTERPRISES, INC.
STRUCTURAL INTEGRITY GROUP LLC
EMBANK (FNL)(OC)(TY A)
CY 4.000 $200.000 $50.000 $110.000 $125.000 $637.500 $1,500.000 $500.000 $225.000
FLOWABLE BACKFILL
CY 4.000 $800.000 $500.000 $770.000 $2,550.000 $828.750 $2,500.000 $1,000.000 $650.000
CONC STR REPAIR(DECK REP (FULL DEPTH))
SF 36.000 $470.000 $500.000 $440.000 $325.000 $510.000 $385.000 $450.000 $150.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 830.000 $260.000 $300.000 $165.000 $185.000 $350.630 $360.000 $320.000 $265.000
CLEANING AND SEALING EXIST JOINTS (CL3)
LF 1,194.000 $40.000 $50.000 $55.000 $45.000 $30.600 $58.000 $35.000 $47.000
CLEANING AND SEALING EXIST JOINTS (CL7)
LF 80.000 $70.000 $50.000 $66.000 $55.000 $54.830 $117.000 $50.000 $60.000
MISC NON-BRIDGE (NBIS)
LB 15.000 $100.000 $250.000 $1,100.000 $200.000 $22.950 $625.000 $55.000 $199.000
MOBILIZATION
LS 1.000 $73,588.000 $50,000.000 $55,000.000 $77,800.000 $95,625.000 $17,000.000 $75,000.000 $90,000.000
BARRICADES, SIGNS AND TRAFFIC HANDLING
MO 6.000 $12,000.000 $1.000 $1.000 $7,500.000 $7,012.000 $12,500.000 $21,000.000 $18,000.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 20.000 $150.000 $1.000 $220.000 $250.000 $255.000 $165.000 $120.000 $500.000
TMA (STATIONARY)
DAY 95.000 $300.000 $1.000 $275.000 $250.000 $382.500 $400.000 $350.000 $250.000
BIODEG EROSN CONT LOGS (INSTL) (8")
LF 200.000 $15.000 $6.000 $11.000 $6.000 $15.300 $10.000 $10.000 $2.000
BIODEG EROSN CONT LOGS (REMOVE)
LF 200.000 $3.000 $1.000 $1.000 $2.000 $6.380 $8.000 $2.000 $1.000
MTL W-BEAM GD FEN (TIM POST)
LF 625.000 $120.000 $30.000 $39.000 $69.000 $63.750 $42.500 $45.000 $55.000
REMOVE METAL BEAM GUARD FENCE
LF 650.000 $15.000 $13.000 $6.000 $17.200 $5.100 $8.000 $4.000 $10.000
GUARDRAIL END TREATMENT (INSTALL)
EA 4.000 $6,000.000 $2,800.000 $5,500.000 $4,210.000 $5,737.500 $5,000.000 $4,500.000 $3,750.000
GUARDRAIL END TREATMENT (REMOVE)
EA 4.000 $460.000 $250.000 $550.000 $401.000 $765.000 $600.000 $800.000 $700.000
INSTL DEL ASSM (D-SW)SZ 1(WFLX)GF2(BI)
EA 10.000 $50.000 $37.000 $55.000 $30.000 $89.250 $200.000 $75.000 $50.000
DRIFTWOOD REMOVAL AREA (1)
LS 1.000 $100.000 $2,000.000 $5,500.000 $4,500.000 $12,750.000 $5,000.000 $5,000.000 $1,500.000
CNC CRACK REPAIR (DISCRETE)(INJECT)
LF 2.000 $400.000 $500.000 $550.000 $255.000 $89.250 $2,300.000 $500.000 $500.000
CONC CRCK REPR(DISCRETE)(ROUT AND SEAL)
LF 747.000 $80.000 $50.000 $77.000 $54.000 $44.630 $33.000 $38.000 $50.000
BRIDGE JOINT REPAIR (CONCRETE)
LF 92.000 $350.000 $200.000 $770.000 $475.000 $382.500 $380.000 $450.000 $650.000
BRIDGE JOINT REPLACEMENT (CONCRETE)
LF 260.000 $600.000 $200.000 $550.000 $780.000 $446.250 $562.000 $600.000 $825.000
BRIDGE JOINT REPLACEMENT (HEADER)
LF 40.000 $700.000 $400.000 $440.000 $500.000 $573.750 $550.000 $400.000 $267.000
CARBON FIBER REINF POLYMER STRENGTHNING
SF 5.000 $180.000 $250.000 $220.000 $650.000 $51.000 $2,000.000 $800.000 $1,000.000
Totals: $861,118.000 $555,941.000 $681,375.000 $778,377.000 $830,733.810 $857,040.500 $877,926.000 $914,108.000