Show Job Controls
Bid Cobra

EL PASO IH0010 (6363-58-001)

Items: 30

County: EL PASO
Length: N/A
Highway: IH0010
District: EL PASO
Control Number: 6363-58-001
DBE Goal: N/A
Project: RMC - 636358001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $309,294.73
Date: 09/03/2020 (5 years ago)
Contract Number: N/A
Type: MISCELLANEOUS CONCRETE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$309,294.73
$363,194.00
Over/Under Est: 17.43% $53,899.27
Over/Under Est: 18.86% $58,321.07
Amt Left: 1.22% $4,421.80
Over/Under Est: 20.83% $64,430.27
Amt Left: 2.9% $10,531.00
Delta: -1.66% -$6,109.20
Over/Under Est: 52.88% $163,555.27
Amt Left: 30.19% $109,656.00
Delta: -26.52% -$99,125.00

Bid Items & Bid Tabulations

30 Total 0 of 30
EL PASO  |  IH0010  |  EL PASO  |  6363-58-001  |  09/03/2020  |  $309,294.73  |  RMC - 636358001  |  MISCELLANEOUS CONC REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
E. G. L. CONSTRUCTION, INC.
SYNERGY PROJECT CONTRACTORS, INC.
INTERNATIONAL EAGLE ENTERPRISES, INC.
DOUBLE H CONTRACTING INC.
REMOVING CONC (RIPRAP)
SY 400.000 $20.840 $15.000 $34.200 $35.000 $60.000
REMOVING CONC (CURB)
LF 2,000.000 $4.860 $8.000 $3.420 $5.000 $20.000
REMOVE CONC (WINGWALL)
CY 10.000 $138.920 $300.000 $342.000 $200.000 $500.000
REMOVING CONC (MISC)
SY 400.000 $27.780 $30.000 $20.520 $18.000 $60.000
REMOVING CONC (HEADWALL)
CY 5.000 $166.700 $190.000 $193.800 $200.000 $500.000
REMOVE CONC (RAIL)
LF 10.000 $34.730 $26.000 $11.400 $100.000 $150.000
FLOWABLE BACKFILL
CY 40.000 $173.650 $168.000 $114.000 $200.000 $150.000
CL A CONC (MISC)
SY 520.000 $138.920 $188.000 $172.140 $90.000 $100.000
CL C CONC (HEADWALL)
CY 5.000 $1,291.920 $830.000 $741.000 $500.000 $700.000
CL C CONC (WINGWALLS)
CY 5.000 $1,389.170 $1,123.000 $855.000 $500.000 $700.000
CONC STR REPR(RAPID DECK REP(FULL DPT))
SF 140.000 $55.570 $107.000 $256.500 $350.000 $200.000
CONC STR REPAIR (STANDARD)
SF 120.000 $125.020 $129.000 $79.800 $300.000 $200.000
RIPRAP (CONC)(CL B)
CY 80.000 $486.210 $371.000 $387.600 $380.000 $700.000
RAIL (HANDRAIL)(TY A)
LF 40.000 $138.920 $98.000 $136.800 $250.000 $200.000
MOBILIZATION
LS 1.000 $5,000.000 $45,000.000 $17,100.000 $30,000.000 $45,000.000
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 100.000 $20.840 $40.000 $17.100 $10.000 $15.000
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 100.000 $6.950 $40.000 $6.840 $10.000 $15.000
PORT CONC TRAF BAR (STKPL,INSTL&RETRN)
LF 100.000 $34.730 $40.000 $26.220 $10.000 $15.000
CONC CURB (MONO) (TY II)
LF 2,000.000 $13.890 $7.870 $17.100 $25.000 $30.000
CONC CURB & GUTTER (TY II)
LF 20.000 $27.780 $23.000 $28.500 $50.000 $80.000
CONC SIDEWALKS (4")
SY 50.000 $83.350 $46.000 $51.300 $70.000 $80.000
CURB RAMPS (SPECIAL)
SY 5.000 $180.590 $245.000 $2,052.000 $200.000 $350.000
CRASH CUSH ATTEN (DES SOURCE)
EA 1.000 $2,778.330 $1,125.000 $4,560.000 $2,000.000 $3,500.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 1.000 $1,875.370 $2,570.000 $3,192.000 $1,200.000 $3,500.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $1,389.170 $904.000 $1,368.000 $1,200.000 $2,000.000
CRASH CUSHION ATTEN (INSTALL) (TRACC)
EA 1.000 $30,561.660 $17,500.000 $17,955.000 $25,000.000 $20,000.000
CONCRETE RAIL REPAIR (TYPE 551)
LF 50.000 $208.370 $105.000 $513.000 $80.000 $450.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 15.000 $130.000 $107.000 $342.000 $95.000 $100.000
TMSP RADAR SPEED CONTROL MONITOR
EA 1.000 $4,100.000 $15,000.000 $4,560.000 $8,000.000 $5,000.000
TMA (MOBILE OPERATION)
HR 400.000 $50.000 $65.000 $45.600 $55.000 $50.000
Totals: $309,294.730 $363,194.000 $367,615.800 $373,725.000 $472,850.000