EL PASO IH0010 (6421-87-001)

Items: 31

County: EL PASO
Length: N/A
Highway: IH0010
District: EL PASO
Control Number: 6421-87-001
DBE Goal: N/A
Project: RMC - 642187001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $973,645.00
Date: 11/02/2022 (3 years ago)
Contract Number: N/A
Type: MISCELLANEOUS CONCRETE REPAIR
Mail/Deliver Bids To: N/A
MONICA DUBRULE
Actions:
Notice HCS Excel Tabs Print Print Notice
Documents:
Bidders (3)
E
Engineer's Estimate
$973,645.00
Over/Under Est: -0.53% -$5,145.00
Over/Under Est: 14.28% $139,032.50
Amt Left: 14.89% $144,177.50
Over/Under Est: 39.01% $379,820.00
Amt Left: 39.75% $384,965.00
Delta: -21.64% -$240,787.50

Bid Items & Bid Tabulations

31 Total 0 of 31
EL PASO  |  IH0010  |  EL PASO  |  6421-87-001  |  11/02/2022  |  $973,645.00  |  RMC - 642187001  |  MISCELLANEOUS CONC REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
INTERNATIONAL EAGLE ENTERPRISES, INC.
B & MS CONSTRUCTION, INC.
SYNERGY PROJECT CONTRACTORS, INC.
REMOVING CONC (RIPRAP)
SY 300.000 $35.000 $36.000 $45.000 $27.360
REMOVING CONC (CURB)
LF 2,000.000 $7.000 $5.000 $8.500 $5.700
REMOVE CONC (WINGWALL)
CY 10.000 $225.000 $200.000 $85.000 $148.200
REMOVING CONC (MISC)
SY 1,000.000 $25.000 $18.000 $38.000 $20.520
REMOVING CONC (HEADWALL)
CY 10.000 $215.000 $200.000 $85.000 $193.800
REMOVE CONC (RAIL)
LF 15.000 $80.000 $100.000 $26.000 $68.400
FLOWABLE BACKFILL
CY 20.000 $225.000 $220.000 $345.000 $336.300
CL A CONC (MISC)
SY 1,500.000 $105.000 $70.000 $195.000 $125.400
CL C CONC (HEADWALL)
CY 5.000 $665.000 $500.000 $540.000 $684.000
CL C CONC (WINGWALLS)
CY 15.000 $800.000 $500.000 $540.000 $712.500
CONC STR REPR(RAPID DECK REP(FULL DPT))
SF 105.000 $310.000 $300.000 $287.000 $370.500
CONC STR REPR(RAPID VERT AND OVERHEAD)
SF 1,200.000 $280.000 $300.000 $195.000 $513.000
CONC STR REPAIR (STANDARD)
SF 300.000 $280.000 $300.000 $200.000 $353.400
RIPRAP (CONC)(CL B)
CY 60.000 $435.000 $400.000 $540.000 $513.000
RAIL (HANDRAIL)(TY A)
LF 20.000 $215.000 $250.000 $190.000 $541.500
MOBILIZATION
LS 1.000 $34,000.000 $45,000.000 $75,000.000 $45,600.000
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 50.000 $13.000 $10.000 $11.500 $99.180
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 50.000 $15.000 $10.000 $57.500 $11.400
PORT CONC TRAF BAR (STKPL,INSTL&RETRN)
LF 50.000 $30.000 $10.000 $74.750 $13.680
CONC CURB (MONO) (TY II)
LF 2,000.000 $25.000 $26.000 $23.000 $27.360
CONC CURB & GUTTER (TY II)
LF 30.000 $50.000 $50.000 $74.750 $51.300
CONC SIDEWALKS (4")
SY 800.000 $70.000 $65.000 $78.000 $75.240
CURB RAMPS (SPECIAL)
SY 10.000 $200.000 $200.000 $350.000 $256.500
CRASH CUSH ATTEN (DES SOURCE)
EA 1.000 $2,000.000 $2,000.000 $1,700.000 $2,280.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 1.000 $1,500.000 $1,200.000 $920.000 $1,710.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $2,000.000 $1,200.000 $690.000 $1,596.000
CRASH CUSHION ATTEN (INSTALL) (TRACC)
EA 1.000 $30,000.000 $32,000.000 $57,000.000 $45,030.000
CONCRETE RAIL REPAIR (TYPE 551)
LF 25.000 $150.000 $80.000 $172.500 $205.200
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 20.000 $81.000 $45.000 $650.000 $96.900
TMSP RADAR SPEED CONTROL MONITOR
EA 1.000 $1,000.000 $1,000.000 $12,600.000 $912.000
TMA (MOBILE OPERATION)
HR 1,000.000 $70.000 $100.000 $85.000 $68.400
Totals: $973,645.000 $968,500.000 $1,112,677.500 $1,353,465.000