EL PASO IH0010 (6455-25-001)

Items: 30

County: EL PASO
Length: N/A
Highway: IH0010
District: EL PASO
Control Number: 6455-25-001
DBE Goal: 0.0%
Project: RMC - 645525001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $1,139,700.00
Date: 12/05/2023 (2 years ago)
Contract Number: N/A
Type: MISCELLANEOUS CONCRETE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Bidders (4)
E
Engineer's Estimate
$1,139,700.00
$1,129,614.00
Over/Under Est: -0.88% -$10,086.00
$1,151,950.00
Over/Under Est: 1.07% $12,250.00
Amt Left: 1.98% $22,336.00
Over/Under Est: 13.06% $148,800.00
Amt Left: 14.07% $158,886.00
Delta: -11.85% -$136,550.00
$1,585,760.00
Over/Under Est: 39.14% $446,060.00
Amt Left: 40.38% $456,146.00
Delta: -23.07% -$297,260.00

Bid Items & Bid Tabulations

30 Total 0 of 30
EL PASO  |  IH0010  |  EL PASO  |  6455-25-001  |  12/05/2023  |  $1,139,700.00  |  RMC - 645525001  |  MISCELLANEOUS CONC REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
SYNERGY PROJECT CONTRACTORS, INC.
HAWK CONSTRUCTION
INTERNATIONAL EAGLE ENTERPRISES, INC.
ALLEN CONCRETE, LLC
REMOVING CONC (RIPRAP)
SY 600.000 $40.000 $36.580 $40.000 $75.000 $47.000
REMOVING CONC (CURB)
LF 1,000.000 $13.000 $11.800 $32.000 $12.000 $33.000
REMOVE CONC (WINGWALL)
CY 10.000 $200.000 $236.000 $375.000 $500.000 $1,040.000
REMOVING CONC (MISC)
SY 2,000.000 $40.000 $20.060 $44.000 $35.000 $32.000
REMOVING CONC (HEADWALL)
CY 10.000 $200.000 $153.400 $375.000 $500.000 $520.000
REMOVE CONC (RAIL)
LF 250.000 $70.000 $70.800 $50.000 $40.000 $78.000
EMBANKMENT (FINAL)(DENS CONT)(TY A)
CY 50.000 $100.000 $47.200 $52.000 $150.000 $334.000
FLOWABLE BACKFILL
CY 40.000 $220.000 $206.500 $500.000 $200.000 $437.000
CL A CONC (MISC)
SY 800.000 $200.000 $88.500 $137.000 $60.000 $63.000
CL C CONC (HEADWALL)
CY 5.000 $2,200.000 $708.000 $2,800.000 $1,500.000 $1,560.000
CL C CONC (WINGWALLS)
CY 5.000 $2,200.000 $1,416.000 $2,800.000 $2,000.000 $1,560.000
CONCRETE PAINT FINISH
SF 200.000 $12.500 $35.400 $36.000 $15.000 $89.000
CONC STR REPAIR(RAPID DECK REP(PRT DPT)
SF 200.000 $300.000 $365.800 $123.000 $250.000 $327.000
CONC STR REPR(RAPID DECK REP(FULL DPT))
SF 400.000 $400.000 $519.200 $150.000 $400.000 $445.000
CONC STR REPAIR (VERTICAL & OVERHEAD)
SF 50.000 $240.000 $342.200 $215.000 $500.000 $416.000
CONC STR REPR(RAPID VERT AND OVERHEAD)
SF 150.000 $400.000 $436.600 $215.000 $400.000 $292.000
CONC STR REPAIR (STANDARD)
SF 500.000 $300.000 $413.000 $138.000 $275.000 $356.000
RIPRAP (CONC)(CL B)
CY 150.000 $450.000 $472.000 $850.000 $600.000 $780.000
RAIL (TY T402)
LF 250.000 $200.000 $159.300 $445.000 $600.000 $312.000
RAIL (TY C402)
LF 250.000 $200.000 $159.300 $445.000 $600.000 $300.000
MOBILIZATION
LS 1.000 $40,000.000 $70,800.000 $30,000.000 $100,000.000 $249,600.000
PERM CTB (F-SHAPE) (TY 1)
LF 200.000 $200.000 $112.100 $305.000 $150.000 $193.000
CONC CURB (MONO) (TY II)
LF 1,000.000 $30.000 $24.780 $40.000 $15.000 $28.000
CONC CURB & GUTTER (TY II)
LF 30.000 $100.000 $53.100 $40.000 $70.000 $260.000
CONC SIDEWALKS (4")
SY 200.000 $75.000 $87.320 $98.000 $75.000 $100.000
CURB RAMPS (SPECIAL)
SY 15.000 $300.000 $295.000 $2,000.000 $1,800.000 $520.000
CONNECTOR PLATE FOR THRIE BEAM
EA 4.000 $1,500.000 $1,416.000 $3,800.000 $4,500.000 $2,600.000
CONCRETE RAIL REPAIR (TYPE 551)
LF 50.000 $140.000 $277.300 $325.000 $120.000 $728.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 20.000 $120.000 $112.100 $110.000 $120.000 $884.000
TMA (STATIONARY)
DAY 130.000 $350.000 $395.300 $450.000 $150.000 $1,040.000
Totals: $1,139,700.000 $1,129,614.000 $1,151,950.000 $1,288,500.000 $1,585,760.000