Show Job Controls
Bid Cobra

EL PASO IH0010 (6363-57-001)

Items: 30

County: EL PASO
Length: N/A
Highway: IH0010
District: EL PASO
Control Number: 6363-57-001
DBE Goal: N/A
Project: RMC - 636357001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $379,751.83
Date: 09/03/2020 (5 years ago)
Contract Number: N/A
Type: MISCELLANEOUS CONCRETE REPAIR
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (3)
E
Engineer's Estimate
$379,751.83
Over/Under Est: 28.05% $106,528.17
Over/Under Est: 28.99% $110,098.17
Amt Left: 0.73% $3,570.00
Over/Under Est: 32.41% $123,067.77
Amt Left: 3.4% $16,539.60
Delta: -2.65% -$12,969.60

Bid Items & Bid Tabulations

30 Total 0 of 30
EL PASO  |  IH0010  |  EL PASO  |  6363-57-001  |  09/03/2020  |  $379,751.83  |  RMC - 636357001  |  MISCELLANEOUS CONC REPAIR  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
INTERNATIONAL EAGLE ENTERPRISES, INC.
DOUBLE H CONTRACTING INC.
SYNERGY PROJECT CONTRACTORS, INC.
REMOVING CONC (RIPRAP)
SY 600.000 $20.210 $40.000 $50.000 $22.000
REMOVING CONC (CURB)
LF 2,000.000 $4.720 $5.000 $15.000 $5.000
REMOVE CONC (WINGWALL)
CY 10.000 $134.770 $200.000 $500.000 $456.000
REMOVING CONC (MISC)
SY 500.000 $26.950 $18.000 $50.000 $10.000
REMOVING CONC (HEADWALL)
CY 10.000 $161.720 $200.000 $500.000 $199.500
REMOVE CONC (RAIL)
LF 30.000 $33.690 $100.000 $50.000 $26.220
FLOWABLE BACKFILL
CY 40.000 $168.460 $220.000 $150.000 $246.500
CL A CONC (MISC)
SY 780.000 $134.770 $90.000 $90.000 $200.000
CL C CONC (HEADWALL)
CY 5.000 $1,253.320 $500.000 $700.000 $1,425.000
CL C CONC (WINGWALLS)
CY 5.000 $1,347.650 $500.000 $700.000 $1,425.000
CONC STR REPR(RAPID DECK REP(FULL DPT))
SF 210.000 $53.910 $400.000 $175.000 $319.200
CONC STR REPAIR (STANDARD)
SF 180.000 $121.290 $300.000 $175.000 $75.000
RIPRAP (CONC)(CL B)
CY 120.000 $471.680 $380.000 $500.000 $510.000
RAIL (HANDRAIL)(TY A)
LF 40.000 $134.770 $250.000 $200.000 $156.000
MOBILIZATION
LS 1.000 $5,000.000 $30,000.000 $40,000.000 $5,000.000
PORT CTB (DES SOURCE)(F-SHAPE)(TY 1)
LF 100.000 $20.210 $10.000 $15.000 $28.500
PORT CTB (MOVE)(F-SHAPE)(TY 1)
LF 100.000 $6.740 $10.000 $15.000 $9.120
PORT CONC TRAF BAR (STKPL,INSTL&RETRN)
LF 100.000 $33.690 $10.000 $15.000 $28.500
CONC CURB (MONO) (TY II)
LF 1,500.000 $13.480 $26.000 $25.000 $20.000
CONC CURB & GUTTER (TY II)
LF 30.000 $26.950 $50.000 $75.000 $57.000
CONC SIDEWALKS (4")
SY 50.000 $80.860 $70.000 $75.000 $68.400
CURB RAMPS (SPECIAL)
SY 10.000 $175.200 $200.000 $300.000 $342.000
CRASH CUSH ATTEN (DES SOURCE)
EA 1.000 $2,695.310 $2,000.000 $3,500.000 $4,332.000
CRASH CUSH ATTEN (MOVE & RESET)
EA 1.000 $1,819.330 $1,200.000 $3,500.000 $2,622.000
CRASH CUSH ATTEN (REMOVE)
EA 1.000 $1,347.650 $1,200.000 $2,000.000 $1,140.000
CRASH CUSHION ATTEN (INSTALL) (TRACC)
EA 1.000 $29,648.390 $25,000.000 $19,500.000 $18,810.000
CONCRETE RAIL REPAIR (TYPE 551)
LF 50.000 $202.150 $80.000 $400.000 $399.000
PORTABLE CHANGEABLE MESSAGE SIGN
DAY 24.000 $130.000 $95.000 $100.000 $228.000
TMSP RADAR SPEED CONTROL MONITOR
EA 1.000 $4,100.000 $8,000.000 $5,000.000 $4,560.000
TMA (MOBILE OPERATION)
HR 600.000 $50.000 $60.000 $45.000 $53.580
Totals: $379,751.830 $486,280.000 $489,850.000 $502,819.600