Show Job Controls
Bid Cobra

EL PASO IH0010 (6339-71-001)

Items: 25

County: EL PASO
Length: N/A
Highway: IH0010
District: EL PASO
Control Number: 6339-71-001
DBE Goal: N/A
Project: RMC - 633971001
Guaranty: N/A
Time: 365 CALENDAR DAYS
Engineer's Estimate: $440,200.00
Date: 01/08/2019 (7 years ago)
Contract Number: N/A
Type: BARRICADES, SIGNS AND TRAFFIC CONTROL
Mail/Deliver Bids To: N/A
SEE PLANS OR PROPOSAL BOOK
Actions:
Notice HCS Excel Tabs Print Print Notice
Pay Estimates:
Bidders (4)
E
Engineer's Estimate
$440,200.00
$417,400.00
Over/Under Est: -5.18% -$22,800.00
$430,110.00
Over/Under Est: -2.29% -$10,090.00
Amt Left: 3.05% $12,710.00
Over/Under Est: -2.04% -$8,975.00
Amt Left: 3.31% $13,825.00
Delta: -0.26% -$1,115.00
Over/Under Est: 28.73% $126,487.20
Amt Left: 35.77% $149,287.20
Delta: -31.41% -$135,462.20

Bid Items & Bid Tabulations

25 Total 0 of 25
EL PASO  |  IH0010  |  EL PASO  |  6339-71-001  |  01/08/2019  |  $440,200.00  |  RMC - 633971001  |  BARRICADES, SIGNS AND TRAF CONTROL  |  365 CALENDAR DAYS
Item Code
Description
Unit
Quantity
Engineer's Estimate
APACHE BARRICADE & SIGN
NIXON ENGINEERING
LESNA CONSTRUCTION, INC.
SYNERGY PROJECT CONTRACTORS, INC.
MOBILIZATION
LS 1.000 $10,000.000 $500.000 $10,000.000 $5,000.000 $19,929.480
PORT CONC TRAF BAR (STKPL,INSTL&RETRN)
LF 200.000 $60.000 $20.000 $10.000 $60.000 $59.830
CRASH CUSH ATTEN (INSTL)
EA 2.000 $9,000.000 $12,000.000 $100.000 $9,000.000 $17,328.000
CRASH CUSH ATTEN (DES SOURCE)
EA 2.000 $500.000 $1,200.000 $100.000 $500.000 $1,487.700
TMSP RADAR SPEED CONTROL MONITOR
EA 2.000 $2,000.000 $500.000 $10.000 $3,000.000 $779.760
TMA (MOBILE OPERATION)
HR 6,000.000 $60.000 $54.000 $65.000 $58.000 $70.680
1 LN CLOSURE 2 LN RD NO SHOULDERS
HR 75.000 $55.000 $65.000 $50.000 $60.000 $105.060
1 LN CLOSURE 2 LN RD PAVED SHOULDERS
HR 20.000 $55.000 $65.000 $20.000 $90.000 $108.300
1 LN CLOSURE 4 LN RD
HR 50.000 $55.000 $65.000 $50.000 $60.000 $136.060
2 LN CLOSURE 4 LN RD
HR 30.000 $55.000 $65.000 $1.000 $60.000 $148.200
FREEWAY 1 LANE CLOSURE
HR 150.000 $65.000 $140.000 $100.000 $90.000 $138.080
FREEWAY 2 LANE CLOSURE
HR 10.000 $65.000 $475.000 $1.000 $130.000 $201.630
FREEWAY 3 LANE CLOSURE
HR 10.000 $75.000 $475.000 $1.000 $160.000 $192.230
EXIT OR ENTRANCE RAMP CLOSURE
HR 75.000 $35.000 $25.000 $20.000 $37.000 $95.760
FREEWAY CLOSURE SEQUENCE DAYTIME ONLY
HR 10.000 $150.000 $150.000 $20.000 $175.000 $239.400
COMPLETE FREEWAY CLOSURE
HR 20.000 $250.000 $550.000 $30.000 $150.000 $325.610
ONE LANE FRONTAGE ROAD CLOSURE
HR 10.000 $55.000 $75.000 $1.000 $60.000 $68.400
TWO LANE FRONTAGE ROAD CLOSURE
HR 10.000 $55.000 $75.000 $1.000 $60.000 $138.080
ONE LANE CONNECTING RAMP CLOSURE
HR 10.000 $60.000 $75.000 $1.000 $60.000 $114.000
TWO LANE CONNECTING RAMP CLOSURE
HR 10.000 $60.000 $75.000 $1.000 $60.000 $187.380
WORK AREA ON SHOULDER
HR 20.000 $40.000 $20.000 $150.000 $90.000 $79.800
TURN AROUND CLOSURE
HR 20.000 $40.000 $20.000 $20.000 $40.000 $90.770
FURNISH ADDITIONAL FLAGGER
HR 10.000 $40.000 $65.000 $10.000 $40.000 $29.930
PILOT VEHICLE AND OPERATOR
HR 10.000 $50.000 $75.000 $10.000 $70.000 $38.330
FURNISH ADDITIONAL ARROW BOARD
HR 10.000 $50.000 $5.000 $5.000 $10.000 $31.490
Totals: $440,200.000 $417,400.000 $430,110.000 $431,225.000 $566,687.200